MuTr Recap Status and Plan. Plan We are shooting for North Station-1 for post Run10 shutdown installation. Best scenario is to mount portable “clamp”

Similar presentations


Presentation on theme: "MuTr Recap Status and Plan. Plan We are shooting for North Station-1 for post Run10 shutdown installation. Best scenario is to mount portable “clamp”"— Presentation transcript:

1 MuTr Recap Status and Plan

2 Plan We are shooting for North Station-1 for post Run10 shutdown installation. Best scenario is to mount portable “clamp” type re-capacitation board without soldering, without taking out Station-1 chamber. Prototype re-capacitation boards are tested in RIKEN.

3 Recap Board Prototype I

4 Recap Board Prototype Test Measured Electrical Contact of between probe and pad after disassembly/re-assembly of recap boards – About 50% of probes lost contact. Problem: – Individual probe doesn’t have flexibility to absorb unique surface structure of pad probe pad Capacitor board

5 Improvement for Prototype II Let individual probe have flexible freedom to adjust elevation so that it can absorb surface structure (remaining solder on pad). – Rubber pad – Spring probe (Current limit < 0.2A to prevent from burning spring) – Comb shape capacitor board Let capacitor board have more power to push probe – Thicker G10 – Angled G10 Prototype IPrototype II Spring probe

6 Conductive Silicon Rubber Pad About 30m  for 2mm thickness probe pad Conductive Rubber 2~3mm thick ~10m  for our probe size

7 Conformal Coating and Remover Conformal coating Removed coating Conformal coating can be removed by “remover”. Removed coating need to be suck up.

8 Schedule 2345678910 Prototype I Prototy pe II HV test mounting production shipping Install HV test Production cost : ~ $50k / Station-1 / Arm

9 Installation Scenario If “clamp” works: – Need Station-1 Scaffold – 1 hour coating removal / octant / man – 2 hours clamp install / gap / octant /man – 1 hour HV test / gap / octant /man – 1 octant/day/2men – 2 weeks + 1 week contingency = 3 total weeks If Station-1 need to be taken out: – 2 ~ 3 months