Chapter 10 Standard Costing: A Managerial Control Tool
COPYRIGHT © 2012 Nelson Education Ltd.
2
Learning Objectives Explain how units standards are set and why standard cost systems are adopted Explain the purpose of a standard cost sheet Describe the basic concepts underlying variance analysis, and explain when variances should be investigated Compute the materials variances and explain how they are used for control Compute the labour variances, and explain how they are used for control (Appendix) Prepare journal entries for materials and labour variances
3
OBJECTIVE 1 Explain how unit standards are set and why standard cost systems are adopted
4
Unit Standards Developing standards enhances control
Need to determine the unit standard cost for a particular input Two decisions: Quantity decision Pricing decision
5
Quantity & Price Decision
The amount of input that should be used per unit of output Quantity Standard The amount that should be paid for the quantity of input to be used Price Standard Quantity Standard × Price Standard = Unit Standard
6
Unit Standard & Development of Standards
Used to enhance cost control Budgeted ‘unit’ costs Unlike budgets which contain aggregate amounts of total revenue and total costs Quantity Standards are developed by: Historical experience Engineering studies Input from operating personnel
7
Development of Standards
Price Standards are the joint responsibility of: Operations Purchasing Personnel Accounting
8
Types of Standards Ideal standards ---
demand maximum efficiency and can be achieved only if everything operates perfectly Currently attainable standards --- can be achieved under efficiency operating conditions
9
Why Standard Cost Systems Are Adopted
Two reasons: To improve planning and control To facilitate product costing
10
Actual costs are compared to budgeted costs and variances are computed
Planning and Control Standards: Enhance planning and control Improve performance management Fundamental requirement for a flexible budgeting system Actual costs are compared to budgeted costs and variances are computed
11
Costs are assigned to products using standards for:
Product Costing Costs are assigned to products using standards for: Direct materials quantity Direct materials price Direct labour quantity Direct labour price Overhead quantity Overhead price
12
Standard Costing Advantages: Greater capacity for control
Provides readily available unit cost information Simplifies cost assignments in both process and job costing systems
13
Explain the purpose of a standard cost sheet
OBJECTIVE 2 Explain the purpose of a standard cost sheet
14
Example: Cornerstone 10-1
HOW TO Compute Standard Quantities Allowed (SQ and SH) Information: Assume that 100,000 packages of corn chips are produced during the first week of March Unit quantity standard is 18 grams of yellow corn per package Unit quantity standard for machine operators is 0.01 hour per package produced Required: For the actual output of 100,000 packages: How much yellow corn should have been used? How many operator hours should have been used?
15
Example SQ x = SQ = 18 x 100,000 SQ = 1,800,000 grams Corn allowed:
Unit Quantity Standard Actual Output SQ x = Standard quantity of materials allowed SQ = 18 x 100,000 SQ = 1,800,000 grams
16
Example SH x = SH = 0.01 x 100,000 SH = 1,000 direct labour hours
Operator hours allowed: Unit Quantity Standard Actual Output SH x = Standard hours allowed SH = 0.01 x 100,000 SH = 1,000 direct labour hours
17
OBJECTIVE 3 Describe the basic concepts underlying variance analysis, and explain when variances should be investigated
18
Variance Analysis Components
SP = Standard unit price of an input SQ = Standard quantity of input for the actual output AP = Actual price per unit of the input AQ = Actual quantity of the input used
19
Total Budget Variance Total Variance Actual Cost Planned Cost = – –
(AP x AQ) (SP x SQ)
20
Price (Rate) Variance - Actual Price Standard Price
Number of inputs used - x Favourable variance = Actual price is less than standard price Unfavourable variance = Actual price is greater than standard price
21
Usage (Efficiency) Variance
Actual Quantity Standard Quantity Standard Unit Price - x Favourable variance = Actual quantity is less than standard quantity Unfavourable variance = Actual quantity is greater than standard quantity
22
The Decision to Investigate
Performance rarely meets established standards exactly Random variations around the standard are expected Management should determine an acceptable range of performance
23
Example: Cornerstone 10-2
HOW TO Control Limits to Trigger a Variance Investigation Information: Standard cost: $100,000; allowable deviation: $10,000; actual costs for six months: June $97,500 September $102,500 July 105,000 October 107,500 August 95,000 November 112,500 Required: Plot the actual costs over time against the upper and lower control limits. Determine when a variance should be investigated
24
Acceptable Range (Don’t Investigate)
Example $120,000 110,000 Acceptable Range (Don’t Investigate) Standard 100,000 90,000 June July August September October November
25
Example $120,000 Investigate 110,000 100,000 90,000 June July August
September October November
26
OBJECTIVE 4 Compute the materials variances, and explain how they are used for control
27
Example: Cornerstone 10-3
HOW TO Calculate the Total Variance for Materials Information: Unit standards: Standard price: $0.01 per gram Standard usage: 18 grams Actual results for the first week in March: Actual production: 48,500 bags of corn chips Actual cost of corn: 780,000 grams at $0.015 Required: Calculates the total variance for corn for the first week in March
28
Example Corn $11,700 Total variance for corn: Actual Costs
Budgeted Costs Total Variance – = AQ x AP 780,000 grams x $0.015 Corn $11,700
29
Example Corn $11,700 $8,730 Total variance for corn: Actual Costs
Budgeted Costs Total Variance – = SQ x SP (18 grams x 48,500 bags) x $0.01 Corn $11,700 – $8,730
30
Example Corn $11,700 $8,730 $2,970 U Total variance for corn:
Actual Costs Budgeted Costs Total Variance – = Corn $11,700 - $8,730 = $2,970 U
31
Direct Materials Variances
Materials Price Variance Measures the difference between what should have been paid for raw materials and what was actually paid MPV = (AP – SP) x AQ
32
Direct Materials Variances
Materials Usage Variance Measures the difference between the direct materials actually used and the direct materials that should have been used for the actual output MUV = (AQ – SQ) SP
33
Example: Cornerstone 10-4
HOW TO Calculate Materials Variances: Formula and Columnar Approaches Information: Unit standards: Standard price: $0.01 per gram Standard usage: 18 grams Actual results for the first week in March: Actual production: 48,500 bags of corn chips Actual cost of corn: 780,000 grams at $0.015 Required: Calculates the materials price and usage variance using the 3-pronged (columnar) and formula approaches
34
Materials Price Variance
Example Formula Approach Materials Price Variance MPV = (AP – SP) AQ MPV = ($0.015 – $0.01) 780,000 MPV = $3,900 U
35
Materials Usage Variance
Example Formula Approach Materials Usage Variance MUV = (AQ – SQ) SP MUV = [780,000 – (18 x 48,500)] ($0.01) MUV = $930 F
36
Example Columnar Approach 1. AQ x AP $11,700 2. AQ x SP $7,800
3. SQ x SP $8,730 780,000 x $0.015 780,000 x $0.01 (18 x 48,500) x $0.01
37
Example Columnar Approach 1. AQ x AP $11,700 2. AQ x SP $7,800
3. SQ x SP $8,730 Price Variance (1 – 2) $3,900 U Usage Variance (2 – 3) $930 F
38
Example Columnar Approach 1. AQ x AP $11,700 2. AQ x SP $7,800
3. SQ x SP $8,730 Price Variance (1 – 2) $3,900 U Usage Variance (2 – 3) $930 F Total Variance (1 – 3) $2,970 U
39
Responsibility for the Materials Price Variance
Belongs to the purchasing agent Price can be influenced by: Quality Quantity discounts Distance of the source from the plant
40
Responsibility for the Materials Usage Variance
Belongs to the production manager Variance can be influenced by minimizing: Scrap Waste Rework
41
Analysis of the Variances
First step: Decide whether the variance is significant Second step: Find out why it occurred
42
Accounting and Disposition of Materials Variances
Materials variances are ADDED to cost of goods sold if they are UNFAVOURABLE Materials variances are SUBTRACTED from cost of goods sold if FAVOURABLE
43
Direct Labour Variances
Labour Rate Variance Computes the difference between what was paid to direct labourers and what should have been paid LRV = (AR – SR) x AH
44
Direct Labour Variances
Labour Efficiency Variance Measures the difference between the labour hours that were actually used and the labour hours that should have been used. LEV = (AH – SH) SR
45
Compute the labour variances and explain how they are used for control
OBJECTIVE 5 Compute the labour variances and explain how they are used for control
46
Example: Cornerstone 10-5
HOW TO Calculate the Total Variance for Labour Information: Unit standards: Standard price: $8.00 per hour Standard usage: 0.01 hours Actual results for the first week in March: Actual production: 48,500 bags of corn chips Actual cost of corn: 360 $8.35 Required: Calculate the total variance for inspection labour for the first week in March
47
Example Actual Costs Budgeted Costs Total Variance - = AQ x AP SQ x SP
Total variance for inspection labour: Actual Costs Budgeted Costs Total Variance - = AQ x AP SQ x SP Inspection labour $3, $3,880 = $874F
48
Example: Cornerstone 10-6
How to Calculate Labour Variances: Formula and Columnar Approaches Information: Unit standards: Standard price: $8.00 per hour Standard usage: 0.01 hours Actual results for the first week in March: Actual production: 48,500 bags of corn chips Actual cost of corn: 360 $8.35 Required: Calculate the labour rate and efficiency variances using the 3-pronged (columnar) and formula approaches
49
Example LRV = (AR – SR) AH Formula Approach Labour Rate Variance LRV =
($8.35 – $8.00) 360 LRV = $126 U
50
Labour Efficiency Variance
Example Formula Approach Labour Efficiency Variance LEV = (AH – SH) SR LEV = (360 – ) $8.00 0.01 x 48,500 LEV = $1,000 F
51
Example Columnar Approach 1. AH x AR $3,006 2. AH x SR $2,880
3. SH x SR $3,880 360 x $8.35 360 x $8.00 (0.01 x 48,500) x $8.00
52
Example Columnar Approach 1. AH x AR $3,006 2. AH x SR $2,880
3. SH x SR $3,880 Price Variance (1 – 2) $126 U Usage Variance (2 – 3) $1,000 F
53
Example Columnar Approach 1. AH x AR $3,006 2. AH x SR $2,880
3. SH x SR $3,880 Price Variance (1 – 2) $126 U Usage Variance (2 – 3) $1,000 F Total Variance (1 – 3) $874 F
54
Causes of Labour Rate Variance
Labour rates are determined by external forces as labour markets and union contracts Labour rates can vary when: more skilled and more highly paid labourers are used for less skilled tasks unexpected overtime occurs
55
Responsibility for the Labour Efficiency Variance
Production managers are responsible for the use of direct labour But once the cause is discovered, responsibility may be assigned elsewhere
Similar presentations