1 53:071 Hydraulics & Hydrology Project #2 Flow Measurement with a Weir Li-Chuan Chen, Marian Muste, Gokhan Kirkil, and Allen Bradley

2 Problem Statement The Iowa DNR plans to return farmland to a native tallgrass prairie landscape as an experiment.

3 Problem Statement A small ephemeral stream drains the site. The Iowa DNR wishes to find out how the runoff from the site changes over time.

4 Objective Design a weir flow control structure to continuously measure discharge at the site.

5 Principle

6 SlopeIntercept

7 Apparatus — Weirs WEIR EXPERIMENT

8 Procedures 1. Insert the weir of the desired shape. 2. Record the reference point of the weir. 3. Set the appropriate discharge in the flume and record the water level difference on the differential manometer. 4. Record the water surface elevation upstream of the weir. 5. Repeat Step 3 and 4 for four more discharges. 6. Repeat Step 1 to 5 for one more weir shapes.

9 Data Sheet Discharge Triangular 90   h (ft) Q (cfs) Ref. Point (ft) W.S. Elev. (ft) Weir Head (ft)

10 Analysis Determine the discharge Q in the flume (using the side-contraction meter) and the head H on the weirs. Using several measured Q-H pairs, plot log Q versus log H. From the best-fit line to the experimental points, determine the k exp (the intercept) and n exp (the slope). Compare k exp and n exp with values indicated in the literature.

11 Sample Result

12 Site Information Measure flows up to the highwater mark

13 Engineering Analysis Recommend a weir geometry and provide the head- discharge relationship. Provide profile and cross-section specs for the weir site (AutoCAD sketch). Estimate uncertainty of the discharge measurement (in ± cfs) for two cases Estimate of the extent of ponding behind the weir for the design flood conditions (water surface profile) Provide the client (the Iowa DNR Restoration Project Manager) with a concise report that answers the project objectives.


Download ppt "53:071 Hydraulics & Hydrology Project #2 Flow Measurement with a Weir Li-Chuan Chen, Marian Muste, Gokhan Kirkil, and Allen Bradley."