MODERATE RISK WASTE FACILITY DESIGN EVOLUTION AT KING COUNTY James Neely NAHMMA 2012 Northwest Conference
2
PART ONE: PILOT HHW FACILITY MADE SEMI-PERMANENT
3
Factoria Transfer Station Pre-Development 2001
4
Pilot MRW Facility Opened Sept. 2002
7
Failure of Retractable Awning
9
2004: Pilot to Semi-Permanent Facility
10
INITIAL RESULTS
11
BE PREPARED FOR THE EXOTICS
12
CONSIDER OUTDOOR STORAGE NEEDS Type 4 Outdoor Explosives Magazine for Marine Flares
13
PART TWO: FINALLY A REAL FACILITY
14
REBUILT FACTORIA TRANSFER STATION AND MODERATE RISK WASTE FACILITY Opening Planned for 2015
15
DESIGN CONSIDERATIONS SUMMARY Size Ventilation and Fire Safety Ergonomics/Self Service Opportunities To Bulk or Not to Bulk Green Building Employee Comfort
16
CONCEPTUAL DESIGN
17
LOCAL EXHAUST VENTILATION
18
DIRECT VENTILATION- BEST