Download presentation
Presentation is loading. Please wait.
Published byCameron Spencer Modified over 9 years ago
1
October 26, 2009 Citizens’ Oversight Committee Presentation to the Presented By: Kelvin Okino Bernards’ Program Director
2
COC Presentation October 26, 2009 Overview Aerial Views of Chaffey College-Rancho Cucamonga Early Construction Activities Completed Projects 2002-2008 Completed Projects in 2007 Completed Projects in 2008 Completed Projects in 2009 Projects under Construction Projects in Bid and Award Projects in Design Projects in Planning Program Schedule Status of Measure ‘L’ Funds
3
Chaffey Community College Aerial View-1958 COC Presentation October 26, 2009 Rancho Cucamonga Campus
4
Chaffey Community College Aerial View-2009 COC Presentation October 26, 2009 Rancho Cucamonga Campus
5
COC Presentation October 26, 2009 Early Construction Activities Groundbreaking—Alta Loma Campus-1958
6
COC Presentation October 26, 2009 Early Construction Activities Construction—Gymnasium-1958
7
COC Presentation October 26, 2009 Early Construction Activities Construction—1958
8
COC Presentation October 26, 2009 Completed Projects 2002-2008 Renovate/Paint Auto Tech Lab Infrastructure/Campus Theme Environmental Impact Report Renovate Athletics Office Scoreboards Snack Bar Track & Field Timer Stadium Flag Pole Rad Tech Retrofit San Antonio Comm. Hosp./CNA Chino Master Plan Vocational Education-Phase I Wargin Hall-Phase I Visitor’s Restroom/ADA Access Science Complex Site work Theater Fire Alarm Bookstore Loading Dock North Parking Lot Irrigation North Parking Lot Landscaping ATL Landscaping Nature Preserve Fence Central Plant, Phase I College Drive Softball Field Fontana, Phase 2 Wilson/College Dr. Intersection Marie Kane Center for Student Services/ Administration Theatre-Phase I North Parking Lot Science Complex Berz Excellence Building College Drive Landscaping Maintenance Yard Drainage Agricultural Demonstration Area Skills Road Extension Fire Lane/Science Site Lighting New Marquee Physical, Health, and Life Science Health and Life Science Re-Roof New Elevator Tower Parking Lot 12
9
COC Presentation October 26, 2009 Completed Projects in 2007 Science Complex Four Buildings – 27,000 sq. ft. – Classrooms, Lab Spaces Berz Excellence Building Two Story-14,738 sq. ft. – Classrooms Marie Kane Center for Student Services/ Administration Two Story-24,828 sq. ft. – Student Services Ralph M. Lewis Center 10,140 sq. ft. – Student Services/Classrooms
10
COC Presentation October 26, 2009 Completed Projects in 2007 Berz Excellence Building Science Complex Rancho Cucamonga Campus Marie Kane Center for Student Services/ Administration
11
COC Presentation October 26, 2009 Completed Projects in 2007 Science Complex Science Complex Looking Northeast Contractor: Soltek Pacific Architect: Harley Ellis Devereaux Completed: November 2007 Scope: Four Buildings-Classrooms, and Lab Spaces-27,000 sq. ft.
12
COC Presentation October 26, 2009 Completed Projects in 2007 Berz Excellence Building Berz Excellence Building Looking North Contractor: RC Construction Services Architect: Harley Ellis Devereaux Completed: November 2007 Scope: Two Story-14,738 sq. ft. -Classrooms
13
COC Presentation October 26, 2009 Completed Projects in 2007 Marie Kane Center for Student Services /Administration Marie Kane Center for Student Services/Administration Looking North Contractor: USS Cal Builders Architect: GKK Works Completed: December 2007 Scope: Two Story-24,828 sq. ft.-Student Services
14
COC Presentation October 26, 2009 Completed Projects in 2007 Fontana Campus Ralph M. Lewis Center
15
COC Presentation October 26, 2009 Completed Projects in 2007 Ralph M. Lewis Center Contractor: PCM Construction Architect: Jorgensen Architects Completed: February 2007 Scope: 10,140 sq. ft. –Student Services/Classrooms Ralph M. Lewis Center Looking Northeast
16
COC Presentation October 26, 2009 Completed Projects in 2008 New Elevator Tower New Elevator Tower for Accessibility from the VSS Building to the Marie Kane Center for Student Services/Administration Parking Lot 12 New Parking Lot for Accessibility to the Marie Kane Center for Student Services/Administration New Marquee New High Visibility Sign at the Main College Entrance Physical, Health, and Life Sciences Renovation Renovation/Modernization of Existing Classrooms Health and Life Science Re-Roof Installation of New Standing Seam Metal Roof
17
COC Presentation October 26, 2009 Completed Projects in 2008 Physical, Health, and Life Sciences Renovation Health and Life Science Re-Roof New Marquee Parking Lot 12/ New Elevator Tower Rancho Cucamonga Campus
18
Completed Projects in 2008 COC Presentation October 26, 2009 New Elevator Tower Contractor: EDGE Development, Inc. Architect: GKK Works Completed: May 2008 Scope: New Elevator Tower for Accessibility New Elevator Tower Looking Northwest
19
Completed Projects in 2008 COC Presentation October 26, 2009 Parking Lot 12 Contractor: EDGE Development, Inc. Architect: GKK Works Completed: May 2008 Scope: New Parking Lot for Accessibility Parking Lot 12 Looking West
20
Completed Projects in 2008 COC Presentation October 26, 2009 New Marquee New Marquee Looking North Contractor: Quiel Bros. Signs Architect: HGA Architects Completed: June 2008 Scope: New Entrance Marquee Sign
21
Completed Projects in 2008 COC Presentation October 26, 2009 Physical, Health, and Life Sciences Renovation Physical, Health, and Life Sciences Renovation Looking North Contractor: PW Construction Architect: WWCOT Architects Completed: August 2008 Scope: Interior Renovations/Modernization
22
Completed Projects in 2008 COC Presentation October 26, 2009 Health and Life Science Re-Roof Contractor: Best Contracting Architect: WWCOT Architects Completed: August 2008 Scope: New Standing Seam Metal Roof Health and Life Science Re-Roof Looking South
23
Completed Projects in 2009 COC Presentation October 26, 2009 Library Lawn/Fontana Phase II Landscaping New Landscaping and Irrigation on the Fontana and Rancho Cucamonga Campuses Physical Science Complex Roof Replacement Installation of a New Standing Seam Metal Roof Language Arts/Social Science-Energy Project An Energy Conservation Project with New Lighting and HVAC Systems New Air Handling Unit and Lighting Fontana Phase III Parking Lot New 459 Stall Parking Lot in Preparation for the New Academic Building
24
Completed Projects in 2009 COC Presentation October 26, 2009 Library Lawn Landscape and Irrigation Rancho Cucamonga Campus
25
Completed Projects in 2009 COC Presentation October 26, 2009 Library Lawn Landscaping-Rancho Cucamonga Campus Library Lawn Landscaping-Rancho Cucamonga Campus Looking Northwest Contractor: Landforms Landscape Construction Architect: Steven Frenken Landscape Architecture Completed: August 2009 Scope: New Landscaping and Irrigation
26
Completed Projects in 2009 COC Presentation October 26, 2009 Fontana Campus Fontana Phase II Landscape and Irrigation
27
Completed Projects in 2009 COC Presentation October 26, 2009 Fontana Phase II Landscaping-Fontana Campus Fontana Phase II Landscaping-Fontana Campus Looking Northeast Contractor: Landforms Landscape Construction Architect: Steven Frenken Landscape Architecture Completed: August 2009 Scope: New Landscaping and Irrigation
28
Completed Projects in 2009 COC Presentation October 26, 2009 Physical Science Complex Roof Replacement Rancho Cucamonga Campus
29
Completed Projects in 2009 COC Presentation October 26, 2009 Physical Science Complex Roof Replacement Physical Science Complex Roof Replacement Looking West Contractor: Cabral Roofing and Waterproofing Corp. Architect: WWCOT Architects Completed: August 2009 Scope: New Metal Seam Standing Roof
30
Completed Projects in 2009 Social Science Building-Energy Upgrades Rancho Cucamonga Campus COC Presentation October 26, 2009 Language Arts Building-Energy Upgrades
31
Completed Projects in 2009 COC Presentation October 26, 2009 Social Science Building-Energy Upgrades Social Science Building-Energy Upgrades Looking North Contractor: Siemens Architect: P2S Engineering, Inc. Completed : August 2009 Scope: New Air Handling Unit
32
Completed Projects in 2009 COC Presentation October 26, 2009 Language Arts Building-Energy Upgrades Language Arts Building-Energy Upgrades Looking North Contractor: Siemens Architect: P2S Engineering, Inc. Completed : August 2009 Scope: Installation of Lighting Upgrades
33
Completed Projects in 2009 COC Presentation October 26, 2009 Fontana Campus Fontana Phase III Parking Lot
34
Completed Projects in 2009 COC Presentation October 26, 2009 Fontana Phase III Parking Lot Fontana Phase III Parking Lot Looking South Contractor: Bogh Engineering, Inc. Architect: HMC Architects Completed: August 2009 Scope: Construction of a New 459 Stall Parking Lot
35
Projects Under Construction Data and Telecom Cabling Data and Fiber Cabling Three Buildings Estimated Completion: October 2009 Visual and Performing Arts Complex Renovation / New Buildings Project Estimated Completion: November 2009 (Contract: Aug. 09) Physical Education Athletics-New Gymnasium New 22,000 sq. ft. Gymnasium Estimated Completion: December 2009 COC Presentation October 26, 2009
36
Data and Telecom Cabling Data and Telecom Cabling Visual and Performing Arts Complex Physical Science Building New Gymnasium Estimated Completion: October 2009 Three Phases Architect/Engineer: P2S Engineering, Inc. General Contractor: T & D Communications, Inc. Original Contract Amount: $ 154,882 COC Presentation October 26, 2009
37
Data and Telecom Cabling New Gymnasium Physical Science Building COC Presentation October 26, 2009 Rancho Cucamonga Campus VPA Building F Performing Arts Building VPA Building B Fashion Building VPA Building C Ceramics Building VPA Building E Music Building
38
Data and Telecom Cabling Progress Photos COC Presentation October 26, 2009 Installation of new splice case for the Stadium Press Box. Looking West Installation of pull box for the New Gymnasium media. Looking West
39
Visual and Performing Arts Complex Renovation / New Buildings Project Estimated Completion: Nov. 2009 (Contract: Aug. 09) Phased Milestones Phase 1: Building F, Site/Utilities – November 2, 2009 (August 22, 2009) Phase 2A: Building E, Utility Connections – (December 30, 2008) Phase 2B: Building E, Site/Utilities –August 4, 2009 (June 7, 2009) Phase 2C: Theater Loading Dock Access – (August 22, 2008) Phase 3: Renovation Courtyard B/C – (May 24, 2008) Phase 4A: Renovations Ceramics Yard – (August 9, 2008) Phase 4B: Building B/C Renovations – (July 30, 2009) Phase 5: Renovation Accessible Route – (June 21, 2008) Architect: HGA Architects General Contractor: ProWest Constructors Contract Amount: $22,145,000 COC Presentation October 26, 2009
40
Visual and Performing Arts Complex COC Presentation October 26, 2009 Performing Arts Building Rendering (Exterior)
41
Visual and Performing Arts Complex F CB E COC Presentation October 26, 2009 Rancho Cucamonga Campus VPA Building F Performing Arts Building VPA Building B Fashion Building VPA Building C Ceramics Building VPA Building E Music Building
42
Visual and Performing Arts Complex Progress Photos-Fashion Studio (Bldg. B) COC Presentation October 26, 2009 Completed classroom at the Fashion Studio. Looking West Completed paint and signage at the Fashion Studio. Looking West
43
Visual and Performing Arts Complex Progress Photos-Ceramics Studio (Bldg. C) COC Presentation October 26, 2009 Completed classroom at the Ceramics Studio. Looking Northeast Completed paint and signage at the Ceramics Studio. Looking East
44
Visual and Performing Arts Complex Progress Photos-Music Building (Bldg. E) COC Presentation October 26, 2009 Completed acoustical clouds and sound board. Looking Southeast Completed landscaping and finishes. Looking East
45
Visual and Performing Arts Complex Installation of bi-fold door glazing. Looking Southeast Progress Photos-Performing Arts Building (Bldg. F) COC Presentation October 26, 2009 Construction of site work. Looking Northeast
46
Visual and Performing Arts Complex Installation of finishes at the Photography Work Room. Looking East Installation of casework at the Material Library. Looking North Progress Photos-Performing Arts Building (Bldg. F) COC Presentation October 26, 2009
47
Physical Education Athletics – New Gym New 22,000 sq. ft. Gymnasium Estimated Completion: December 2009 Basketball/Volleyball Courts Locker Rooms Snack Bar Bleachers for 984 Individuals Architect: NTD Architecture General Contractor: EDGE Development, Inc. Contract Amount: $8,560,543 COC Presentation October 26, 2009
48
Physical Education Athletics – New Gym Project Rendering(Aerial Perspective) COC Presentation October 26, 2009
49
Physical Education Athletics – New Gym COC Presentation October 26, 2009 Project Rendering (Main Entrance Perspective)
50
Physical Education Athletics – New Gym Physical Education Athletics- New Gymnasium COC Presentation October 26, 2009 Rancho Cucamonga Campus
51
Physical Education Athletics – New Gym Progress Photos COC Presentation October 26, 2009 Construction of site work. Looking East Construction of New Gymnasium elevator tower. Looking South
52
Physical Education Athletics – New Gym Progress Photos COC Presentation October 26, 2009 Installation of drywall at the Locker Room. Looking East Installation of New Gymnasium main floor. Looking East
53
Projects in Bid and Award COC Presentation October 26, 2009 Physical Education Athletics - Renovation Architect: NTD Architecture Anticipated Bid Release: October 2009 One story with Mezzanine-30,843 sq. ft. Construction Scheduled to Begin February 1, 2010
54
Projects in Bid and Award Physical Education Athletics- Renovation COC Presentation October 26, 2009 Rancho Cucamonga Campus
55
Projects in Design COC Presentation October 26, 2009 Campus Center West Architect: MDA Johnson Favaro Anticipated Bid Release: Spring 2010 Two Story Structure-16,454 sq. ft. Fontana Phase III Academic Building Architect: HMC Architects Anticipated Bid Release: Fall 2009 Two Story Structure-30,400 sq. ft. Omnitrans Transportation Center Architect: HMC Architects Anticipated Construction: Summer 2010 377 Parking Stalls for Vehicles and a Dedicated Bus Drop-Off Zone
56
Projects in Design Campus Center West COC Presentation October 26, 2009 Omnitrans Transportation Center Rancho Cucamonga Campus
57
Campus Center West Anticipated Bid Release: Spring 2010 COC Presentation October 26, 2009
58
Omnitrans Transportation Center Omnitrans (Site Options) / Architect: HMC Architects COC Presentation October 26, 2009 Rancho Cucamonga Campus
59
Projects in Design Fontana Phase III Academic Building COC Presentation October 26, 2009 Fontana Campus
60
Fontana Phase III Academic Building COC Presentation October 26, 2009 Anticipated Bid Release: Fall 2009
61
Projects in Planning COC Presentation October 26, 2009 Language / Liberal Arts and Letters Library Remodel/Expansion Physical Science Northwest/Southeast Section Remodel Central Plant Build-Out
62
Projects in Planning Library Remodel/ Expansion Central Plant Build-Out Physical Science Northwest/ Southeast Section Remodel COC Presentation October 26, 2009 Language/Liberal Arts and Letters Rancho Cucamonga Campus
63
Program Schedule COC Presentation October 26, 2009 Measure ‘L’ Build-Out Plan Scheduling of remaining projects has been developed and is currently under review by the Chaffey Community College District
64
Summary of Construction Costs Construction Costs by Individual Projects as of October 19, 2009 COC Presentation October 26, 2009 Projects Under Construction CONSTRUCTION COSTS ABCDEF Contract #DescriptionContractorConstruction Completion %Original Contract Board Approved Change Orders Current Contract AmountCurrent CO%Potential Change OrdersProjected Total CO% [A+B][B/A]-1 [E+B]/A 06P40Educational Excellence CenterRC Construction100.00% $ 5,277,600 $ 367,463 $ 5,645,0636.96% 337Science ComplexSoltek Pacific100.00% $ 16,511,000 $ 1,090,091 $ 17,601,0916.60% 06P21Student Services & AdministrationUSS Cal Builders100.00% $ 9,436,750 $ 479,631 $ 9,916,3815.08% 07P91Parking Lot 12/ElevatorEdge Devlp.100.00% $ 1,897,007 $ 68,534 $ 1,965,5413.61% 07P113ADA Walkways / Fire Lane Extension4-Con100.00% $ 366,470 $ 5,095 $ 371,5651.39% 07P100PHLS BuildingsPW Construction100.00% $ 8,196,500 $ 871,357 $ 9,067,85710.63% 08P31HLS Re-RoofingBest Contracting100.00% $ 456,169 $ 16,383 $ 472,5523.59% 08P43Campus MarqueeQuiel Signs100.00% $ 180,000 $ 1,500 $ 181,5000.83% 08P11VPA ComplexProWest94.00% $ 22,145,000 $ 1,006,475 $ 23,151,4754.54% $ 492,3356.77% 08P83Library Landscape - FontanaLand Forms100.00% $ 385,000 $ (450) $ 385,0000.00% -0.12% 08P62PE Athletics- New GymEdge Devlp.86.00% $ 8,560,543 $ 249,057 $ 8,809,6002.91% $ 243,9565.76% 09P71 Data and Telecom CablingT and D Comm.96.00% $ 154,882 $ - $ 154,8820.00% $ 7,5004.84% 09P74 Fontana III Parking LotBogh Engineering98.00% $ 1,089,000 $ 42,618 $ 1,131,6183.91% $ -3.91% 09P55 Physical Science Re-RoofCabral Roofing100.00% $ 623,636 $ - $ 623,6360.00% 09P104 LA/SS Energy ProjectSiemens100.00% $ 2,700,000 $ - $ 2,700,0000.00% $ 95,1643.52% 09P103 Chino Parking LotLaird Const.100.00% $ 414,550 $ - $ 414,5500.00% $ 35,0978.47% 09P112 Chino LandscapeSierra Landscape100.00% $ 81,300 $ - $ 81,3000.00% $ 5,0006.15% $ 0 $ - $ 00.00% $ 0 $ - $ 00.00% Total for all Projects $ 78,475,407 $ 4,197,755 $ 82,673,6125.35% $ 879,0526.47% * Note: Potential CO's - This represents potential change order costs in review and discussion with the Contractors, Bernards and the Architects.
65
Summary of Funds COC Presentation October 26, 2009 Program Funds Measure L Bond Funds (Includes Rancho Cucamonga, Fontana and Chino Campuses) Fund SourceAmountPercentage of Total Fund SourceAmountPercentage of Total Original Measure L Bond$229,830,00061.30% Original Measure L Bond$229,830,00094.03% Bond Refinance Proceeds$2,300,0000.61% Bond Refinance Proceeds$2,300,0000.94% Accrued Bond Interest$12,291,6853.28% Accrued Bond Interest$12,291,6855.03% Other Funds$130,495,50034.81% Total Measure L Bond Funds$244,421,685100.00% Total Program Funds$374,917,185100.00%
66
Remaining Funds COC Presentation October 26, 2009 Program Funds Measure L Bond Funds (Includes Rancho Cucamonga, Fontana and Chino Campuses) Total Program Funds$374,917,185 100.00% Total Measure L Bond Funds $244,421,685100.00% Committed (Expensed or Encumbered) $250,725,66066.87% Committed (Expensed or Encumbered) $190,137,24877.79% Remaining Balance$124,191,52533.13% Remaining Balance$54,284,43722.21%
67
Questions and Answers
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.