1 ALICE Operations short summary LHCC Referees meeting June 12, 2012

2 Data taking in 2012 2  Stable operation, steady data taking, good performance of the LHC and ALICE Accumulation of RAW since beginning of 2012 run Total 450 TB of physics data

3 Data processing 3  2011 pp data processed in Pass1 most of the periods in Pass2 some special (2.76GeV reference data) Pass3  2011 PbPb data Pass2 completed in time for “Hard Probes” Pass3 in preparation for QM’2012 in August  2012 pp processing with new calibration schema  Presently running large MC productions  … and user analysis

4 Production job efficiencies 4 MC (aliprod), RAW (alidaq), QA and AOD filtering Averages: aliprod: 90%, alidaq: 75%, global: 82% LHC11h Pass1 LHC11h Pass2

5 Chaotic and organized analysis 5 The efficiency remains almost constant (trains) March – average 10K jobs 7.9GB/sec from SE Last month – 11K (+10%) 9.8GB/sec from SE (+20%)

6 Analysis efficiencies 6  Analysis uses ~1/3 of available CPU resources  Average efficiency ~30%, with large variations I/O intensive jobs are not ‘inefficient’ they simply use other aspects of the hardware… … that said, the CPU/Wall is what is being measured and reported and thus we work to improve it Efficiency strongly depends on the type of analysis

7 The Analysis Trains  Polling together many user analysis tasks (wagons) in a single set of Grid jobs (the train)  Managed through a web interface by a Physics Working Group conductor (ALICE has 8 PWGs)  Provides a configuration and test platform (functionality, memory, efficiency) and a submission/monitoring interface  Speed – few days to go through a complete period AliROOT Analysis Framework MonALISA Web interface LPM AliEn Grid jobs 7

8 Status  Trains created for 6 PWGs 4 PWGs already actively submitting trains 2 in testing phase  Up to 30 wagons (individual tasks) for the most advanced  Even for non-optimized trains the average efficiency is >60% 8

9 Future of trains 9  Only viable method for running large scale (many hundreds of TB input data) analysis on a regular basis ~300TB is what the users have to go through today to analyze the 2010 and 2011 PbPb data samples + associated MC  Works equally well with smaller samples – the time gain is significant over chaotic user analysis Does not replace chaotic fully, but individual users do no need to run over everything…

10 Storage 10  Following a T1-T2 workshop in January – sites call for a significant improvement of SE monitoring and control xrootd development is ongoing new MonALISA tools for the servers  These will be presented and refined during the 2 nd Federated Data Workshop at Lyon CCIN2P3 (September 2012) We expect that the combined system will significantly improve the efficiency of the jobs..by detecting bottlenecks and services overloads

11 Services summary 11  Stable operation of all components  Minor hiccups, very good support at all centers  Storage remains critical Continuous cleanup of replicas (of older productions) and having less replicas of ESDs (analysis firmly on AODs) The ongoing installation of 2012 pledges is reducing the urgency at some sites

12 CPU requirements update CCRC F2F 10/01/2008 12 2012 2013 OLD 2012 2013 NEW

13 Summary 13  The 2011 pp & HI period data is processed and being analyzed  2012 pp data taking and processing ongoing  Many thanks to the T0/T1/T2 centers for the excellent performance and support


Download ppt "ALICE Operations short summary LHCC Referees meeting June 12, 2012."