Download presentation
Presentation is loading. Please wait.
Published byMaud Tate Modified over 9 years ago
1
Copyright © 2009 T.L. Martin & Associates Inc. Chapter 3 Requirements of a realistic CPM schedule.
2
Copyright © 2009 T.L. Martin & Associates Inc. A realistic CPM schedule The owner and its construction representatives need to determine a realistic contract performance period. –Too little time increases initial pricing and will result in contractor requests for time due to even minor changes. –Too much time (and if the contract disallows an early completion) initial pricing will be greater than necessary due to extended contractor overhead cost. The owner incurs time related costs as delivery of the project is prolonged: –added administrative costs –lost project use costs –lost production cost, facility rent and / or duplicate space costs.
3
Copyright © 2009 T.L. Martin & Associates Inc. A realistic CPM schedule
4
Copyright © 2009 T.L. Martin & Associates Inc. A realistic CPM schedule Forecast completion and key project milestone Document actual progress Establish reasonable payment Predict manpower needs Determine the impact of changes The project schedule affects the management effort of the project from the day it is accepted until substantial completion. If properly prepared, the schedule can:
5
Copyright © 2009 T.L. Martin & Associates Inc. A realistic CPM schedule Incorrectly forecast completion Support overpayment Incorrectly indicate that the owner’s actions will impact job progress Incorrectly indicate that the contractor and/or subcontractor will impact job progress If improperly prepared, the schedule can:
6
Copyright © 2009 T.L. Martin & Associates Inc. A realistic CPM schedule Define the individual tasks that make up the project. Define how the tasks are related to each other. The construction schedule should present a detailed understanding of any contract specified phasing and/or sequences of work. Activity identification and associated quantities of work by phase or task sequence should be accurately determined.
7
Copyright © 2009 T.L. Martin & Associates Inc. A realistic CPM schedule Activity duration should be developed based on quantities of work it represents with an attainable production. –Considering estimate detail, crew make-up and anticipated man-hours and/or equipment hours per installed unit, the bid estimate represents a good measure of likely performance unique to the contractor. Activity logic and duration should include any unique requirements defined by the contract drawings and specification.
8
Copyright © 2009 T.L. Martin & Associates Inc.Activities Defines the scope of work –Drawings –Estimates –Specifications Should be based on work quantity Separate work performed by multiple subcontractors into separate activities Owner and contractor / subcontractor should agree to activity scope and allocated work quantities Description - 48 characters (P3) Description - should contain some type of operating verb to avoid confusion
9
Copyright © 2009 T.L. Martin & Associates Inc. Planning Unit (Original Duration) PLANNING UNIT: The increment of time used to schedule a project - hours, days, weeks, or months Work starts in the morning of the (day) and finishes in the afternoon (P3) Duration of zero, work starts in the morning but completes in the afternoon of the previous period (P3) Multiple shifts cannot be defined in a work day calendar Use hours as the planning for multiple shift operations Maximum suggested duration for work tasks is 30 calendar days (20 work days)
10
Copyright © 2009 T.L. Martin & Associates Inc. Activity Identifications (“ID”) Alphanumeric values to define activities (individual work scopes) Should relate to areas and/or phases of the project Assign values for “continuous flow from left to right” Predecessor should always be lower than successor Leave a gap in sequence Should not change Required for “apples to apples” comparisons Some scheduling software change IDs and/or line numbers
11
Copyright © 2009 T.L. Martin & Associates Inc. Type of Activity Work Tasks Hammock Activities or Summary Bars Milestones Flags
12
Copyright © 2009 T.L. Martin & Associates Inc. Activity Codes Definition - Assigned to an activity to organize them into manageable groups for: Updating Reporting Analyzing Summarizing
13
Copyright © 2009 T.L. Martin & Associates Inc. Activity Codes Areas of the Project Phases Work Descriptions - Type of Work Responsibility Specification Section (CSI) Contract Type Blank - User defined as needed
14
Copyright © 2009 T.L. Martin & Associates Inc. Calendars Define work periods when activities can start and stop Global calendars - applied to all subsequent (base) calendars Project Start sets 1st day of the project in planning units Global calendar typically should be left as a seven day work week with no holidays Base calendar (31 possible in P3) - typical should be five day work week with holiday Specifications should define calendar and holidays
15
Copyright © 2009 T.L. Martin & Associates Inc. Calendars Other non-work periods: Winter shut down period Environmental shut down period Anticipated lost weather days (sometimes defined in specification)
16
Copyright © 2009 T.L. Martin & Associates Inc. Logical Relationships Relationships logically connect activities Should represent the contractors proposed sequence of construction Either predecessor or successor relationships Only one activity that has no predecessor – award / notice to proceed (“NTP”) Only one activity that has no successor - completion Four main relationship types: –Finish to Start –Start to Start –Finish to Finish –Start to Finish
17
Copyright © 2009 T.L. Martin & Associates Inc. A realistic CPM schedule The CPM should be developed following standard guidelines for useful schedules. –The schedule should depict how the project team intends to build the job. –The schedule contains one start and one ending activity. Only one activity in the schedule does not have a predecessor and only one activity does not have a successor. –The schedule should address all contract requirements. –The use of software constraints to activity timing is minimal to none. –The use of relationship leads and lags between activities is held to a minimum to none. –Activities are coded to allow easy report selection.
18
Copyright © 2009 T.L. Martin & Associates Inc. A realistic CPM schedule Allow adequate time for development review and approval Include and/or follow a comprehensive scheduling specifications in contract requirements Owners should not issue NTP until an accepted schedule is in place Owner should prepare an accurate independent resource and cost estimate for the project. Responsibility for preparing the schedule must include contractors field superintendent, subcontractors and Owner representatives. How to Assure a Quality Schedule
19
Copyright © 2009 T.L. Martin & Associates Inc. Please continue to Chapter 4 Standard CPM Smoke and Mirror Tricks (Manipulations)
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.