CEMENT STABILIZATION OF ROADS CSIR Transportek Frank Netterberg Soillab (C&CI Steering Committee)
2
Terms of Reference Consortium was contracted by the Cement and Concrete Institute (C&CI) on behalf of its members to: –Investigate the influence of the new SABS EN 197-1 cement specifications on the use of cement as a road material stabilizer (ie is TRH 13 still appropriate).
3
Progress Interviews within the industry (completed) Design laboratory test programme (completed) Carry out laboratory testing (commencing shortly) (First material identified and being collected) (Cements being organised)
4
Laboratory test programme Initial programme was to: Test five suitable materials Use 7 different cements Study effect of: –Time –Temperature on strength, workability –Cement composition and durability This would require about R8 million and about 196 tonnes of material
5
Revised programme Seven cements Two materials Initially workability and strength to be assessed
6
Cements Full range of standard and non-standard cement tests on each cement
7
Materials Dolerite (low plasticity index (PI < 6) Dolerite (medium-high PI (10 - 16) Full range of standard and non-standard material tests on each sample
8
Stabilisation tests All tests at 3% cement and 100 % Mod AASHTO effort Materials compacted after 2 and 4 hours Materials conditioned at 10, 23 and 45ºC Cured for 7 days at 23°C and 95-100% humidity Tested for density and strength (CBR, UCS and ITS)
9
Proposed programme Initiate material testing –Mid November 2002 Complete initial tests – End February 2003 Report – End March 2003