Weekend Cabin Retreat Project Wall and Ceiling Construction
Sacramento City College EDT 300 Kenneth Fitzpatrick, P.E. EDT Wall and Ceiling Construction
2
EDT 300 - Wall and Ceiling Construction
Objectives Name the members of a typical frame wall. Explain methods of frame wall construction. Interpret information shown on a ceiling joist span data chart. Sketch the various types of exterior walls used in residential construction. EDT Wall and Ceiling Construction
3
Residential Construction
Residential wall construction is usually one of three types: Frame Masonry Combination frame and masonry. EDT Wall and Ceiling Construction
4
Residential Construction
The wall panels may be Constructed on site or Prefabricated at another location and transported to the site. The trend is toward more prefabrication and less on-site construction. EDT Wall and Ceiling Construction
5
Frame Wall Construction
Various framing members used in conventional construction. Sole plate Bottom of wall. 2 x 4 on side. Top plates Top of wall. 2 x 4 on side. Studs Sides of wall. 2 x 4 on end. Headers Span openings in walls. 4 x 10; 4 x 12. Etc. Bracing. Strengthens wall corners. EDT Wall and Ceiling Construction
6
EDT 300 - Wall and Ceiling Construction
7
Frame Wall Construction
EDT Wall and Ceiling Construction
8
Frame Wall Construction
Plates and studs 2 x 4 inch lumber. Headers or linters 4 x 6; 4 x 8; 4 x 10; 4 x 12 Bracing 1 x 4 stock Metal strap Plywood sheathing. EDT Wall and Ceiling Construction
9
Frame Wall Construction
EDT Wall and Ceiling Construction
10
Frame Wall Construction
Wall framing lumber must have Good stiffness Nail-holding properties Free from warp Easy to work. Species that meet these criteria: Douglas fir Southern Yellow Pine Hemlock Spruce, and Larch. EDT Wall and Ceiling Construction
11
Frame Wall Construction
The most common lumber grade used is #2 grade or its equivalent. Moisture content should be between 15 and 19 percent. EDT Wall and Ceiling Construction
12
Frame Wall Construction
Usually begins with the sole plate. The spacing of the studs is marked off on the sole plate The wall is built on top of the sub-floor. The sub-floor provides a large, flat work surface. EDT Wall and Ceiling Construction
13
Frame Wall Construction
EDT Wall and Ceiling Construction
14
Frame Wall Construction
Exterior frame walls can be Flush with the outside of the foundation wall or Moved 1/2" to 3/4" inside the foundation wall to allow for the thickness of sheathing, weatherboard, or rigid foam insulation. EDT Wall and Ceiling Construction
15
Frame Wall Construction
EDT Wall and Ceiling Construction
16
Frame Wall Construction
EDT Wall and Ceiling Construction
17
Frame Wall Construction
EDT Wall and Ceiling Construction
18
Frame Wall Construction
The sole plate Acts as an anchor for the wall panels Is a nailer for interior and exterior wall sheathing. A nailer Is a structural member (like a 2 x 4) that is used to support the drywall (gypsum board). EDT Wall and Ceiling Construction
19
Frame Wall Construction
A wall panel, when built on-site May be very large if sufficient people and equipment are available to raise the wall. Is usually built in smaller sections. EDT Wall and Ceiling Construction
20
Frame Wall Construction
Wall studs Are cut to length (usually 7'-9" when 1-1/2" material is used) Are nailed to the sole and top plate. A second plate is added after the wall is in place. EDT Wall and Ceiling Construction
21
Frame Wall Construction
The distance from the top of the subfloor to the bottom of the ceiling joists is usually 8'-1 1/2". This distance provides a finished wall height of 8'-O". EDT Wall and Ceiling Construction
22
Frame Wall Construction
Openings for doors and windows are framed before the wall is moved to the vertical position. The door and window opening must be framed with headers, to span the opening. EDT Wall and Ceiling Construction
23
Frame Wall Construction
Two methods are used in constructing headers Solid blocking. Cripple construction. EDT Wall and Ceiling Construction
24
Frame Wall Construction
Solid blocking header The header size is increased. The header completely fills the space from the top of the rough opening to the top plate. EDT Wall and Ceiling Construction
25
Frame Wall Construction
Solid blocking header construction Various methods are used 1. Two 2 x 12 pieces of lumber are nailed together with a piece of 1/2" plywood between them to form a 3 1/2" thick header. This method reduces construction time, but increases shrinkage. 2. Solid 4 x 6, 4 x 8, 4 x 10 wood members may also be used. Trend is to use solid members. Faster, saves construction labor costs. EDT Wall and Ceiling Construction
26
EDT 300 - Wall and Ceiling Construction
27
EDT 300 - Wall and Ceiling Construction
28
Frame Wall Construction
Header Construction - Cripple and Trimmer Older method. Uses cripple studs and trimmers firmly nailed to the sole and top plates. Cripples are studs that are not full length due to a wall opening. Trimmers are studs that support the header over an opening in the wall. EDT Wall and Ceiling Construction
29
EDT 300 - Wall and Ceiling Construction
30
EDT 300 - Wall and Ceiling Construction
31
EDT 300 - Wall and Ceiling Construction
32
EDT 300 - Wall and Ceiling Construction
33
Frame Wall Construction
Corner bracing is required by most codes. Two methods of bracing are used. Diagonal corner braces Plywood sheathing EDT Wall and Ceiling Construction
34
Frame Wall Construction
Diagonal corner braces Use 1 x 4 inch wood material or Metal straps Installed from the top corner of the wall down to the sole plate. EDT Wall and Ceiling Construction
35
EDT 300 - Wall and Ceiling Construction
36
Frame Wall Construction
Plywood Sheathing Bracing A sheet of 1/2" plywood Nailed to the studs at each corner EDT Wall and Ceiling Construction
37
EDT 300 - Wall and Ceiling Construction
38
Frame Wall Construction
Typical methods of framing used to form exterior wall corners EDT Wall and Ceiling Construction
39
EDT 300 - Wall and Ceiling Construction
40
EDT 300 - Wall and Ceiling Construction
41
EDT 300 - Wall and Ceiling Construction
42
Frame Wall Construction
The corner must provide A nailing edge for the interior wall material Drywall (gypsum board). Adequate support for the structure. EDT Wall and Ceiling Construction
43
Frame Wall Construction
Interior frame walls are constructed the same way as exterior walls. Sole plates. Bottom of wall One 2 x 4 member on side. Studs 2 x 4 wall members Double top plates. Top of wall Two 2 x 4 members on side. EDT Wall and Ceiling Construction
44
Frame Wall Construction
Interior walls Must be securely fastened to the exterior walls that they intersect. A nailing edge must be provided for the plaster base, drywall, or paneling. Use a 2 x 6 secured to cross blocking. Double the exterior wall studs at the intersection of the partition. The same arrangement is used at the intersection of all interior walls. EDT Wall and Ceiling Construction
45
EDT 300 - Wall and Ceiling Construction
Exterior Walls EDT Wall and Ceiling Construction
46
EDT 300 - Wall and Ceiling Construction
Interior Walls EDT Wall and Ceiling Construction
47
Frame Wall Construction
Rough openings for windows and doors Are dimensioned to the center of the opening when located in a frame wall. Specific dimensions of doors and windows are usually provided by the window and door schedule. The width is listed first and The height is listed second. EDT Wall and Ceiling Construction
48
Frame Wall Construction
The rough opening height of most doors is 6'-10". Tops of all windows are usually the same distance above the floor as doors. EDT Wall and Ceiling Construction
49
Frame Wall Construction
Each wall opening requires a header above the opening. The header supports the weight above. The length of the header will be equal to The width of the rough opening + The thickness of two trimmers. EDT Wall and Ceiling Construction
50
EDT 300 - Wall and Ceiling Construction
51
EDT 300 - Wall and Ceiling Construction
The exterior and interior walls are Erected Plumbed (straightened for level) Braced Top plates are added. Ceiling joists are then put in place. Ceiling joists are usually positioned across the width of the house and in the same direction as the rafters. EDT Wall and Ceiling Construction
52
EDT 300 - Wall and Ceiling Construction
The size of ceiling joists required will depend on: The load to be supported. Span distance. Wood specie. Spacing of joists. Grade of lumber used. EDT Wall and Ceiling Construction
53
EDT 300 - Wall and Ceiling Construction
Ceiling construction is similar to floor construction. The main differences A header is not required around the perimeter Smaller lumber is used. (smaller loads). EDT Wall and Ceiling Construction
54
EDT 300 - Wall and Ceiling Construction
Long ceiling joist spans may require a bearing wall partition or beam. If a beam is used, it may be located below the joists or placed flush with them using ledger strips. EDT Wall and Ceiling Construction
55
EDT 300 - Wall and Ceiling Construction
56
EDT 300 - Wall and Ceiling Construction
The upper corner of the ceiling joists often interferes with the roof slope. To prevent this interference, the corner is usually cut to match the slope. EDT Wall and Ceiling Construction
57
EDT 300 - Wall and Ceiling Construction
58
EDT 300 - Wall and Ceiling Construction
Roof trusses are being used in residential construction to a much greater extent. This approach eliminates the traditional ceiling joist and rafter. EDT Wall and Ceiling Construction
59
Framing Considerations
An access hole must be provided in the ceiling (usually in closet) to afford entry to the attic. The size of this opening may be as small as 2 feet square. Framing around the opening is the same as for openings in the floor. Double headers are used for large holes (for example, when installing a disappearing stairway) but are usually not required for minimum size openings. EDT Wall and Ceiling Construction
60
Framing Considerations
Several areas in the house that require special framing. Openings for heating ducts. Wall backing for various fixtures. Extra support for the bathtub. EDT Wall and Ceiling Construction
61
EDT 300 - Wall and Ceiling Construction
62
EDT 300 - Wall and Ceiling Construction
63
EDT 300 - Wall and Ceiling Construction
64
Framing Considerations
Framing for a bay window presents special problems. For a bay window, the floor joists extend beyond the wall to provide support for the unit. If the bay window is to be set at right angles to the joists, then cantilevered joists should be used. EDT Wall and Ceiling Construction
65
EDT 300 - Wall and Ceiling Construction
66
Masonry Wall Construction
EDT Wall and Ceiling Construction
67
Masonry Wall Construction
A masonry wall is constructed entirely of brick, concrete block, stone, clay tile, terra cotta, or a combination of these materials. EDT Wall and Ceiling Construction
68
Masonry Wall Construction
Walls that require more than one thickness of masonry must be bonded together. They may be bonded by using: a header course every 16" vertically corrugated metal wall ties in the mortar joints. Metal wall ties should be placed no more than 16" apart vertically and 32" horizontally. EDT Wall and Ceiling Construction
69
EDT 300 - Wall and Ceiling Construction
70
EDT 300 - Wall and Ceiling Construction
71
Masonry Wall Construction
Solid masonry walls for residential construction are usually 8" thick. Concrete block walls (cavity walls) are popular in many sections of the country. Block walls are relatively inexpensive to construct and a variety of textures and designs are possible. EDT Wall and Ceiling Construction
72
Masonry Wall Construction
One disadvantage of a solid masonry wall is that furring strips (usually 2" x 2" or 1 " x 3") are required on the inside of the wall if dry wall, plaster, or paneling is used. Insulation may be added. EDT Wall and Ceiling Construction
73
EDT 300 - Wall and Ceiling Construction
74
EDT 300 - Wall and Ceiling Construction
75
Masonry Wall Construction
Solid brick and stone walls have been used extensively in years past, but because of the cost of construction they are diminishing in importance for residential purposes. The same exterior effect may e obtained with a brick or stone veneer on frame construction and the wall will be better insulated, less expensive to construct and present fewer construction problems. EDT Wall and Ceiling Construction
76
Masonry Wall Construction
Floor joists are placed directly into openings in solid brick and stone walls. Each joist is cut at an angle on the end to prevent toppling the wall if the house should catch fire. The cut is known as a firecut. EDT Wall and Ceiling Construction
77
EDT 300 - Wall and Ceiling Construction
78
Masonry Wall Construction
Stonework involves artistry on the part of the mason due to the various size and texture of the material ordinarily used. EDT Wall and Ceiling Construction
79
Masonry Wall Construction
Stonework is commonly referred to as ashlar or rubble. Ashlar stonework uses dressed, cut, or squared stones. Each stone is a specific size and fits in an exact place in the pattern EDT Wall and Ceiling Construction
80
EDT 300 - Wall and Ceiling Construction
81
Masonry Wall Construction
Rubble stonework is made up of irregular shaped stones. If the stones are basically flat, the result may look like courses of stone, then the term coursed rubble is applied. EDT Wall and Ceiling Construction
82
EDT 300 - Wall and Ceiling Construction
83
Masonry Wall Construction
Another type of rubble stonework is called uncoursed cobweb or polygonal rubble. These stones are dressed with relatively straight edges and are selected to fit a particular place. EDT Wall and Ceiling Construction
84
EDT 300 - Wall and Ceiling Construction
85
EDT 300 - Wall and Ceiling Construction
86
Masonry Wall Construction
Masonry veneer is usually placed one inch away from the frame wall to: provide a dead air space for insulation provide a means of escape for moisture which condenses on the inside of the masonry. EDT Wall and Ceiling Construction
87
Masonry Wall Construction
The term veneer is commonly used to indicate that a less expensive or desirable material has been covered up with some type of facing material. The facing is usually 4" thick (but may range from approximately 1 " to 6"). The veneer does not help support the weight of the building. EDT Wall and Ceiling Construction
88
EDT 300 - Wall and Ceiling Construction
89
EDT 300 - Wall and Ceiling Construction
90
EDT 300 - Wall and Ceiling Construction
91
Masonry Wall Construction
Flashing and termite shields should be used at the base of solid masonry or brick veneer walls. Flashing prevents moisture from entering the structure. Termites are a threat in a large part of the country and cause millions of dollars in damage to homes each year. EDT Wall and Ceiling Construction
92
EDT 300 - Wall and Ceiling Construction
93
EDT 300 - Wall and Ceiling Construction
94
Masonry Wall Construction
If a solid masonry wall is used, the top plate must be anchored securely to the wall. Anchor bolts are placed between the bricks and bolt the plate in place. A lintel block is used in concrete block construction and anchor bolts are cast in place. The plate is then secured by the use of bolts. EDT Wall and Ceiling Construction
95
EDT 300 - Wall and Ceiling Construction
96
EDT 300 - Wall and Ceiling Construction
97
EDT 300 - Wall and Ceiling Construction
Brick Names and Sizes Brick is a fired clay product. The color is ordinarily determined by the natural color of the clay, but sometimes earth colors are added to produce a wider variety. Brick may be purchased in single colors or in a mixture to produce a blend. EDT Wall and Ceiling Construction
98
EDT 300 - Wall and Ceiling Construction
Brick Names and Sizes There are two basic types of brick used for wall construction; common brick and face brick. Face brick is usually uniform in size and has sharp corners and lines. Common brick is not as uniform in size and color and may have a lip on one or more edges. EDT Wall and Ceiling Construction
99
EDT 300 - Wall and Ceiling Construction
Brick Names and Sizes In recent years, common brick has been used more widely as a facing material. They produce a rustic character which is quite different from the face brick. The texture is much more distinct. They look especially good with a deep rake joint which accents the individual character of each brick. EDT Wall and Ceiling Construction
100
EDT 300 - Wall and Ceiling Construction
Brick Names and Sizes The names of brick shapes are well established, but sizes are not standardized. EDT Wall and Ceiling Construction
101
EDT 300 - Wall and Ceiling Construction
Brick Names and Sizes Specific terms apply to the position or way the brick is laid. Note that the term "stretcher” "header," etc. applies to the position of the brick in the wall and not the type or size of the brick. EDT Wall and Ceiling Construction
102
EDT 300 - Wall and Ceiling Construction
103
EDT 300 - Wall and Ceiling Construction
Brick Names and Sizes Numerous types of mortar joints are used in brickwork. Masons have tools designed specifically for making the joints. EDT Wall and Ceiling Construction
104
EDT 300 - Wall and Ceiling Construction
105
EDT 300 - Wall and Ceiling Construction
106
EDT 300 - Wall and Ceiling Construction
107
EDT 300 - Wall and Ceiling Construction
Brick Names and Sizes Some brick bonds are recognized standards. The running bond is used extensively in brick veneer construction. The common bond is popular for solid masonry walls. EDT Wall and Ceiling Construction
108
EDT 300 - Wall and Ceiling Construction
109
EDT 300 - Wall and Ceiling Construction
110
EDT 300 - Wall and Ceiling Construction
111
EDT 300 - Wall and Ceiling Construction