Saverio MINUTOLITOTEM T1 Readiness Review, 30 November 20101 Readiness Report on T1 Electrical Systems and Electronics
2
Saverio MINUTOLI Summary Readiness of all systems Response on change requests from ESR in September QA/QC, including test during and after installation with requests of necessary infrastructure TOTEM T1 Readiness Review, 30 November 20102
3
Saverio MINUTOLI3 T1 is composed by 2 arms Each arm is composed by 5 planes Each plane is composed by 6 CSC trapezoidal chambers Each chamber is composed by 1 anode and 2 cathode planes For mechanical reasons, each arm is divided into two halves : each half is considered independent from the other also from electrical/logical point of view In total, each halve include 15 chambers Overview of T1 detector TOTEM T1 Readiness Review, 30 November 2010
4
Saverio MINUTOLITOTEM T1 Readiness Review, 30 November 20104 T1 detector in H8
5
Saverio MINUTOLI5 T1 functional electronics system architecture TOTFED CSC Detectors AFECs CFECs S-bit DataOut Clk40 FastCmd I 2 C 40÷100 cm LVDS CMOS LVDS CMOS PLL25 QPLL T1 Tree CLK40 Tree SPY Mezz CCUM DCU GOHs GOH VFAT TrgMez DDAV MUX TDAV MUX VFAT CMOS LVDS ROC TOTFED TTCRx OPTORx FEC DOHM DOHs TTCRx mFEC Trigger bits Data bits Data to DAQ (S-Link; VME; or USB) Trigger Info Readout Path Control Path TTC TOTEM Slow Control On Detector region Local Detector region Counting Room region TokenRingTokenRing 4 x 15 Det4 x 15 AFEC + 4 x 39 CFEC4 x 9 ROC2T + 2D + 4mFEC= 4 x T1 ¼4 x 1 DOHM TOTEM T1 Readiness Review, 30 November 2010
6
Saverio MINUTOLI6 1 2 3 4 5 5 5 4 4 3 3 2 2 1 1 T T T M M M B B B = CSC = ROC ROCs 45 ROCs 23 ROCs 01 = IP5 6 th frame DOHM = DOHM C C C C C C C C C C C C C C C = CFEC A A A A A A A A A A A A A A A = AFEC ¼ T1 electronic boards placement TOTEM T1 Readiness Review, 30 November 2010
7
Saverio MINUTOLI7 ¼ T1 at the CERN lab. B188 TOTEM T1 Readiness Review, 30 November 2010
8
Saverio MINUTOLI Summary Readiness of all systems Response on change requests from ESR in September QA/QC, including test during and after installation with requests of necessary infrastructure TOTEM T1 Readiness Review, 30 November 20108
9
T1 Low Voltage system MARATON Power Box NearFar - + MARATON Primary Rectifier -N-F+N+F MARATON Remote Controller -n-f+n+f Distribution Box 6° frame MARATON Power Box Distribution Box 6° frame On platform ¼ T1 2 x 4 ; 36 wires shielded cables, to MARATON Power Box Control Room Saverio MINUTOLI9 TOTEM T1 Readiness Review, 30 November 2010 FUSE Box Vsense Box FUSE Box Vsense Box FUSE Box Vense Box FUSE Box Vense Box On platform
10
Saverio MINUTOLI LV OPFCs electrical connections TOTEM T1 Readiness Review, 30 November 201010 Each T1 quarter is powered independently. 4 electro-mechanic breakers installed Tested and deployed within DSS. Electrical drawing updated OPFCs AC input and DC output tested 3 OPFCs already installed 4 th currently used in H8 1 OPFC spare at the B188 (electronic boards test bench). 385V DC connections tested on both sides (rack and platform).
11
Saverio MINUTOLI T1 services rack on HF platform TOTEM T1 Readiness Review, 30 November 201011 4 minirack installed on HF platform Safety smoke turbine installed, connection to DCS ?? All cables from the Counting Room traced and tested Cooling circuit done on –side, +side ??
12
Saverio MINUTOLI12 MARATON power box HF PLATFORM TOTEM T1 Readiness Review, 30 November 2010 3 MARATONs already installed 4 th currently used in H8 1 spare at the B188 (electronic boards test bench) MARATON local settings adjusted Vout=2.5V; Imax=15A; OVP=4V. All MARATONs on the platform even the empty location, switched ON and controlled from CR via Remote Control Monitoring boards and OPFCs. 3 RCMs already installed 4 th currently used in H8 1 spare at the B188 (electronic boards test bench) All RCMs and cabling to MARATON have been tested.
13
Saverio MINUTOLI ¼ T1 Local L.V. distribution TOTEM T1 Readiness Review, 30 November 201013 MARATON Power Box Distribution Box 6° frame ¼ T1 FUSE Box Vsense Box On platform Local LV distribution completely redesigned (ESR request). Built Fuse Box on platform Built an integrated Fuse Box monitoring system DCS Built new LV cables, between HF platform and 6 th frame of T1 Built new T1 6 th frame internal LV distribution Box Modified internal T1 LV cabling Replaced internal LV connectors Modified internal LV sense distribution Built Vsense Box on platform All of the items above have been checked and tested in the last test beam in H8 Because of this renewal of the system, need to replace the cables minus side Cable path way.
14
Saverio MINUTOLI 14 T1 H.V. system DCS SCADA OPC Server SHV R.M. R.M.= 52 pin Radiall Connector Distribution box on 6 th frame R.M. SHV R.M. 4 x A1550P HV modules A1550P 24 Chs 5 kV/1mA NearFar - + ¼ T1 TOTEM T1 Readiness Review, 30 November 2010
15
Saverio MINUTOLI H.V. distribution TOTEM T1 Readiness Review, 30 November 201015 HV Main frame in CR shared between all TOTEM subdetectors 3 modules A1550P already installed 4 th currently used in H8 1 spare at the B188, ready to be installed All HV boards have been tested Checked the Safety interlock of the local HV distribution box. All the HV cabling between CR and Platform have been tested, even with ¼ T1 emulator with dummy load.
16
Saverio MINUTOLI16 1 2 3 4 5 5 5 4 4 3 3 2 2 1 1 0x78 0x7E 0x77 0x79 0x76 0x7D 0x7A 0x7B 0x7C = CSC = ROC ROCs 45 ROCs 23 ROCs 01 = IP5 6 th frame DOHM = DOHM = SCR cable Slow Control Ring system TOTEM T1 Readiness Review, 30 November 2010 SCR distributes Fast Command (L1, BC0, Calib, Reset) and LHC clock Manage the F.E. settings through 16 I 2 C channels. DOHM independent LV channel Redundancy connection checked All the ¼ T1 quarters passed the SCR tests.
17
Saverio MINUTOLI 1m 100m Optic Fibers Patch Panel 8 MPO GOL/DOHM MPO in line adapter Fan-out Box on T1 6th frame Multi ribbon cable (8x12) Ribbon fiber cable (12x1) Single fiber 12 4.5m 3m ¼ T1 internal distribution #2 #1 #3 #4 Data SCR Trigger Platform 6 th Frame Control Room ¼ T1 Optic System TOTEM T1 Readiness Review, 30 November 201017
18
Saverio MINUTOLI Optic fibers distribution TOTEM T1 Readiness Review, 30 November 201018 Patch panel in Control Room installed Control Room Fiber patch cords available FEC, Data TOFED and Trigger TOTFED Local patch cords between Platform and T1 6 th frame available T1 internal connections checked and tested All T1 (4 x ¼) fiber optic systems have tested and validated during last test beam in H8 Local patch cords need to be installed on YE3 disk.
19
Saverio MINUTOLI ¼ T1 DCS and DSS systems TOTEM T1 Readiness Review, 30 November 201019 DCS system 3 PT100 temperature sensors installed and checked 2 on electronic boards and 1 on cooling plate 2 active Radiation Monitor sensors installed and checked 1 on 1 st plane internal and 1 on 5 th plane external On the adjacent quarter the RadMon sensors are located on the same plane but opposite sides. DSS system 2 PT100 temperature sensors installed and checked 2 on electronic boards. 2 passive Radiation Monitor sensors installed
20
Saverio MINUTOLI T1 DCS and DSS systems TOTEM T1 Readiness Review, 30 November 201020 Each DCS/DSS system of ¼ T1 have been checked and tested. DCS and DSS systems (both hardware and software) of T1 tested for 4 quarters during last short technical stops using a special unit to simulate the T1 presence. T1 DCS box in the Counting Room Temporally removed to include the LV Fuse monitoring All the cables DCS, DSS and Spares. PT100 RADMON
21
Saverio MINUTOLI Other sensors TOTEM T1 Readiness Review, 30 November 201021 Sensors (position x, y, z) (Joao): Ultra sound sensors mounted, cabled and tested Potentiometers mounted, cabled and tested The position of the Potentiometer sensors must ensure the exchangeability of the quarters. B Sensors ( Benoit): Only 8 out of 16 sensors installed (¼ yellow and ¼ green). cabling of B sensors to be completed
22
Saverio MINUTOLI Alignment laser beams system TOTEM T1 Readiness Review, 30 November 201022 Alignment system of CMS traversing T1: Checked all cables for possible interference Mechanical fixation to keep cables from entering laser beam zone
23
Saverio MINUTOLI Grounding and Shielding systems TOTEM T1 Readiness Review, 30 November 201023 Shielding of the digital signal cables completed Reinforced electrical connection of Aluminum structure parts Earthing point on CMS finalized (Sergei and Dmitry) Main grounding ribbon running the length of the support frame
24
Saverio MINUTOLI Summary Readiness of all systems Response on change requests from ESR in September QA/QC, including test during and after installation with requests of necessary infrastructure TOTEM T1 Readiness Review, 30 November 201024
25
Saverio MINUTOLI Requests (1) TOTEM T1 Readiness Review, 30 November 201025 The committee recommends contacting the CMS integration office for a ground point onto YE2, YE3, and perhaps onto the HF platform. Dmitry should be involved since this is rather a mechanical issue. I propose to drill the threaded holes on inner radial surface of "YE4 inner disks" with 30 mm offset from its edge. The holes should be on 3 o'clock and 9 o'clock for both EndCaps. (Dmitry) Each ¼ T1 have a main grounding ribbon running the length of the support frame. The ribbon is copper, 200 microns thick and approximately 10 cm wide. (also by Sergei) Exteriors of CSCs connected with copper foil (also by Sergei) In addition the aluminum support structure electrical continuity have been reinforced with copper braid or thick wires.
26
Saverio MINUTOLI Requests (1) TOTEM T1 Readiness Review, 30 November 201026 Cavern GROUNDMain grounding ribbon CSC ground reinforced Frame joints reinforced Boards support grounding
27
Saverio MINUTOLI Requests (2) TOTEM T1 Readiness Review, 30 November 201027 The committee endorses the insertion of fuses to protect 1.5mm 2 power cables between the LV power supply and the 6 th frame. It is important to explore the failure modes with the inline fuses in conjunction with remote sensing. Consider to add remote monitoring of the fuses for trouble shooting. Make sure that any additional work on the – side gets into the site planning. Request of installing fuses on each electronics card triggered a complete redesign of the LV distribution on the detector. Two x 4 LV distribution boxes (on T1 and at the MARATON output) New cables on YE3 to connect the LV boxes One fuse on each line at the MARATON output. Status of fuses is available locally and remotely through DCS. One x 4 LVsense box (at the MARATON input) Additional work on –side already planned within the schedule.
28
Saverio MINUTOLI Requests (2) “Panels and Cables” TOTEM T1 Readiness Review, 30 November 201028 Fuse Box Front view Fuse Box Rear view New LV cables New 6 th frame LV Distribution Box ¼ T1 internal LV and Vsense cabling
29
Saverio MINUTOLI Requests (2) “Remote monitoring” TOTEM T1 Readiness Review, 30 November 201029 Fuse ROC_TOP blown All ROC Fuses OK ROCs 2V5 Main power OFF DOHM Fuse OKDOHM 2V5 Main power OFFFuse DOHM blown By means of an optoMOS, the information on the status of each of the fuses is stored in digital format, optically isolated from the DCS system. The three fuse status bits for each ROC plane, plus the ON/OFF status of the main voltage, are fed to an R-2R ladder network.
30
Saverio MINUTOLI Requests (2) “Vsense redundancy” TOTEM T1 Readiness Review, 30 November 201030 Vsense Box Added Low Voltage sense redundancy in order to avoid Slow Control Ring break due to the master ROC failure.
31
Saverio MINUTOLI Requests (2) “Vsense behavior in failure mode” TOTEM T1 Readiness Review, 30 November 201031 OVP = 4V OVP = 3.3V OVP = 2.9V
32
Saverio MINUTOLI Requests (2) “Vsense behavior in failure mode” TOTEM T1 Readiness Review, 30 November 201032 Can be forced to zero by SW 5ms.
33
Saverio MINUTOLI Requests (3) TOTEM T1 Readiness Review, 30 November 201033 Verify with the manufacturer that the flat cable crimp quality is qualified for power distribution of the foreseen levels. The CSORVEM company (www.csorvem.it ISO9001) has confirmed that all its products are tested both mechanically and electrically within the limits of the characteristics of the components.www.csorvem.it Automatic and semi-automatic crimping machines and more than 40 different tools/die sets available. In our case Dielectric strength contact to contact of 500V and Current rating of 1.2A@20˚C for the Erni SMC type B connector. In our case Voltage rating of 50V and Current rating of 300mA considering a section of wire 0.050mm 2 (6A@1mm 2 ) for the flat cable. The manufacturer confirms that the crimp quality is qualified for power distribution of the foreseen levels.
34
Saverio MINUTOLI Requests (3) TOTEM T1 Readiness Review, 30 November 201034 ISO 9001 Quality test
35
Saverio MINUTOLI Requests (4) TOTEM T1 Readiness Review, 30 November 201035 The Committee endorses the plan for shielding of the flat cables to the chambers. All digital flat cables were removed from the detector and shielded with copper tape (35μm) welded at its overlapped ends. The shield was protected by an insulation braid. The shield was connected to the metallic cover of the ROC (source) by means of wire soldered to the cable shield on one side and a terminal lug to the other. Shielded cables
36
Saverio MINUTOLI Summary Readiness of all systems Response on change requests from ESR in September QA/QC, including test during and after installation with requests of necessary infrastructure TOTEM T1 Readiness Review, 30 November 201036
37
Saverio MINUTOLI Installation test and infrastructure TOTEM T1 Readiness Review, 30 November 201037 CHECKS on the system are foreseen when in the cavern They are programmed in the last phases of installation: Before insertion in the end cap After the insertion in the end cap and before moving HF on 4 risers The system check needs the LV, HV, R/O and DCS/DSS connections. This in turns requires: DCS running Power for LV racks S4 F05 (rectifiers)EXD 20/55 (breakers) Power in TOTEM racks S2 B03 (HV)S2 B02 (DCS) DAQ-DataDAQ-Trigger
38
Saverio MINUTOLI Installation test and infrastructure TOTEM T1 Readiness Review, 30 November 201038 Schedule and assignment of manpower finalized Presence of key people from CMS and TOTEM for the installation is defined. Availability of manpower confirmed : CERN, INFN, and availability of FSU The work to be completed before installation is on schedule
39
Saverio MINUTOLI Conclusions TOTEM T1 Readiness Review, 30 November 201039 Commissioning of the 4 quarters had been extensively done on the H8 beam in the past months. Both hardware and software checked and functional. Transport of 2 quarters to IP5 planned for the beginning of December (7-10) The other two quarters will preferably be transported beginning of January (7-8) We are ready for installation Thank you for your attention.