1
Conducting An Energy Analysis
2
Professional Energy Analysis – Summary
4
Energy Analysis Preliminaries
5
EA – Preliminaries
6
MS Word Files can be downloaded to the HP49+ with Transfer Algorithms EA –Preliminaries nipuna (Sanskrit): skilled, capable of, kind or friendly towards
7
greengurus “Nipuna” en:p:ÙN: Program with Energy equations as MS Word Files nipuna (Sanskrit): skilled, capable of, kind or friendly towards EA –Preliminaries Download To HP49+
8
MS Word FilesHP49+ Files EA –Preliminaries nipuna (Sanskrit): skilled, capable of, kind or friendly towards
9
EA –Preliminaries ni nipuna (Sanskrit): skilled, capable of, kind or friendly towards
10
HP 49+ Solves Series of multiple equations with a few keystrokes EA –Preliminaries nipuna (Sanskrit): skilled, capable of, kind or friendly towards
11
EA –Preliminaries nipuna (Sanskrit): skilled, capable of, kind or friendly towards
12
Identify Layout of facility Operating Schedule Compile an Equipment List. Establish Geographic Location/ Degree Days/Weather Data. EA –Preliminaries Gathering the data for analysis
13
Analysis of Bills: Know the rate structure in effect for the facility. Separate energy bills into their components. E.g. demand charge and energy charges for the electric bill. EA –Preliminaries Gathering the data for analysis
14
EA –Preliminaries Gathering the data for analysis
15
EA –Preliminaries Gathering the data for analysis
16
Get Equipment List before conducting the audit EA –Preliminaries Gathering the data for analysis
17
EA –Preliminaries Gathering the data for analysis
18
EA –Preliminaries Gathering the data for analysis
19
Initial Walk-through Tour Introductory Meeting Audit leader should meet with the - facility manager and the - maintenance supervisor. EA – Preliminaries
20
Audit Interviews - facility manager - finance officer - floor supervisors and equipment operators - maintenance supervisor and staff Initial Walk-through Tour EA – Preliminaries
21
Initial Walk-through Tour EA –Preliminaries Get the tools together
22
Infrared Thermometer (must know emissivity) EA – Audit Preliminaries Initial Walk-through Tour
23
Light Meter Parts of facility might be over- or under-lighted EA – Audit Preliminaries Initial Walk-through Tour
24
Digital Snap- Around Volt-Ohm- Ammeter EA – Audit Preliminaries Initial Walk-through Tour
25
HVAC Combo Kit EA – Audit Preliminaries Initial Walk-through Tour
26
Power Factor Meter EA – Audit Preliminaries Initial Walk-through Tour
27
Ultrasonic Leak Detector Valuable for testing steam traps EA – Audit Preliminaries Initial Walk-through Tour
28
Air Velocity Measurement Anemometers Rotating Vane Pitot Tube Hot Wire EA – Audit Preliminaries Initial Walk-through Tour
29
Blower Door To determine the air leakage rate EA – Audit Preliminaries Initial Walk-through Tour
30
Combustion Analyzer EA – Audit Preliminaries Initial Walk-through Tour
31
Manometers EA – Audit Preliminaries Initial Walk-through Tour
32
EA – Audit Preliminaries Initial Walk-through Tour
33
Lighting Inventory: - light fixtures - lamp types, sizes and numbers - levels of illumination - uses of task lighting Initial Walk-through Tour
34
Lighting Inventory Initial Walk-through Tour
35
Lighting Inventory Initial Walk-through Tour
36
Lighting Inventory Initial Walk-through Tour
37
Building Envelope Initial Walk-through Tour
38
Building Envelope Initial Walk-through Tour EA – Audit Preliminaries
39
Building Envelope Initial Walk-through Tour
40
Boiler and Steam Distribution Age? Combustion Efficiency Btu/h Rating AFUE Pressures Temperatures Boiler Tune- up? Initial Walk-through Tour
41
Boiler and Steam Distribution Look for leaks! Steam Traps!
42
HVAC System Inspect: Evaporator Condenser Filters. kW/Ton Rating EER, SEER Initial Walk-through Tour
43
Fans and Blowers HVAC System Initial Walk-through Tour
44
Motors Measure: Voltage Current Power Factor Note: Horse Power, Load Factor Fan and Blower Electric Motor — 1/2 HP Reversible Electric Motor — 5 HP, 1740 RPM Initial Walk-through Tour
45
Motors Variable Speed Drives Initial Walk-through Tour
46
Hot Water Distribution System Initial Walk-through Tour
47
Energy Audit Special Topics
48
Codes and Standards
50
FERC
51
Codes and Standards FERC
52
Codes and Standards Natural Gas ?
53
Codes and Standards ASHRAE Standard 90.1 – 2001
54
Codes and Standards
55
Indoor Air Quality
56
Codes and Standards *1000 Btu/ft2/year
57
Rate Structures and Energy Bills
58
Electric Power Flow
59
Rate Structures and Energy Bills FERC orders 888 and 889 Electric Deregulation
60
Rate Structures and Energy Bills Electric Energy vs. Demand
61
Rate Structures and Energy Bills Electric: Energy vs. Demand Large Quantities of Electricity cannot be stored
62
Rate Structures and Energy Bills Electric Components of Bill
63
Rate Structures and Energy Bills Electric Sample Rate Structue
64
Rate Structures and Energy Bills Electric Sample Rate Structue
65
Rate Structures and Energy Bills Electric Power Factor
66
greengurus “Nipuna” Program with Electrical equations as MS Word File Rate Structures and Energy Bills Electric Power Factor
67
Rate Structures and Energy Bills Electric Special Rates
68
Rate Structures and Energy Bills Electric Special Rates
69
Natural Gas Interruptible Rates Highest Priority Customers pay more but will not be interrupted at times of high demand Rate Structures and Energy Bills
70
Monthly Bill Analysis
71
Profile for a metal products company in Florida Look for red flags Monthly Bill Analysis
72
Energy Balance Monthly Bill Analysis
73
Demand Balance Monthly Bill Analysis
74
Look for red flags Monthly Bill Analysis
75
Look for particularities Monthly Bill Analysis
76
Life Cycle Costing
77
Example: Choice between two Compressors Typical Life Cycle Example
78
Life Cycle Costing Typical Life Cycle Example
79
greengurus “Nipuna” Program with Eco- nomics equations as MS Word File Life Cycle Costing