Sync Data Lists Make sure internet connectivity on mobile Click on Sync button to get all the Schemes, Activity, Equipment, Material and etc data lists from the server
4
Sync Data Lists Sync activity will be used when changes will be occurred on server side in data lists After sync internet connection will not be required
5
Add New FIR Press Add New button to start FIR questionnaire
6
GPS Settings Press Settings button Note: Enable GPS before starting app
7
GPS Settings Enable “Google location service”, “GPS satellites” and “Location & Google search”
8
Add New FIR Press Add New button to start FIR
9
Scheme Type Select Scheme Type Select Scheme Sub Type
10
Name of Scheme Select Name of Scheme
11
Construction Start Date Select Construction Start Date Select Weather Condition
12
Log book found in order?
13
Inspection Team Member Type the name of team members visiting the construction site Team member field is MANDATORY If you want team member field to blank. Then type a blank space
14
Name of Supervisor Type the name of the supervisor present at site Supervisor field is MANDATORY If you want Supervisor field to blank. Then type a blank space
15
Work in Progress?
16
Labor Working at site Type a NUMBER for no. of skilled & unskilled labor working at site Both fields are MANDATORY if skilled & unskilled labor working at site are ZERO then type “0”
17
Construction Activity Rate the contractor's performance List of Activities are pre- defined. If you want to add a new Activity coordinate to you web app administrator After add new activity SYNC your app
18
Construction Activity In case “% completed” answer is 0%. “0” Rating field should be filled. For adding new Construction Activity SELECT “Add (Rate the constructor’s performance)” option
19
Equipment available at site No. / Quantity field is MANDATORY For adding new Equipment SELECT “Add (Equipment available at site)” option
20
Material available at site No. / Quantity field is MANDATORY For adding new Material SELECT “Add (Material available at site)” option
21
Remarks for Progress
22
Inst./Sugg. To Construction Team
23
Images Press Camera Icon to take field visit picture If you point out some important thing on the pic type your message in Image description field Press the Save button to save FIR
24
Upload FIRs’ Press “List All” button to upload saved FIRs’ to the server. You should have internet connectivity to upload saved FIRs’
25
Upload FIRs’ Press Submit All button to upload listed FIRs’