Download presentation
Presentation is loading. Please wait.
Published byNoreen Williamson Modified over 9 years ago
1
2001 Winter Presentation
2
Site Location
3
Site View
4
1923 1968 1972 Boston Improved Sewage Site History
5
Peninsula, surrounded by water Area of in-filled land Winter snow Site Constraints
6
Engineering Constraints Soil Properties Compactable Soil 4000 psf bearing capacity Capacity, silt/clay and sand mixture 20’ water table Loading Live Load50 psf Dead Load70 psf Wind Load35 psf Roof Load28 psf
7
Budget Information
8
“With a clear understanding of the historical influences of site, the land, the harbor, the history of Boston…” Architect’s Vision
9
Architectural Design 1 (Redesign) Keep the integrity of the DOME Allow open center to remain Evaluate programmatic functionality Relocate sloped floor rooms to basement level for ease of constructability of slabs
10
Architectural Design 1 (Redesign)
11
Engineering Design 1 Steel (Redesign) Composite steel design Regular column grid Easy installation Steel moment frame Typical Beam: W14X26 c=1” Moment Frame: W16X36
12
Design 1 Steel Estimate (Redesign) Total = $3,145,000
13
Engineering Design 1 Precast (Redesign) 12” masonry wall 24” deep precast concrete girders
14
Design 1 Precast Estimate (Redesign) Total = $3,231,000
15
Design 1 Schedules Finish Dates: Steel - 09/28/16, Precast - 10/05/16 Durations : Steel – 8 mo & 4 wks, Precast – 9 mo Precast Steel
16
Architectural Design 2 Concepts Flow like the waves of the bay Structure like the hull of a boat Gesture towards the historic influence of the site Open walls towards the oak trees Individuality between faculty and students
17
Architectural Design 2 Auditorium Classrooms, seminar rooms, labs Student offices Faculty offices, facilities, administration
18
Engineering Design 2 Steel Gravity System Composite steel design No truss for auditorium Typical Beam W14X30 Typ Girder W24X55 Typ Col W12X40 Auditorium beam w24X76
19
Engineering Design 2 Steel Foundation layout Strip & spread footings Steel bracing Tube 3X3X1/4
20
Design 2 Steel Estimate Total = $2,722,000
21
Engineering Design 2 Precast Concrete gravity system Load bearing wall, 2-way slab 48’ post-tensioned girders
22
Engineering Design 2 Precast Foundation layout 3’ wide strip footing 12” masonry walls Load path
23
Design 2 Precast Estimate Total = $2,800,000
24
Design 2 Schedules Finish Dates: Steel - 09/14/16, Precast - 09/21/16 Duration: Steel – 8 mo & 2 wks, Precast – 8 mo & 3 wks Precast Steel
25
Architectural Design 3 Concepts Box in a box Simple, double structure Advantageous use of sloped classroom and auditorium floors Flow of light to below grade level Exterior wood structure to gesture towards trees
26
Architectural Design 3 Auditorium Classrooms, seminar rooms, labs Student offices Faculty offices, facilities, administration
27
Architectural Design 3
28
Engineering Design 3 Steel Inside Frame Plan Gravity SystemSteel Bracing Tube 3x3x1/4
29
Engineering Design 3 Steel Outside Frame Plan Flat RoofSteel Knee Brace Frame
30
Design 3 Steel Estimate Total = $3,083,000
31
Engineering Design 3 Wood Inside Frame Plan Gravity System Wood Wall Lateral System
32
Engineering Design 3 Wood Outside Frame Plan Pre-fabricated wood truss with knee brace Prefab wood truss 2"X6" Column 12"DIA Knee brace 2"X6" Joist 2"X4" Steel Brace 12"X2"
33
Engineering Design 3 Wood Outside Structure Load Path Gravity Load Lateral Load
34
Engineering Typical Connection Steel Bracing Wood With Steel Plate & Bolts
35
Design 3 Wood Estimate Total = $2,978,000
36
Design 3 Schedules Finish Dates : Steel - 08/24/16, Wood - 09/07/16 Durations: Steel – 7 mo & 3 wks, Wood – 8 mo & 1 wk Wood Steel
37
Equipment Selection Skid Steer Loader Mini Excavator Truck Crane
38
Budget Comparison
39
Design Evaluations DesignArchitectEngineerCM 1S Attractive Dome Design Moment Frame Is Expensive Constructability & Budget Concerns 1P Good CirculationDome Poses Wind Load Problems Constructability & Budget Concerns 2S Concept Fits Local Area Rigid Diaphragm Problem Best Budget 2P Least Visually Pleasing Rigid Diaphragm Problem Good Budget 3S Best Looking BuildingGirders Have Deflection Problem Very Constructible 3W Very Interesting Building Sloped Roof Helps Snow Load Very Constructible
40
Decision Matrix DesignAttractiveInterestBudgetScheduleTotal 1S 435517 1P 346619 2S 651315 2P 562417 3S 22318 3W 11428 Explanation of design rankings: 1=Best…6=Worst Lowest point total wins
41
Design Choice Design 3 Best combination of strengths vs. weaknesses were 3W & 3S from matrix Wood/Steel Hybrid Combine the attractiveness/interest of 3W with the cost and schedule benefits of 3S Keep wood exterior structure of 3W, but incorporate the steel interior structure of 3S
42
Team Dynamics/Interaction
43
“The most challenging and the most successful part of this whole process is the perpetual learning of our own and each others discipline and how we must collaborate in order to succeed.” “The structural system is not the only aspect of the building. We need to think about the others' intentions and constraints. Compromising between different intentions is very important in developing a successful project.” “The greatest thing we will take away from this class is learning how to successfully work in a challenging situation with diverse people on a project with little contact.”
44
Lessons Learned Cross-Discipline Knowledge Vocabulary Interests/Concerns Teamwork Tolerance Dependence/Collaboration Organization/Work Habits Technology New Applications
45
2001 Winter Presentation Questions?
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.