1
Public Involvement Meeting June 11, 2014
2
Introduce the project Provide history and current status of the project Explain the benefits of the project Review service road alternatives Present the upcoming project schedule Discuss opportunities for public input 2
3
WIS 29 is a primary route with large traffic volumes The purpose of the project is to correct geometric deficiencies associated with accesses to WIS 29 The project need is to provide reasonable access to WIS 107 and to WIS 29 3 E. 13 th Ln Big Rib River E. 15 th StHighland Dr Cattail Ave 152 nd Ave Maratech Ave Weisenberger Rd Krautkramer Rd NORTH
4
The WIS 107 interchange was originally constructed in 1992; with an asphalt overlay placed in 2011. Improvements to WIS 29, east of WIS 107, were completed in 2013. The proposed service road is an outcome of the ongoing WIS 29 freeway conversion study. 4
5
During the past eight months: initial data collection. Met with local officials from the surrounding communities. Next, we will gather input on the alternatives, and prepare preliminary environmental documentation. 5
6
Removal of access on WIS 29, near the WIS 107 interchange ramps, will help reduce an emerging safety concern. 6 1,800 feet 900 feet NORTH E. 13 th Lane Access
7
7 WIS 29 Service Road Existing: 80 vehicles per day Forecasted (2036): 2000 per day WIS 29 Service Road Existing: 80 vehicles per day Forecasted (2036): 2000 per day WIS 107 Existing: 2800 vehicles per day Forecasted (2036): 4100 per day WIS 107 Existing: 2800 vehicles per day Forecasted (2036): 4100 per day WIS 29 Existing: 16500 vehicles per day Forecasted (2036): 21100 per day WIS 29 Existing: 16500 vehicles per day Forecasted (2036): 21100 per day WIS 29 Existing: 19100 vehicles per day Forecasted (2036): 24200 per day WIS 29 Existing: 19100 vehicles per day Forecasted (2036): 24200 per day E. 13 th Ln Big Rib River E. 15 th St Highland Dr Cattail Ave 152 nd Ave Maratech Ave Weisenberger Rd Krautkramer Rd NORTH
8
8
9
9
10
Obtain public input Review the displays Ask questions Provide comments Continue design process Review public and agency comments Prepare draft environmental document Select preferred alternative More public involvement Second public involvement meeting - late 2014 Right of way acquisition - 2015 and 2016 Construction - 2017 10
11
11 Any Questions?
12
Jed Peters, P.E.Brian Andreas, P.E. WisDOT Project ManagerStrand Associates, Inc. 715-365-5731608-251-4843 Jed.Peters@dot.wi.govBrian.Andreas@strand.com www.dot.wisconsin.gov 12