Download presentation
Presentation is loading. Please wait.
Published byDorcas Crawford Modified over 9 years ago
1
Stanford Linear Accelerator Center Next Linear Collider Test Accelerator EPICS Support S. Allison, R. Chestnut, M. Clausen, K. Luchini
2
Our Problem DM, MEDM, DM2K, StripTool and Matlab screens served by different hosts onto the same head. VMS and Unix/Legacy system and Epics in the mix. Need to manage host processes AND displays on single heads.
3
Stanford Linear Accelerator Center Next Linear Collider Test Accelerator and EPICS PSI Epics Meeting May, 2001 S. Allison, R. Chestnut, M. Clausen, K. Luchini
4
Current NLCTA Controls Originally an EPICS target Mixture of SLC, Labview, Veetest Slow (1/2 Hertz control) Two structures with two klystrons each “Process” structures to show feasibility/durability for NLC Desire to run without operators present
5
What’s the big deal? Structures are critical for NLC design Results are pivotal for the NLC cotillion at Snowmass Current intense involvement by a diagnostics group SWAT team Current intense scrutiny by management
6
Drive 1 Drive 2 Klys Out Sled RE1 FE1 Load1 RE2 FE2 Load2 These measurement points correspond to the variables mentioned in the briefing. These are in Joules, and are the integral over the RF pulse. NLCTA RF Processing Layout
7
The move to EPICS Slow IOC (MV177) — Alan Bradley — VSAM Fast IOC (MVME 2700) — ADC signals — TDC signals — DAC control — Digital I/O
8
Slow IOC Alan Bradley interface to move from Veetest to Epics Prying details from PLC programmers Lots of signals – the devil is in the details Work well under way, with many details remaining
9
Fast IOC 60 (or 120 Hz) operation New (for us) integrating ADC, TDC, DAC and digital I/O support New (for us) Power PC Requirements specify pulse by pulse monitor and control of structure processing
10
Fast IOC Hardware MVME 2700 Power PC Caen V265 Gated ADC (3) Lecroy 1176 TDC VMIC 2534 32-bit Digital I/O VMIC 4100 12-bit D/A Joerger VTR812 12-bit digitizer (later)
11
Fast IOC fast loop Read in 20 ADC signals and 6 TDC signals Perform limit checks on various power measurements Disable on one felony OR two parole violations in quick succession Provide ring buffers for off-line analysis All of the above synchronized on each pulse
12
Fast ADC and “PIOP” records One ADC interrupts; other records fired by events; whole fast loop is one lockset. One “ADC” record for each module Quadratic conversion per channel Circular buffers built in
13
Fast ADC Record FE1 8 HW Inputs 120 Hz Per Channel: Signal in Joules N-sec circ. buffer 8x3 conversion coefficients Load1 ……
14
Fast ADC and “PIOP” records One “PIOP” record per structure – not 1-to-1 with ADC records. “PIOP” record has 20 or so db links to hard- coded PVs. One ADC and one PIOP at 60 Hz take 6% of the MV177 Seems to take about.0016 seconds per loop.
15
“PIOP” subroutine record Inputs: 9( or maybe12) converted ADC signals + limits 120 Hz Functioning: Calculate NORM, LOST Check for warning/error Drive GO/NOGO digital output
16
Fast IOC asynchronous fast code Implement re-enabling strategies for different failure modes Watch vacuums and other relevant data Can also trip off on vacuum All of the above fast, but asynchronous to the pulse-by-pulse flow
17
Next Milestones May 7 – have local testing done; ready to move equipment down to NLCTA. May 15 – next run starts; be ready to run parasitically June 29 – Current structures at end of life; Snowmass; cut over to Epics as primary system.
18
The other 20% Displays (many) Infrastructure (save/restore, archiver, configs, CUDs, StripTool, SIP, SCP support, alarm logging) Testing – modules, drivers, and fast, synchronous software Matlab support (offline event analysis)
19
The really big deal Data storage for archiving (Network layout, computer center role, etc.) Faster machines (additional load!) NLCTA could keep a fast Sun busy AND fill any space we can give them.
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.