1 MSD II –Managerial Presentation Spring 2009 P09454: Design & Testing of Centrifugal Pump Components

2 Design Team: Rishitha Dias - ISE – Project Manager Kevin Klucher - ME – Lead Engineer John Hayles - ME Reme Meck - ME Ammar Jangbarwala - ME

3 Project Background: Project Family: Sustainable Technologies for the Global Marketplace Project Track: Flow Visualization Sponsor: Dresser-Rand Corp. Faculty Guide: Dr. S. Day

4 Project Deliverable: The goal of the project is to design, build, test and deliver to KGCOE, a centrifugal pump system for particle imaging velocimetry (PIV) studies, which can be used both as a teaching tool for undergraduate students as well as a research tool for graduate and faculty researchers.

5 Customer Needs: Primary Customers:  Faculty & Graduate Researchers  Undergraduate Instructors Customer Needs / Target Specifications:  Generate Multiple Flows~ 3 Unique Impeller Designs ~ 2 Unique Diffuser Designs  PIV Compatibility>85% Transmissivity of Pump Components  Lab Teaching Tool< 5 min Component Swap Time > 0.45” Tool Clearance Measureable Flow, Pressure & Power. Parts must withstand a drop from 42”

6 Inherited Pump System: Close-up view of Pump Housing & Impeller Sensors & Actuators Tank GUI

7 System Architecture:

8 Design Concept Summary Impeller & Diffuser Riser

9 Deliverable Status:

10 P09454-105P09454-106 P09454-102P09454-103P09454-104 Previous Impeller Design:New Impeller Designs: Impeller Designs

11 Old Impeller Design: Impeller Designs

12 Diffuser Designs P09454-201 P09454-203

13 Pump Housing:

14 Project Status:

15 Budget: > 40% of the $6,500 budget remaining Component Manufacture & Materials costs are dominant.

16 Schedule: Product development Phase Current Stage of Design Phase 1 Phase 2 Phase 3 Phase 4 MSD I MSD II Planning Concept Development System Level Design Testing & Refinement

17 Schedule: Project is on Schedule  Component Manufacture Complete  Pump Assembly Complete  Flow Testing Complete  Documentation Complete

18  Characterize Various Flows  5 Impellers & 2 Diffusers available to generate curves  Interchangeable Components  Assembly/Disassembly averages 3.5 minutes Performance:  Measure Pressure, RPM & Flow  Built into GUI functionality  Control Flow, RPM, Pressure  GUI Controls & Valves  PIV Compatible  Clear Acrylic Components

19 Results:

20

21 Test Results As head rises, the flow decreases, demonstrating basic pump curve relationships. With the addition of a vaned diffuser, the head generated is increased versus flat ring diffusers. P09454-102Vaned P09454-102Flat Plate Pressure (psi) Flow (gpm)Head (ft) Pressure (psi) Flow (gpm)Head (ft) 3.58.48.0772.67.56.000 3.688.3082.77.26.231 47.89.2312.876.462 57.211.5383.66.38.308 6.85.415.6924.25.59.692 8418.4624.74.610.846 8.8220.3085.82.513.385 91.520.7696.21.214.308 9.11.2521.0006.2114.308 9.250.7521.3466.4014.769 P09454-103Vaned P09454-103Flat Plate Pressure (psi) Flow (gpm)Head (ft) Pressure (psi) Flow (gpm)Head (ft) 3.58.58.0772.57.45.769 3.58.18.0772.876.462 47.99.2313.16.77.154 4.87.2511.0774.25.39.692 5.656.713.0384.94.511.308 6.65.415.2315.33.712.231 7.753.617.8855.82.713.385 92.120.7696.21.714.308 9.21.421.2316.41.214.769 9.750.7522.5006.50.715.000

22 Discussion Pump provides 10x the options (impeller and diffuser) with 65% faster component switch time Head generated is up to 60% greater than previous system benchmarks Flow rate is not up to maximum theoretical value of 22.3 gpm. However, ~ 25% increase over previous iteration Diffuser made a large difference in the amount of head generated, up to a 27% increase for the basic 102 impeller New designs can be rapid prototyped and tested in the test loop within several days based on standard dimensions used for the components

23 Questions?