Download presentation
1
Grid Interconnection and Power Quality Assessment of Distributed Resources
Farid Katiraei Ph.D. Candidate Department of Electrical and Computer Engineering University of Toronto Wind Power Generation Symposium Feb. 20, 2004
2
Outline DR connection process Utility impact assessment
Interconnection requirements Power quality issues Case studies: A Hybrid system
3
Decentralized Power System
4
Standards and Regulations
“IEEE Std. 1547, for interconnecting Distributed Resources with Electric Power System”, IEEE Standards, July 2003 CSA Standard CAN3-C235, C325, C107.1 “MicroPower Connect Interconnection Guideline”, July 2003 Ontario Electrical Safety Code (OESC) Ontario Energy Board Act, 1998 ( sec. 27.1) Electric Safety Authority (ESA)
5
DR Connection Process Step 1: Basic planning Step 2: Feasibility study
- Data collection and Plan development, - Environmental assessment Step 2: Feasibility study - Utility impact assessment, - Electrical inspection requirements (ESA) Step 3: Implementation - Detailed design and review, - Basic interfacing equipments, - ESA plan approval Step 4: Commissioning & Authorization of the connection Step 5: Operation & Maintenance It is applicable to all kind of DRs, the complexity of the process is related to size of DR.
6
Utility Impact Assessment
Power quality assessment Interconnection requirements line/equipment upgrades Grounding Power flow System protection modification Fault currents, re-coordination Synchronization
7
Power Quality Issues Voltage regulation (Load dependent)
Voltage fluctuation (not greater than 5%) Flicker (No objectionable flicker) Voltage Unbalance Harmonic injection (TDD,THD < 5%) DC injection (< 0.5% of In) Reactive power requirements (Preferred pf. : lag 0.95 lead) Surge withstand performance ( up to 220% of the rated voltage)
8
Study system Impact assessments of a Hybrid system:
DG1: 2 MVA gas-fired diesel generator DG2: 2.5 MVA electronically-interfaced DG3: 1.5 MW wind turbine (Rotor diameter 76m, Wind speed: 5-25 m/s, Hub height: 64m) Load demand: Sensitive load, Industrial/Residential load Case I: Wind turbine start up Scenario 1: Grid interconnected system Scenario 2: Stand-alone system Case II: Short circuit analysis Line-Ground fault on the Utility side, Fault clearing
10
Wind turbine start up Direct connected generators:
Speeding up with the wind, connection at 85% of synchronous speed Soft starter, limit start up current Second winding (two speed turbines) Electronically interfaced: Synchronization Wind farm: Sequential start up
11
I-1: Grid Connected System
Bus voltages - t=2.0 s
12
I-1: Grid Connected System
Power variation - t=2.0 s
13
I-2: Stand-alone System
Bus voltages - t=2.0 s
14
I-2: Stand- alone System
Power variation - t=2.0 s
15
Case II: Fault Analysis
Voltage fluctuation - Fault @ t=0.5 s - t=0.58 s DR < 30 kW , maximum clearing time, DR > 30 kW default time
16
Case II: Fault Analysis
Freq. variation t=0.5 s t=0.58 s -Reconnect @ t=1.08s
17
Conclusion Comprehensive study of the system
Steady-state analysis Dynamic Analysis Appling uniform interconnection Standards
18
Thank You Question(s) ?
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.