Download presentation
Presentation is loading. Please wait.
Published byGriselda McDaniel Modified over 9 years ago
1
Modern Building: Green Library Eric Strafelda Tyler Mitchell Jordan Timmersman
2
NDSU Modern Building 300,000 sqft (3x the size of the current library) Site location: East of Memorial Union 6 floors Two roof areas that allow for solar panel Allows for sunlight to be utilized fully
3
Requirements Electrical Engineering Design – Blue Prints Electrical Engineering Specifications Electrical Engineering Studies Solar Roof Study
4
Meeting with Architect We met with the architect and got the AutoCAD drawings form him. He wanted the building to be as green as possible Wanted us to design for the following: Efficiency Cost Light Quality
5
Meeting with NDSU Facilities We talked with Brent Dekrey about seeing what the current library has in it. Library is provided heat from steam plant Has a 1200A service Needed to have chillers and air handling units in our calculation for new library. Roughly 100,000 sqft Has a 100 kW backup generator
6
Service Sizing Calculations Receptacle Loading: All loading is unknown for our building so we assumed a 1 VA per square foot 1VA*1VA*300,000sqft = 300,000VA General Lighting: All lighting is unknown for our building so we assumed a 3.5 VA per square foot 3.5 VA was found in code book Sec. 220.12 3.5VA*300,000sqft = 1,050,000VA
7
Service Sizing Calculations Lighting Demand Factor: Most of your lighting loads are considered to be a continuous load 25%*General Lighting Load = 262,500 VA
8
Service Sizing Calculations Motor/Mechanical Loads 1 CFM per sq ft and 340 sq ft per ton of coolant With 300,000 sq ft over 6 floors that is 50,00 sq ft per floor. With 1000 ton chiller. 1000 ton chiller = 3500 kW (6) 50,000 Air Handling Units (AHU) 2 motors rated at 75 hp motors 6 150 hp motors for AHU’s
9
Service Sizing Calculations Combining Motor/Mechanical Loads According to NEC section 440.7 you use 125% of your highest rated motor and then face value for all other loads. 150 hp X 746 W/hp X125%=140,000 W 5 X 150 hp X 746 W/hp=560,000 W 3500 kW for the chiller Total Motor Load of 700 kW
10
Service Sizing Calculations Combing all the numbers previously found. Total VA=2,312,500 VA=V*I*1.73 V=480V A=2,786.14 Using NEC section 240.6 We selected a service size of 3000 Amps
11
PV Economic Study One of our major objectives in this project was to be able to work with an outside client such as an architect. Our client asked us to provide an economic study to see if installing a photovoltaic array would be a wise investment.
14
PV Payback Analysis Solar Cash Flow Projection NDSU Modern Building Project Cash Flow AssumptionsIncentive AssumptionsFinancial Performance Installed Capacity DCkW342Fair Market Value$/watt 4.00Unlevered IRR3.61% DC/AC Derate%83%Tax Rate35.00%Payback Period 13.32 Installed Capacity ACkW283.86Federal/State ITC45% System Capacity Factor%16.8206%Depreciation basis85% Annual GenerationkWh 418,264Cost basis 1,368,000 Annual System Derate%0.50%Bonus Depreciation50% Solar PPA Rate$/kWh0.067Depreciable Basis 1,162,800 Utility Escalation Rate%2.50%Bonus Depreciation 581,400 Utility Incentive$/kWh0Ongoing Depreciation 581,400 System Cost$/watt 4.00 Annual O&M$/kW 20.00 MACRS Schedule20.00%32.00%19.20%11.52% 5.76%
15
PV Fringe Benefits Some Fringe Benefits that are not related to direct energy cost analysis include: Educational Thermal Demand Savings Power Quality Utility Buyback Environmental Public Perception
16
PV Analysis Conclusion Given the warranty/useful life a PV array is 20 years. The 13.32 payback period is very favorable Including the 3.61 return on investment along with all fringe benefits. We would recommend the inclusion of a PV array atop our modern building
17
Project Status We have successfully completed the deliverables for the first semester. We had to do a little rearranging of our schedule and an updated timeline is on the following slide.
18
Timeline
19
Budget ItemQty.CostTotalPurchase Price 2011 NEC Code3$90$2703 @ $75 = 225 AutoCAD MEP1$200 Plotting$125 TOTAL$595$225.00$370
20
Summary Using the NEC code book and information gathered from campus administrators we were able to select a service size of 3000A Using engineering economic analysis we were able to accurately predict the cost of a PV Array installation and recommend its inclusion. We are still on track to deliver our completed project next semester.
21
Questions?
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.