Download presentation
Presentation is loading. Please wait.
Published byKristopher Gregory Modified over 9 years ago
2
GSET Technical Seminar Series Space Telescope Science Institute November 21, 20051 Earned Value Management: An Introduction and Short Tutorial Wayne Baggett
3
GSET Technical Seminar Series Space Telescope Science Institute November 21, 20052 Outline What is Earned Value? Government Requirements Small Project Usage Why Use Earned Value? Earned Value in a Nutshell Conclusions
4
GSET Technical Seminar Series Space Telescope Science Institute November 21, 20053 What is Earned Value? How does Dilbert know this?
5
GSET Technical Seminar Series Space Telescope Science Institute November 21, 20054 What is Earned Value? Project Management Technique Integrates technical performance requirements, resource planning, and cost accounting with schedule Provides insight into project status Provides “early warning signals” for problems Provides a disciplined means of managing the project
6
GSET Technical Seminar Series Space Telescope Science Institute November 21, 20055 Government Requirements OMB Circular A-11, Exhibit 300 (2004) Requires EVMS for all major acquisitions Agencies must have ANSI-compliant EVMS in place by December 31, 2005 EVMS data must be used to identify problems and provide realistic final cost estimates as a part of decision packages Federal Acquisition Regulations (2005) amended to require contractor-maintained EVMS
7
GSET Technical Seminar Series Space Telescope Science Institute November 21, 20056 Government Requirements These requirements apply to large projects or programs; DOD requires Contract Value ≥ $50M: validated ANSI-compliant EVMS, structured reports and reviews, ongoing surveillance $50M > Contract Value ≥ $20M: ANSI-compliant EVMS (validation not required), tailored reports and reviews, ongoing surveillance Contract Value < $20M: EVMS optional, ongoing surveillance Very rigid, heavily constrained system at this level
8
GSET Technical Seminar Series Space Telescope Science Institute November 21, 20057 Small Project Usage Small projects provide “the best opportunities for earned-value employment” Consider its use for “… all in-house funded developmental projects where a firm commitment is made to management.” “Software projects can especially benefit from the employment of a simple earned-value approach.” (Fleming and Koppelman, “Earned Value Project Management: A Powerful Tool for Software Projects,” Crosstalk, July, 1998, p. 19.)
9
GSET Technical Seminar Series Space Telescope Science Institute November 21, 20058 Small Project Usage The Personal Software Process (PSP SM ) and Team Software Process (TSP SM ) use EVM PSP has practitioners estimate task efforts and track their actual efforts Tasks estimated are very small – about 10 hours each Data are used to improve future estimates TSP expands the use of EVM to the project level Use of PSP and TSP helps projects meet their commitments (Tuma, D. and Webb, D., “Personal Earned Value: Why Projects Using the Team Software Process Consistently Meet Schedule Commitments,” Crosstalk, March 2005, p. 17.) PSP and TSP are registered service marks of Carnegie Mellon University
10
GSET Technical Seminar Series Space Telescope Science Institute November 21, 20059 Small Project Usage Several projects at STScI have used EVM: Most used a tailored version of EVM JWST S&OC development FOS, PPS, PRDS JWST FITS Writer development INS Master Schedule development DMS Automated Test System development
11
GSET Technical Seminar Series Space Telescope Science Institute November 21, 200510 Why Use Earned Value? Obligates planning to the level of task management Less likely to overlook work Provides objective measures of progress Allows early detection of budget and schedule problems Allows an objective projection of eventual project cost and schedule
12
GSET Technical Seminar Series Space Telescope Science Institute November 21, 200511 Key to Earned Value Determine the value for every task prior to starting work!
13
GSET Technical Seminar Series Space Telescope Science Institute November 21, 200512 Guidelines for Setting/Earning Value Use a consistent unit of measurement that makes sense for the project Dollars – required for large gov’t projects Hours – useful on small projects; PSP SM Arbitrary number – not recommended, but still used Consider task duration Select Earned Value Methods that are as objective as possible
14
GSET Technical Seminar Series Space Telescope Science Institute November 21, 200513 Earned Value Methods MethodUsageExamples Equivalent Units Value based on completed portion of a large number of completed activities S/W Implementation, H/W Production 0-100Value earned upon completing work that starts and ends within one status period Outlines, Document Preparation, Formal Reviews 50-50Part of value earned when work starts and remainder when it ends, usually when work straddles two reporting periods; percentages are determined by the manager Short Engineering Analyses, System Design, Build and Acceptance Tests Interim Milestones Value earned at the completion of objective milestones; usually for work that straddles several consecutive status periods Long-Term Analyses, System Design, Requirements Definition Apportioned Effort Value earned is prorated based on a portion earned for another unit of work QA, Configuration Management, Database Management Percent Complete Value earned based on subjective estimate; usually for work that has no objective measure of completeness Long-Term Studies, Maintenance and Operations Level of Effort Value based on passage of time; usually for work that cannot be defined or measured Project Management, Receptionist, Help Desk Objectivity
15
GSET Technical Seminar Series Space Telescope Science Institute November 21, 200514 Example: Planned vs. Actuals $13,000 under budget! Current Date
16
GSET Technical Seminar Series Space Telescope Science Institute November 21, 200515 Example: Earned Value BAC=$200 SV=EV-PV=($30) CV=EV-AC=($17) PMB PV EVAC
17
GSET Technical Seminar Series Space Telescope Science Institute November 21, 200516 Earned Value Concepts Planned Value (PV) – planned cost of doing the scheduled work (formerly BCWS) Earned Value (EV) – planned cost of the work completed (formerly BCWP) Actual Cost (AC) – actual cost of the work completed (formerly ACWP) Performance Measurement Baseline (PMB) – the time-phased budget plan against which performance is measured
18
GSET Technical Seminar Series Space Telescope Science Institute November 21, 200517 Earned Value Concepts (cont.) Schedule Variance (SV) – measures how project is doing relative to the schedule SV = EV – PV Positive Ahead of Sched., Negative Behind Sched. Cost Variance (CV) – measures how project is performing; productivity measure CV = EV – AC Positive Efficient, Negative Inefficient
19
GSET Technical Seminar Series Space Telescope Science Institute November 21, 200518 Earned Value Concepts (cont.) Budget Variance (BV) – measures how project is doing against the budget BV = PV – AC Positive Under Budget, Negative Over Budget Budget At Completion (BAC) – sum of the planned value plus the Undistributed Budget
20
GSET Technical Seminar Series Space Telescope Science Institute November 21, 200519 Example: Earned Value VAC=BAC-EAC=($33) EAC=AC + ETC=$233 ETC=(BAC-EV)/CPI=$146 SPI=EV/PV=0.70 CPI=EV/AC=0.81
21
GSET Technical Seminar Series Space Telescope Science Institute November 21, 200520 Earned Value Concepts (cont.) Schedule Performance Index (SPI) – measure of schedule compliance: is work being done at the planned rate? SPI = EV/PV 1 Faster than planned Cost Performance Index (CPI) – productivity measure: is the work costing what was expected? CPI = EV/AC 1 Efficient
22
GSET Technical Seminar Series Space Telescope Science Institute November 21, 200521 Earned Value Concepts (cont.) Estimate To Complete (ETC) – estimate of the effort required to complete the project from the current date ETC = (BAC – EV)/CPI Estimate At Completion (EAC) – the estimated total cost of the project EAC = AC + ETC
23
GSET Technical Seminar Series Space Telescope Science Institute November 21, 200522 Earned Value Concept Summary AcronymDefinitionEquationInterpretation PVBudgeted cost of task(none) EVEarned value for task(none) ACActual cost of task(none) SVSchedule VarianceSV=EV - PV >0 = Ahead, <0 = Behind BVBudget VarianceBV=PV - AC >0 = Under, <0 = Over CVCost VarianceCV=EV - AC >0 = Productive, <0 = Unproductive BACBudget At Completion BAC= UB + PV “UB”=Undistributed Budget SPISchedule Perf. IndexSPI=EV/PV >1 = Faster, <1 = Slower CPICost Perf. IndexCPI=EV/AC >1 = Efficient, < 1 = Inefficient ETCEstimate to CompleteETC=(BAC-EV) /CPI EACEstimate At CompletionEAC=AC+ETC VACVariance at CompletionVAC = BAC - EAC >0 = Under, <0 = Over
24
GSET Technical Seminar Series Space Telescope Science Institute November 21, 200523 Costs of EVMS Marginal cost of using EVMS is estimated at less than 1% to a few% of total contract cost Based mainly on large DOD contracts with experienced EVMS users Some costs are unnecessary according to EVMS criteria, but effort is put into those activities anyway Expect costs to be higher at STScI due to inexperience in using EVM and our culture Mitigated by our implementation Christensen, David S., “The Costs and Benefits of the Earned Value Management Process,” Acquisition review Quarterly, Fall, 1998, p. 373.
25
GSET Technical Seminar Series Space Telescope Science Institute November 21, 200524 Benefits of Earned Value It is a single management control system that provides reliable data. It integrates work, schedule, and cost using a work breakdown structure. The associated database of completed projects is useful for comparative analysis. The cumulative cost performance index (CPI) provides an early warning signal. The schedule performance index provides an early warning signal. Christensen, David S., “The Costs and Benefits of the Earned Value Management Process,” Acquisition review Quarterly, Fall, 1998, p. 373.
26
GSET Technical Seminar Series Space Telescope Science Institute November 21, 200525 Benefits of Earned Value The CPI is a predictor for the final cost of the project. It uses an index-based method to forecast the final cost of the project. The “to-complete” performance index allows evaluation of the forecasted final cost. The periodic (e.g., weekly or monthly) CPI is a benchmark. The management by exception principle can reduce information overload. Christensen, David S., “The Costs and Benefits of the Earned Value Management Process,” Acquisition Review Quarterly, Fall, 1998, p. 373.
27
GSET Technical Seminar Series Space Telescope Science Institute November 21, 200526 “The most common problem product teams face is unreasonable schedule pressure. … When teams are forced to work to unreasonable schedules, they are unable to make useful plans. Every plan they produce misses management’s edicted schedule and is therefore unacceptable. As a result, they must work without the guidance of an orderly plan. Under these conditions, the team will generally take much longer to complete the project than they otherwise would.” Watts Humphrey, “Pathways to Process Maturity: The Personal Software Process and Team Software Process,” SEI Interactive, June 1999.
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.