1 July 2015 Helen Coleman, Director Elizabeth Stegmaier, Associate Director LaTonya Webb, Assistant Director Fred Coleman, Director of Diversity University of Illinois at Urbana-Champaign 2015 Contractor Training July 2015

2 Comments from Allan Stratman,
Executive Director of Facilities & Services 2015 Contractor Training July 2015

3 AGENDA Pre-Qualification Bid Checklist Material Deficiency Checklist
Certs & Statutory Requirements Financial Disclosures MAFBE Overview Contract Preparation Upcoming Projects AGENDA 2015 Contractor Training July 2015

4 Pre-Qualification Register for the Vendor Services Application (VSA) VSA Help Document Submit Application in Contractor Annual Prequalification System (CAPS) Getting Started – CAPS STATE FARM CENTER ABBOTT POWER PLANT 2015 Contractor Training July 2015

5 Navigation to VSA and CAPS
Source: 2015 Contractor Training 2015 Contractor Training July 2015

6 Source: https://przm.apps.uillinois.edu/
VSA Application Main Source: 2015 Contractor Training July 2015

7 VSA Registration Page Source: SURVEYING BUILDING 2015 Contractor Training July 2015

8 VSA Required Information Legal Vendor Name Vendor Type Type of Firm
Name of Principal Officer State Incorporated Illinois Dept. of Human Rights # Vendor MAFBE Profile (If applicable) CMS Certification Type CMS Certification Expiration Date Registered Agent Information Organizational Profile (Name, address, phone, contact info.) User Profile (Name, Title, , Phone) 2015 Contractor Training July 2015

9 Getting Started - CAPS 2015 Contractor Training July 2015

10 Contractor Annual Prequalification (CAPS)
Registered agent information is inconsistent with Secretary of State business registration information IDHR # is expired or missing Documentation provided for legal disclosures is inadequate Insufficient experience in division of work for which applying Minimum of 10 projects provided with reference information. Must include at least 2 public works projects All projects were completed within the past 5 years Projects must have included work specific to the division of work for which applying Common Mistakes 2015 Contractor Training July 2015

11 Surety letter and power of attorney are missing or insufficient.
Attachments are missing or have errors. Required attachments include: Surety Letter and Power of Attorney Board of Elections Electronic Certificate Substance Abuse Policy Certification and Statutory Requirements Form Financial Disclosure and Conflict of Interest Form Explanation of legal disclosures (if applicable) MBE/FBE CMS Certification documentation (if applicable) Substance abuse policy does not meet minimum state requirements. Common Mistakes 2015 Contractor Training July 2015

12 CAPS Reference Links Illinois Dept. of Human Rights Secretary of State Business Services Corporate Search Board of Elections Registration Substance Abuse Prevention on Public Works Projects Act (820 ILCS 265/) 2015 Contractor Training July 2015

13 Source: http://www.uocpres.uillinois.edu/contractors/contracts
Bid Checklist Source: 2015 Contractor Training July 2015

14 Material Deficiency Checklist
Source: Section , 10.2.A Material Deficiencies 2015 Contractor Training July 2015

15 Most Common Material Deficiencies
Source: Section , 10.2.A Material Deficiencies 2015 Contractor Training July 2015

16 Senate Bill 51/Public Act 096-0795
As part of the requirements of Public Act , bidders are required to complete certain certifications and disclosures for themselves, and upon award for their subcontractors. This is accomplished via the following forms: Certifications and Statutory Requirements Form Financial Disclosures and Potential Conflicts of Interest Form Fillable forms are located at: 2015 Contractor Training July 2015

17 Certs & Statutory Requirements
Source: 2015 Contractor Training July 2015

18 Certs & Statutory Requirements
Failure to provide vendor name, IDHR # or IDHR expiration date (#18) Failure to check the non-applicable line if the vendor has <14 FTE (#18) Failure to check the appropriate boxes regarding business with Iran and Board of Elections registration (#32 and #33) Incorrect Apprenticeship Training Number provided. The name/number of local union is not acceptable (#39) Failure to provide project name and all information in the signature block Common Mistakes Source: 2015 Contractor Training July 2015

19 Financial Disclosures
Source: 2015 Contractor Training July 2015

20 Financial Disclosures
Failure to provide Illinois Procurement Bulletin number Failure to select Instrument of ownership of beneficial interest (company type) from dropdown menu Failure to complete a separate form for all parent entities and/or owners that are companies or trusts Failure to check both ownership disclosure statements in Step 2 Failure to answer Step 4 – 7 for each owner listed in Step 2 and the company itself Common Mistakes 2015 Contractor Training July 2015

21 Financial Disclosures
Failure to provide ALL information requested in Step 8 Failure to indicate “procurement relationship” (Prime of Sub) for each project listed in Step 8 and on attachment, if applicable Failure to provide Step 8 attachment in the same format as the table on the form and required information is missing, if applicable Common Mistakes 2015 Contractor Training July 2015

22 Contract Execution Checklist
2015 Contractor Training July 2015

23 Contract Execution Checklist
Failure to submit all contract paperwork within the 15 days provided in the contract documents Failure to provide powers of attorney for each bond Failure to include executed Attachment A for each MBE/FBE used towards MAFBE goals Dollar value on Attachment A does not equal or exceed the value on Attachment B submitted with the bid Insurance and Builder’s Risk certificates are not executed correctly Failure to list Board of Trustee as additional insured Failure to provide waiver of subrogation clause Common Mistakes 2015 Contractor Training July 2015

24 Failure to include project name and number
Failure to provide coverage for entire project amount (BRI) Failure to include Earthquake and Flood Coverage when required (BRI) Failure to provide a properly executed sealed/signed corporate signature authority letter Failure to ensure to send the Project Labor Agreements to the East Central Illinois Building & Trades Counsel and are signed and submitted to our office Common Mistakes 2015 Contractor Training July 2015

25 MBE/FBE/FMB Capital Construction Goals
- Established by University Board of Trustees September 2010 - 15% in Urbana, Peoria and Springfield, 22% in Chicago - Goal is a combined goal and can be met using Tier I subcontractors and suppliers (Tier I = direct subcontractor/supplier to prime bidder only) - Goal applies to each division of work bid and any amount that is bid within a division of work - Goal applies to base bids and alternate(s) bid, combined or separately 2015 Contractor Training July 2015

26 MBE/FBE/FMB Eligibility Requirements
- ONLY vendors certified by IL CMS BEP as MBE, FBE or FMB are recognized and counted towards MBE/FBE goals by the University. - Use the Illinois Central Management Services Business Enterprise Program (IL CMS BEP) Vendor Directory to confirm a vendors MBE/FBE/FMB status - IL CMS BEP Directory is found at: Put border around photos EVERITT LAB LEVIS CENTER 2015 Contractor Training July 2015

27 Bidding Requirements - Must utilize Attachment B to list MBE/FBE/FMB and proposed utilization $ - IL CMS BEP Certification required for each vendor listed; otherwise no goal credit or a material deficiency - Proposed utilization in dollars will be converted to a percentage to determine if goal is met or not - Proposed utilization is maintained through contract award, schedule of values and utilization of MBE/FBE/FMB vendor on project 2015 Contractor Training July 2015

28 Verification of MBE/FBE/FMB with Bid
MBE/FBE/FMB vendors certification status is found by viewing and printing the vendor profile Expiration date shown on IL CMS BEP profile must be a date in the future before bid opening date Submit IL CMS BEP vendor profile with bidding documents IL CMS BEP profile sample 2015 Contractor Training July 2015

29 Good Faith Effort (GFE) When Goal Not Met
GFE documentation due within 7 calendar days of bid opening. GFE begins with attendance at pre-bid meeting where resources to find MBE/FBE/FMB vendors is shared in pre-bid meeting packet Invitation to Bid (ITB) identifies all scope prime advertises to MBE_FBE vendors in order to meet the goal ITB sent to MBE/FBE/FMB community 2X Phone calls placed to MBE/FBE/FMB list a minimum of 3 days prior to bid opening if goal not met ITB sent to any MBE/FBE/FMB vendor that can provide supplies or perform any work scope in the proposed University construction advertisement—local and regional. Regions = Peoria, Springfield, Chicago, Danville, Decatur, and Bloomington GFE documentation compared to prime bidders that did meet the goal Expectation: 2015 Contractor Training July 2015

30 Commercially Useful Function Policy
- Enterprises which might be considered “pass-throughs” or “fronts” are not permitted - University recognizes Illinois Central Management Services (IL CMS) does not address “commercially useful function” in minority and female business enterprise certification review process - CMS policy is for each agency to adopt their own rules for determining “commercially useful function—University is drafting a more comprehensive policy MECHANICAL ENGINEERING BUILDING NOYES LAB 2015 Contractor Training July 2015

31 Illinois Public Higher Education Procurement Bulletin website -
Upcoming Projects F&S website – future projects Illinois Public Higher Education Procurement Bulletin website - current ads Check if first link is still valid. If not, please update. 2015 Contractor Training July 2015

32 Upcoming Projects (Over $5M)
Project Number Project Title Anticipated Bid Date Divisions of Work Project Budget U13024 CERL MAIN BUILDING ADDITION (Rebid) 9/15/2015 1,2,3,4,5 $ 7,000,000 U14072 SURVEYING BUILDING RENOVATION 10/15/2015 TBD $ 8,000,000 U14111 ABBOTT POWER PLANT - GAS BOILER REPLACEMENT - PHASE 2 12/21/2015 $ 9,500,000 U14088 EVERITT LABORATORY RENOVATION - BIOENGINEERING GRAINGER ENGINEERING BREAKTHROUGHS INITIATIVE (Early Bid Package) 9/1/2015 $ 50,000,000 Input a new screen shot and include photos of Everitt and another large project. Put a border around the photos. EVERITT LABORATORY SURVEYING BUILDING RENOVATION 2015 Contractor Training July 2015

33 Questions? Presentation will be available at: Check link. 2015 Contractor Training July 2015


Download ppt "Bidding Capital Project at the University of Illinois for Contractors"

Similar presentations


Ads by Google