Florida Gas Transmission Mainline Hydrostatic Test From the Palmetto Expressway Interchange with Okeechobee Road to the Intersection of Milam Dairy Road.

Similar presentations


Presentation on theme: "Florida Gas Transmission Mainline Hydrostatic Test From the Palmetto Expressway Interchange with Okeechobee Road to the Intersection of Milam Dairy Road."— Presentation transcript:

1 Florida Gas Transmission Mainline Hydrostatic Test From the Palmetto Expressway Interchange with Okeechobee Road to the Intersection of Milam Dairy Road with NW 64 th Street Miami-Dade County

2  Who is Florida Gas Transmission (FGT)?  Why is FGT testing?  What is the test exactly?  When will the test occur?  Where will the test take place?  How will the test be conducted?  How will the test affect me? Today’s Outline

3  Natural gas transmission company operating a 5,000 mile pipeline system along the Gulf  Provide 65% of all the natural gas for power generation in Miami-Dade County  18” diameter Mainline serving South Florida  Customers include:  Electric utility companies  Local distributors  Industrial clients Florida Gas Transmission Company

4  The U.S. Department of Transportation regulates all interstate pipelines  Testing is federally mandated  Best practice to confirm the safety and reliability of the pipeline  Safety is our #1 priority  Ensure continued superb client service Need for the Test

5  Hydrostatic Test  Remove the natural gas from the line Controlled release vents harmlessly into atmosphere LDC-service is continued on parallel loop system  Test the integrity of the pipeline by filling the line with water Put the water under pressure for a fixed period of time Nature of the Test

6  Hydrotesting the 18” Mainline system  Standard, common pipeline test procedure  Recent, successful 18” Mainline tests were completed in:  Saint Lucie  Palm Beach  Began Miami-Dade testing February 2011 Background  Martin  Broward

7 Public Awareness Campaign Project Process Begin Project Obtain Permits "Pig" Existing System Correct Any Anomalies Conduct Hydrotest End Project Prepare System for Testing

8  Test window has tentatively been set:  March 29 – April 26, 2012  Coordinated with FP&L and regulators Project Schedule

9  Total Project Length = 2.2 miles  Begin: W 39 th Street (NW 91 st Terrace)  End: NW 64 th Street  Generally follows 3 roadway alignments:  Palmetto Expressway (SR 826) & W 20 th Ave  Hialeah Expressway (SR 934) & NW 74 th St  Milam Dairy Road (NW 72 nd Ave / SR 969)  Hialeah, Medley, Miami-Dade County Project Location

10 Project Limit N Project Location (con’t)

11  Remove natural gas from the 18” Mainline  Completed the week before the hydrotest  Fill the line with water  Pressurize the system  Normal operating pressure is 722 PSI  Test pressure is up to 1,444 PSI Relatively short duration (approx. 30 minutes)  Reduce pressure to 1,108 PSI Maintain for 8 hours How the Test is Performed

12  De-pressurize the line  Drain the water from the system  If any integrity issues are found:  They are corrected as soon as possible  The hydrotest is performed again Any re-testing will be performed as soon as possible, during the same hours  Resume normal natural gas service How the Test is Performed (con’t)

13  Safety is our #1 priority  Performed extensive test preparations, including an inspection of the entire system  Pipe anomalies will be repaired in advance of conducting the hydrotest  For the duration of the high pressure test, as a safety consideration, we plan to isolate the pipeline route from people and traffic Safety During the Test

14  Advance Preparations  Make all key stakeholders aware Adjacent property owners Emergency service providers General driving public  Announcements Flyers, newspaper, FL511, website, etc.  Dynamic message signs 2 weeks in advance Conducting the Test

15  Night of the Test  Begin at midnight  Close cross streets with barricades  Law enforcement support  Confirm all-clear for entire corridor  Conduct hydrotest  Reopen roadways at approximately 4:00 AM Conducting the Test (Con’t)

16  General Utility Permit from the Florida Department of Transportation is in process  Emergency responders will be able to cross as needed  Officers will be stationed at major cross street detours Traffic Control During the Test

17 Project Location – District 13

18 Project Location – District 12

19 Please visit our website: www.fgthydrotest.com Or contact FGT: Mr. Terry Coleman 2405 Lucien Way, Suite 200 Maitland, FL 32751 Toll Free – 800.381.1477 Office – 407.838.7054 Fax – 407.838.7052 Email – Terry.Coleman@sug.com For More Information

20 FGT 18” Mainline Hydrotest Summary  Federal mandate  Testing with water  Test window is tentatively March 29 – April 26, 2012  Midnight – 4:00 AM  Road closures with law enforcement  W 20 th Ave  Hialeah Expwy & NW 74 th St  Milam Dairy Rd (NW 72 nd Ave)  Emergency vehicles can always cross Project Limit N

21 Thank You


Download ppt "Florida Gas Transmission Mainline Hydrostatic Test From the Palmetto Expressway Interchange with Okeechobee Road to the Intersection of Milam Dairy Road."