1 EWB-MAP Water Tank Project Construction Progress June 5-12, 2012

2 Map of Las Delicias Water System DOWNHILL

3 260 Homes Served by Tanque 3 33 Homes Served by Tanque 2 291 Homes Served by Tanque 1 DOWNHILL Map of current Las Delicias Water System from ADESCO with approx house locations indicated

4 117 Homes Served by Tanque 3 33 Homes Served by Tanque 2 154 Homes Served by Tanque 1 Proposed Water Distribution System 280 Homes Served by New Tank DOWNHILL

5 Map of Current Water System (section relevant for EWB-MAP modifications) RED lines – supply lines to tank (uphill by pump) BLUE lines – distributions lines by gravity DOWNHILL New 17,000 gallon tank Exisiting 11,000 gallon tank

6 Proposed update to Water System (section relevant for EWB-MAP modifications) RED lines – supply lines to tank (uphill by pump) BLUE lines – distributions lines by gravity NEW SUPPLY LINE 1 NEW DISTRIBUTION LINE 2c NEW DISTRIBUTION LINE 2a NEW DISTRIBUTION LINE 2b NEW TANK A B C D E F DOWNHILL 1.Tank Construction 2.Pipe connections 3.Pipeline Plans 4.Distribution of Work

7 DAY 1 – June 5, 2012

8

9 Photos

10 Day 2 – Wednesday June 6, 9 AM

11 Day 2 – 3 PM

12 Daniel Rivera (Engineer from Rotary) Miguel Delgado (driver/handyman) from FIAT) Miguel Martinez (Supervisor) Holman (driver from FIAT) Sergio (LD ADESCO member) Mario (LD resident)

13 Day 3 – Thursday June 7, 9 AM

14 Day 4 – Friday June 10, 11 AM

15

16

17 Day 5 – Saturday June 9, noon

18 Day 6 – June 11: noon

19 Day 7 – June 12 noon

20 Day 7 – 4 PM – ‘mesita’ complete

21 Schedule for Completion of Tank 1.Wed June 13: start laying rocks/sand for base of foundation 2.Thur June 14: continue laying rocks/sand for base of foundation 3.Fri June 15 – Tue June 19: cut/tie rebar and prepare form for foundation 4.Wed June 20: pour foundation 5.Rain could delay these tasks

22 Photos

23 Ordered tubing and fittings from local supply store in San Salvador

24 Proposed update to Water System (section relevant for EWB-MAP modifications) RED lines – supply lines to tank (uphill by pump) BLUE lines – distributions lines by gravity NEW SUPPLY LINE 1 NEW DISTRIBUTION LINE 2c NEW DISTRIBUTION LINE 2a NEW DISTRIBUTION LINE 2b NEW TANK A B C D E F DOWNHILL 1.Tank Construction 2.Pipe connections 3.Pipeline Plans 4.Distribution of Work

25 Proposed update to Water System (section relevant for EWB-MAP modifications) RED lines – supply lines to tank (uphill by pump) BLUE lines – distributions lines by gravity NEW SUPPLY LINE 1 NEW DISTRIBUTION LINE 2c NEW DISTRIBUTION LINE 2b NEW TANK A B C D E F DOWNHILL

26 Photos along Pipeline Path Area of Connection to Tubo Madre NEW SUPPLY LINE 1 NEW DISTRIBUTION LINE 2b NEW TANK A B C D

27 Photos along Pipeline Path (location of valve box?) NEW SUPPLY LINE 1 NEW DISTRIBUTION LINE 2b NEW TANK A B C D

28 Photos along Pipeline Path (location of valve box?) NEW SUPPLY LINE 1 NEW DISTRIBUTION LINE 2b NEW TANK A B C D

29 Photos along Pipeline Path NEW SUPPLY LINE 1 NEW DISTRIBUTION LINE 2b NEW TANK A B C D

30 Photos along Pipeline Path NEW SUPPLY LINE 1 NEW DISTRIBUTION LINE 2b NEW TANK A B C D

31 Photos along Pipeline Path NEW SUPPLY LINE 1 NEW DISTRIBUTION LINE 2b NEW TANK A B C D

32 Photos along Pipeline Path NEW SUPPLY LINE 1 NEW DISTRIBUTION LINE 2b NEW TANK A B C D

33 Photos along Pipeline Path NEW SUPPLY LINE 1 NEW DISTRIBUTION LINE 2b NEW TANK A B C D

34 Photos along Pipeline Path NEW SUPPLY LINE 1 NEW DISTRIBUTION LINE 2b NEW TANK A B C D

35 Photos along Pipeline Path NEW SUPPLY LINE 1 NEW DISTRIBUTION LINE 2b NEW TANK A B C D

36 Meeting with Mayor to discuss installation of pipeline Alcalde (Mayor) Ingeniero Romeo Jose Barillas (alcaldiaopico@yahoo.com, 2331-3001)alcaldiaopico@yahoo.com Travelled to Alcaldia (Mayor’s office) with Alfredo Torres (member of LD ADESCO) on Tuesday June 12, 2012) Got on waiting list at 8:30 & met with Mayor at 10:45 Requested help digging trench and installing PVC tubing. Alfredo had official letter from ADESCO Mayor knew about project (had been contacted by Ana Maria de Keene – honorary consul of El Salvador in Philadelphia) and agreed to help with everything including supplying the 4” (supply) and 2” (distribution) pipes. Questions from mayor: – Is 160 PSI PVC acceptable? – Do you want cemented PVC or rapid connection? – Will send an engineer to evaluate poject. Other questions (from RAC) – Location of valve boxes, air bleeds, T’s, cleanouts – Should prepare detailed plan to send to mayor ASAP

37 Distribution of Work EWB-MAP – Overall project management and communication between parties – Updating design verifying that work meets design specs. – Long term planning FIAT (Sister Gloria) – Purchase of last minute supplies, order trucks of materials, submission of receipts to Rotary for reimbursement. Storage of supplies. – Organizing volunteers, hiring one mason Las Delicias ADESCO – Organizing community labor (each house volunteers 1 day or pays $6 for another person to do the work) – Ensuring secure storage of supplies – Communication with Alcaldia Daniel Rivera (Rotary San Salvador) – Purchase of supplies (1 week notice): rebar, concrete – Payment of supervisor and mason (hire one mason) – Local project management and oversight of supervisor (Miguel Martinez) Alcaldia San Juan Opico – Installation of two lines (4” supply and 2” distribution) of tubing in the same trench between Calle Principal and Tanks.

38 Project Expenses (Thru June 11)

39 Contacts FIAT guest house: 2-226-7610 Miguel Delgado (FIAT driver/helper) cell: 7- 570-8675 Rene (LD President): 7-458-4150 Miguel Martinez (Supervisor on work site): 7- 465-0654 Alcalde (Mayor) Ingeniero Romeo Jose Barillas (alcaldiaopico@yahoo.com, 2-331-3001)alcaldiaopico@yahoo.com