EPT 221 Engineering Design Introduction to Engineering Economics
2
Introduction What is engineering economics? A subset of economics for application to engineering projects. Engineers seek solution to problems, and the economic viability of each potential solution is normally considered along with the technical aspects. Scope of lecture: Time value of money Interest Evaluating economic alternatives Breakeven economics
3
Objectives of the chapter: 1. to introduce students to various economic/accounting terms that engineers need to be aware of i.e. time value for money, interest, cash flow diagrams etc 2. to be familiar and apply the various methods available in making decisions on the economic aspects of an engineering project
4
Time value of money (TVM) A very important concept in engineering economics: i.e. money obtained sooner is more valuable than money obtained later, and money spent sooner is more costly than money spent later. Having the money sooner: Provides the ability to invest or otherwise use the money during intervening years Eliminates the risk that the money might not be available next year Eliminating the risk that inflation might reduce the purchasing power of the money during the next year.
5
How TVM effects design choices? Designs have: Different purchase prices Different operating and maintenance costs Different expected lifetimes
6
Interest What is interest? - a rental amount charged by financial institutions for the use of money 2 types of interest: 1. simple interest 2. compound interest Interest = total amount owed – principal amount
7
Simple interest: interest on the principal only Interest = Principal amount x number of interest periods x interest rate I = Pni Compound interest: interest on the principal and the unpaid interest
8
Interest rate, i Interest rate :the percentage of the principal which is paid as the interest over a certain period of time
9
Example: Suppose that RM50,000 is borrowed from a bank with an interest rate of 8% per annum. How much would the interest be at the end of 2 years? How much would the borrower have to pay to the bank at the end of the 2 years?
10
Cash flow diagram A graphical representation of the cash flow with time Inflows: arrows pointing upwards Outflows: arrows pointing downwards
11
Interest Formulae 1. single payment compound amount 2. single payment present worth 3. uniform series compound amount 4. capital recovery 5. nominal interest 6. uniform series compound amount 7. uniform series sinking fund 8. gradient series
12
n = number of interest periods i = interest rate per period P = monetary values at the present F = monetary value at a future time A = series of monetary amounts, equal in value I = interest earned during an interest period
13
1. Single payment compound amount F = ? 01234 n-2 n-1n P period
14
Example A loan of RM1,000 is made at an interest of 12% for 5 years. The principal and interest are due at the end of the fifth year. Calculate how much you have to pay after the 5 years. Use formula. Use factor.
15
Using a table. YearAmount at start of year (RM) Interest at end of year (RM) Owed amount at end of year (RM) Payment (RM) 1100012011200 2 134.41254.40 3 150.5281404.9280 4 168.59141573.51940 5 188.82231762.3417
16
2. Single payment present worth F 01234 n-2 n-1n P=? period
17
Example Let the future sum F=RM1,000 and the interest rate i=12%. The number of periods is n= 4 years. Find the present amount of the principal sum. Determine the present worth of a machine that will be sold 15 years from now for $10,000. assume that given interest rate is 6 percent per year.
18
P = ? 01234 n-2 n-1n A period AAAAAA 3. Uniform series present worth
19
Example Determine the present value of a machine tool that saves $500 a year for 25 years. Assume that the interest rate is 6% per year over the life of the tool. Use formula or Use the table at the end of your text book to find (P/A) at i=6% and n=25.
20
4. Capital recovery (equal-payment-series capital-recovery factor) P 01234 n-2 n-1n A=? period AAAAAA
21
5. Nominal interest vs effective interest rate Nominal interest rate, r: the interest rate per year Effective interest rate, i: the interest rate per interest period
22
Nominal interest vs effective interest i = effective interest rate r = nominal interest rate m = interest periods per year y = number of years n=total number of interest periods
23
6. Uniform series compound amount F = ? 01234 n-2 n-1n A period AAAAAA
24
7. Uniform series sinking fund F 01234 n-2 n-1n A=? period AAAAAA
25
8. Uniform Gradient Series Factor Often periodic payments do not occur in equal amounts and may increase or decrease by constant amounts (eg. RM10, RM110, RM210, etc….) The gradient (G) is a value in the cash flow that starts with 0 at the end of year 1, G at the end of year 2, etc.
26
Gradient series P = ? 01234 n-2 n-1 n A period A+2G A+4G A+3G A+(n-2)G A+(n-1)G A+(n-3)G
27
Summary table of interest factors
28
Evaluating economic alternatives 5 methods: 1. present-worth method 2. future worth method 3. equivalent-uniform annual-worth method 4. rate-of-return method 5. payback period
29
1. Present worth method The option/alternative with the most positive PW is the best alternative
30
Example Our company has received a vendor quote stipulating that it will supply 5,000 parts per year for the next 3 years at $25,000 per year. Our manufacturing engineering department, however estimates that is the company invests in a new machine tool for $10,000, we can produce the same 5,000 parts per year for an annual cost of $18,000 per year. Assume that the interest rate is 8% per year; which alternative is more economical, make or buy?
31
Solution Using the single payment present worth method: Vendor: PW=$-25,000(P/F, 8%, 1)+$-25,000(P/F,8%,2)+$- 25,000(P/F,8%,3) =$-25,000(1+0.08) -1 +$-25,000(1+0.08) -2 +$-25,000(1+0.08) -3 = $-64,425 Own company: PW=$-10,000 + $-18,000(P/F,8%,1)+$- 18,000(P/F,8%,2)+$-18,000(P/F,8%,2) = $-56,386 Using the uniform series present worth: Vendor: PW=
32
Least common multiple $30,000 $45,000 years 0123456 0123456 $45,000 $30,000 least common multiple Used for alternatives with unequal lives
33
Example Machine tool A will last 3 years and cost $45,000 to replace. Machine B costs $30,000, performs as well as the other machine, but need to be replaced every 2 years. Which machine is better assuming the interest rate is 6% per year?
34
2. Future worth method The alternative with the most positive FW is chosen.
35
3. Equivalent annual worth method (EUAW) The alternative with the most positive EUAW is chosen. EUAW with no salvage value (SV): Salvage value is the remaining value of an amount after depreciation EUAW with salvage value (SV):
36
Advantage: alternatives that have different lives do not have to be compared using the least common multiple of the lives.
37
Example A new machine initially costs $40,000 and $10,000 per year to operate. The machine has a 10-year life and $1000 salvage value. Assume that the interest rate is 10% per year. As an alternative, the company can lease the machine for $7,500 per year for 10 years. Use the EUAW method to determine which alternative is the most economical.
38
4. Rate of return method (ROR) The ratio of money gained or lost on an investment relative to the amount of money invested. The alternative with the greatest return is chosen. Use the ROR to find the special interest rate i* when the present value of the cash flows is zero.
39
Example The redesign of an existing product will require a $50,000 investment but will return $16, 719 each year for years 1 through 5. The company has a minimum attractive rate of return of 25%. Use ROR method to determine whether to complete the redesign. Solution PW = $-50,000 + $16,719(P/A,i*%,5)=0.0 P/A because the return is the same throughout the 5 years. So, (P/A, i*%,5)=$50,000/$16,719=2.991 Go to the tables at the end of the text book, and find what is the i* at P/A = 2.991 and n=5. i*=20% which is less than the minimum attractive rate of return of 25%. So, is redesigning a viable option or not?
40
5. Payback period is the length of time required for the cash flow to recover the initial investment. Simple payback period (ignores the time value of money): Discounted payback period (DPP): the number of years for the discounted cash flow to equal to zero.
41
Breakeven Economics Is used to determine whether a proposed product would be profitable compared to modifying an existing product or just the profitability of a product. Breakeven point, q*: the point at which cost or expenses (loss) and income (profit) are equal i.e. no net loss or gain
42
Fixed cost, FC: expenses that do not vary with production. Eg: utility bill, rent, administrative labour, advertising, legal, building depreciation Variable cost, VC: expenses that depends on the amount product manufactured. Eg: raw materials, production labour. Revenue (income), R= Total revenue = rq r = revenue per unit q = quantity of product sold v = variable cost per unit Profit = difference between revenue and costs = R =TC = rq – FC - vq
43
Breakeven analysis Cost FC TC R q q* Breakeven quantity Loss Profit breakeven point If TC>R loss If R>TC profit If q>q* profit If q*>q loss q*: the specific volume of production that the profit is zero.
44
Example The company receives $5 per unit sold and the variable costs to make each unit are $3.50. Determine the fixed costs such that the company will break even when making 20,000 units.
45
Summary Engineering economic analyses should consider the time value of money Interest factor formulas and tables are useful in evaluating alternatives The PW and FW methods can be used to evaluate alternatives having different lives by using the least common multiple of years. The EUAW method is preferred because it has the advantage of not requiring the use of the least common multiple. The breakeven point is that level of production (and sales) that results in a zero profit
46
Exercise: Due 17 th October 2008 (NO LATE SUBMISSIONS WILL BE ENTERTAINED!!!) Textbook: Rudolph J. Eggert, Engineering Design Question number: 16, 24, 26, 33