Chapter 6 Introduction to Microsoft Project
Charts and Graphs Gantt Chart Pert Chart Introduction to Microsoft Project Work breakdown structure
2
Introduction These charts are used for Strategic Management
Project Management Application of knowledge, skills, tools and techniques for project activities in order to meet or exceed stakeholder needs and expectation from a project.
3
Introduction Helps project manager and team in term of
Scope management Time management Cost management Quality management Charts for project scheduling Gantt Chart, also known as (Time Line Charts) PERT chart (Evaluation Review Technique)-network diagram.
4
Gantt Chart A Gantt chart is a graphical representation of the duration of tasks against the progression of time. useful tools for planning and scheduling projects. allow you to assess how long a project should take. lay out the order in which tasks need to be carried out. help manage the dependencies between tasks. determine the resources needed.
5
Advantages Gantt charts are useful tools when a project is under way.
monitor progress. You can immediately see what should have been achieved at a point in time. Show how remedial action may bring the project back on course.
6
Gantt Chart
7
PERT chart "PERT" developed by the United States Department of Defense as a management tool for complex military projects is an acronym for "Program Evaluation and Review Technique". This technique was soon adapted for used in educational research and evaluation. Through PERT, complex projects can be blueprinted as a network of activities and events (Activity Network Diagram).
8
PERT chart It is used for project scheduling. Pert charts allow software planners, or individuals to: Determine the critical path a project must follow. Critical path is the longest overall duration, determining the shortest time to complete the project Establish most likely time estimates for individual task by applying statistical models. Calculate boundary times that define a time ‘window’ for a particular task.
10
Project Management Software
Among the project management software used to create charts and graph are: Microsoft Project Microsoft Visio
11
Microsoft Project Ikon Microsoft Project
12
Entry Bar Tool Bar Title Bar Menu Bar Entry Table View View Bar Status Bar Gantt Chart View
13
Microsoft Project-Gantt Charts
Gantt charts provide a standard format for displaying project schedule information by listing project activities and their corresponding start and finish dates in a calendar format Symbols include: A black diamond: milestones or significant events on a project with zero duration Thick black bars: summary tasks Lighter horizontal bars: tasks Arrows: dependencies between tasks
14
Creating a Gantt Chart The Gantt chart is constructed with a horizontal axis representing the total time span of the project, broken down into increments (days, weeks, or months). constructed with a vertical axis representing the tasks that make up the project and constructed with a graph area which contains horizontal bars for each task connecting the period start and period ending symbols.
15
The Gantt chart also has variants such as:
Milestones: important checkpoints or interim goals for a project Resources: for team projects, it often helps to have an additional column containing numbers or initials which identify who on the team is responsible for the task
16
Status: the projects progress, the chart is updated by filling in the task's bar to a length proportional to the amount of work that has been finished Dependencies: an essential concept that some activities are dependent on other activities being completed first
17
Task List Time line
18
Milestone Sub Task Extra Notes
19
Starting Microsoft Project
Start a new file Click Menu File and then New
20
To enter details of the project
Click Menu File then Properties Enter details on: Title Subject Author Manager Company Category Keywords
21
Creating a Gantt Chart Click on Gantt Chart icon Click on Gantt Chart
22
Entering Tasks Enter task name in Task Name and determine the timeline using Duration, Start and Finish Date Enter details here
23
Entering tasks List of tasks
24
Entering sub tasks There two ways: :
Indent. Click on the starting of task name and drag to the right Using the buttons
25
Indent
26
Task Dependency Types
27
Connecting one tasks with another
28
Connecting Tasks Connecting Tasks
Highlight Two tasks that is going to be connected Click Edit. Click Link Task Determining the dependency type FS, SF, SS, FF Double click on the first task Click Tab Predecessor. Select the task name in the drop-down menu. Choose the dependency type.
29
Determining the dependency type
Chose the dependency type
30
Milestone Milestone Normally show the event
The time period is usually 0 or 1 day only.. Example: Start Project, End Project Double click on the cell. Choose Tab Advance and Mark Task As Milestone.
31
Milestone Tab Advanced Mark here
32
Time scale To change the Time scale For example days, weeks, months
Click on Format. Choose Timescale. Choose the time scale unit desired
33
Time Scale Unit Of time scale
34
Gantt Chart View To update the Gantt chart view Click Format.
Click on Gantt Chart Wizard to show Critical Path Date Resources
37
Date Critical Path
38
Work Breakdown Structure
a results-oriented family tree that captures all the work of a project in an organized way portrayed graphically as a hierarchical tree, tabular list of "element" and tasks or the indented task list that appears in Gantt chart schedule
39
Work Breakdown Structure
40
PERT Chart Microsoft Project
41
Starting Pert Chart in Ms Project
Click on View. Choose PERT Chart or Click on PERT Chart icon on the left side of Ms Project window
42
Pert Components PERT has two main components: Arrows Node/ field
Every node has information on task name, task ID, duration, start, finish and resources Arrows shows the activities flow Every arrows is possible to have crictical path. 2 format: AoA (ADM) = activity-on-arrow (arrow diagramming method) AoN (PDM) = activity-on-node (precedence diagramming method)
43
Activity-on-Arrow (AOA) Network Diagram for Project X
44
Arrow Diagramming Method (ADM)
Known as activity-on-arrow (AOA) Every activities is presented by arrows Node shows the starting and finishing date
45
ACTIVITY - ON – ARROW (AoA) NETWORK
The advantages are : Show the project’s time length Show the activities which the starting point and end point are flexible or can be edited without changing the project’s time length - float. 1 A B C D E F G 2 4 6 3 5
46
Precedence Diagramming Method (PDM)
Activities are presented by boxes Arrows show the dependency between activities More popular compared to ADM (AOA) Better in showing different types of dependencies
47
Creating PERT Chart Creating PERT chart Determine the activities
Determine the flow of the activities Estimate the time for each activities Prepare a time-scale chart for activities to determine the critical path
48
Example: Precedence Diagramming Method (PDM) Network Diagram for Project X
49
Critical Path The flow of activities that must be completed in order to complete the whole project The delay in critical path will delayed the whole project.
50
Simple Example of Determining the Critical Path
Consider the following project network diagram. Assume all times are in days. a. How many paths are on this network diagram? b. How long is each path? c. Which is the critical path? d. What is the shortest amount of time needed to complete this project?
51
Determining the Critical Path for Project X
52
Total Expected Time of Project = Activity Estimates
PERT Estimates Activity Estimate = ((Optimistic Time + (4 x Most Likely Time) + Pessimistic Time)) 6 n Total Expected Time of Project = Activity Estimates i=1
53
Activity Analysis for PERT
Predecessor Optimistic Estimates (Days) (a) Most Likely Estimates (Days) (b) Pessimistic Estimates (Days) (c) Expected Duration (a+4b+c) 6 A None 1 2 4 2.2 B 3 5 8 5.2 C 3.8 D 3.3 E 1.0 F C,D 4.0 G D,E 3.0 H F,G 2.3 I 9 5.5 J H,I .5 1.3
54
Possible PERT Activity Paths
Possible Paths Path Total Path 1 A+B+C+F+H+J 18.8 Path 2 A+B+D+F+H+J 18.3 Path 3 A+B+D+G+H+J 18.6 Path 4 A+B+D+G+I+J 20.5* Path 5 A+B+E+G+I+J 18.2