1
BIM IN ACTION?? Dr Mark Shelbourn University of the West of England South West Regional BIM Hub
3
http://www.bdonline.co.uk/carbuncle-cup-chancellors-building-university-of-bath-stride-treglown/5069213.article
4
Project Details Five storey general teaching accommodation GIA 8230m 2 Construction value £16m GC Works 1 Single Stage Design and Build Key dates: Inception March 2012 Planning registered June 2012 Planning granted October 2012 Construction October 2012 Completion date 24 th September 2013 Practical completion 24 th September 2013
6
Procurement Building to be operational by September 2013 University and project team agreed this was ambitious Agreed to a new approach to the design, approvals, tendering, construction and handover
7
Project Issues Design and construction phase – issues with the cladding 1. Initial tendering and pricing procedure for the cladding 2. Methodology and construction of the external cladding
8
Tendering & Pricing Procedure Programme constraints 8 week turnaround Sub-contractor quotes to main contractor Lowest price chosen Guess what happened? Chosen sub-contractor had not included for any of the fixings to attach the cladding panels Could BIM have helped?
9
Method & Construction of cladding 12 week manufacture in Germany Delay of 5 weeks due to manufacture supply chain issues Slower than expected installation by SC Tight site constraints Lack of available storage Inexperience of SC installing this type of panel Lack of appropriate machinery Delay on when building would be watertight
10
Building wrapped to allow internal works before being watertight
11
Method & Construction of cladding 12 week manufacture in Germany Delay of 5 weeks due to manufacture supply chain issues Slower than expected installation by SC Tight site constraints Lack of available storage Inexperience of SC installing this type of panel Lack of appropriate machinery Delay on when building would be watertight Cladding came off the critical path, programme adapted – with discussion with the PM team and client
12
Method & Construction of cladding Could BIM have helped?
13
BIM was used…
14
Method & Construction of cladding Practical completion awarded at 8.00am on 24 th September 2014 – 1 hour before the building was due to be opened by the Chancellor – Prince Edward Earl of Wessex Not really complete… Missing timber to ceilings for example What about FieldBIM?
17
FieldBIM A cloud-based service for field management. Use a mobile app on-site for collaboration and reporting Example videovideo Autodesk - http://www.autodesk.com/products/bim-360- field/overviewhttp://www.autodesk.com/products/bim-360- field/overview SPOTNIC – nRAH, Adelaide SPOTNIC
18
THANK YOU Any questions?