Team assignment 13 TEAM 3 – K15T1 Hanh Luong – Leader – T095095 Hao Tran – T094442 Huy Nguyen – T094016 Hieu Le – T093798 Quang Nguyen – T094193.

Similar presentations


Presentation on theme: "Team assignment 13 TEAM 3 – K15T1 Hanh Luong – Leader – T095095 Hao Tran – T094442 Huy Nguyen – T094016 Hieu Le – T093798 Quang Nguyen – T094193."— Presentation transcript:

1 Team assignment 13 TEAM 3 – K15T1 Hanh Luong – Leader – T095095 Hao Tran – T094442 Huy Nguyen – T094016 Hieu Le – T093798 Quang Nguyen – T094193

2 Content 1. Assumption 2. Schedule 3. Budget 4. Summary

3 Assumption With this Viking project, team gives some critical assumptions -1 ideal day = 8h -1 week = 6 ideal days -Development team size = 7 -The project will be developed on new platform. It include the following: new database structure, new software architecture -About equipment to support project development, they will be reused but mail server is not because the company doesn’t have it.

4 Schedule The table show is the list of user stories and features in Viking project Story IDUser Story Feature 1Manage Users F1 2Manage Projects F2 3Manage Lifecycle F3 4Manage Roles F4 5Manage Members F5 6Manage Permissions F6 7Log In F7 8Synchronize Data F8 9Manage Issues F9 10Manage Artifacts F10 11Manage CommunicationsF11 12Manage Reports F12 Based on above table, team had meeting and the table following hyperlink is the result of estimator in teamfollowing hyperlink

5 The above information is result of estimation in ideal case. But in fact, there are some differences. And the table below will show the rate of ideal time and elapsed time. Schedule Human resource Available Hours/Day Ideal Hours/Day Scrum Master 68 Product owner 58 Development team Team leader 78 Architect 58 Developer & Tester 1 78 Developer & Tester 2 78 Developer & Tester 3 78 Total: 4456 Rate (Available Hours/ Ideal Hours):0,79

6 Schedule From above result, team put stories into sprint. Specific is shown in this below table SprintStory ID Ideal days of each story Ideal days of each sprint Elapsed days of each sprint Sprint 1 1 2,5 67 2 3 Sprint 2 3 2,75 56 4 2 Sprint 3 5 3 56 6 2 Sprint 4 7 1 57 9 4,25 Sprint 5 8 2 57 10 3,25 Sprint 6 11 3 57 12 2,25 Total 31 39

7 Schedule Finally, based on all information and result that are analyzed above, this figure is Product Roadmap Release

8 Budget The table below shows overview about Viking budget VIKING'S BUDGET Salary$24,856.00 Training$0.00 Equipment$100.00 Software/Tools$2,320.00 Risk & Change$0.00 Facilities/Infrastructure (water, electric, office, etc.)$238.00 Team Building (Entertainment, birthday, bonus, etc.)$200.00 Customer relationship (travel, hotel, etc.)$100.00 Total$27,814.00

9 Budget First, this table shows salary of Human resource. Salary table RoleHourly RateSalary Scrum Master1003945 Product owner803156 Team leader903551 Architect903551 Developer & Tester 1903551 Developer & Tester 2903551 Developer & Tester 3903551 Total budget 24856

10 Budget Second, this table shows price of equipment, tool and software No.ContentQuantityUnit Unit prize TotalNote 1.Equipment (Hareware) $100 1Laptop 7Thing $0 Reuse equipment 2Database Server 1Thing $0 3Modem 1Thing $0 4 Mail server (machine, domain name, etc.) 1Thing$100 2.Tool (Software) $2.320 1 Pragmatic's Defect Tracker 1License$20 2Microsoft Project 1License$1.000 3 Relational database management system (RDBMS) MS SQL Server Workgroup Edition 2005 1License$1.300 4netBean 1License $0free Total: (1) + (2) $2.420

11 Budget Finally, this table shows other price (team building, Facilities/Infrastructure and Customer relationship) Cost category Month Detail cost Total cost Facilities/Infra structure (water, electric, office, etc.) Electric ($35 per month) Water ($15 per month) Cleaning ($100 per month) Network ($20 per month) 1$35 $15$100$20$170 2$18 $8$50$10$68 $35$23$150$30$238 Team Buildding (Entertainmen t, birthday, bonus, etc) MonthPartyBonusTotal cost 1 $100 2 $0$200 Customer relationship (travel, hotel, etc.) Month Detail cost Total cost 1 $100 2 $50$150 $100

12 Resource Estimations about resource is described in schedule and budget

13 Summary Inclusion, in this documentation: About schedule: When apply Scrum process, with an overview, time to develop Viking project is shorter than applying RUP process. About budget: Familiar with schedule when applying Scrum process, Viking’s budget is less. About resource: From above analyzing, we can see that Scrum applying require less human resource to develop Viking project.

14 Thanks for your listening!