National Nanofabrication Centre Centre for Nano Science and Engineering IISc, Bangalore, India TUMS Murthy Oct 28, 2014 Cleanroom Admin Committee Meeting
2
TUMS Murthy Analysis of IISc users (other than MITO84) – 53 users average around 35K/year – Top 10 users average around 97 K /year – Maximum usage by Suman Sarkar @5.2 Lakhs – Only 5 people exceed 1.0 Lakh User Statistics Oct 28, 2014 Cleanroom Admin Commitee Meeting
3
TUMS Murthy Order placed for cleanroom management system software with FOM networks – Installation to be completed by the end of this year – Software and hard ware locks will be installed – Automatic invoice generation will be possible Starting to invoice for precious metals from October usage Decision to be taken for Wafers Cleanroom Highlights Oct 28, 2014 Cleanroom Admin Commitee Meeting
4
TUMS Murthy – Order being placed for a water mist fire extinguisher to be located in the outer corridor of the cleanroom – Order being placed for smoke generators for testing smoke detectors – RFQs sent out for – Shifting of VESDA from utility building into the cleanroom – Installation of conventional fire/smoke detectors in utility building in UPS and chemical storage areas Oct 28, 2014 Fire Safety Cleanroom Admin Commitee Meeting
5
TUMS Murthy Annual clean room maintenance is being planned for December 19-31 Major work planned is the arresting of leakage of fresh air at the AHUs Rework the thermal insulation of chilled water lines Wet exhaust scrubber Relaying the flooring of cleanroom outside corridor Oct 28, 2014 Annual maintenance Cleanroom Admin Commitee Meeting
6
TUMS Murthy Oct 28, 2014 Thank You Cleanroom Admin Commitee Meeting