MST 326 Lecture 7 Project planning John Summerscales School of Engineering University of Plymouth
2
Golden rule: “A golden rule in terms of estimating the time required is to assume people are only productive four out of five days” C Sheldon and M Yoxon, Environmental Management Systems – third edition, Earthscan, London and Sterling VA, 2006.
3
Lecture outline l Gantt charts l Project Evaluation Review Technique (PERT) l Critical Path Analysis/Method (CPA/CPM) l Technology Road Maps (TRM)
4
What is a project ? a group of people brought together to achieve a defined objective in a defined period of time and with defined resources
5
Measuring success? l deliverables: what will be achieved l deadlines: when will it happen l milestones: end of each significant stage l are there quantitative parameters ?
6
Success or failure ? deadline achieved or if not then why? budgets met or reasons for variances acceptability of the finished item match to specification/customer expectations consequences culture change or new strategic alliances
7
Project management l develops innovative, creative and committed managers l provides a vehicle for measurement of resource effectiveness and for optimisation l permits strategic accountability
8
Henry Laurence Gantt graphical representation of the duration of tasks plotted vs time e.g. student timetable load chart shows workload relative to capacity one row per person vs hours in the day progress chart shows succession of tasks from start to finish
9
Gantt chart: progress chart
10
Gantt chart: CFD of RIFT research
11
MS Project... formats Calendar Gantt chart Network diagram Task usage Resource graph Resource sheet Resource usage Report
12
Program Evaluation Review Technique (PERT) l graphic representation of schedule for project –developed by USN for Polaris missile programme l shows –sequence of tasks –which tasks can be performed simultaneously –permits determination of the critical path for the individual tasks to be completed on time in order for the project to meet its completion deadline
13
Critical Path Analysis/Method l developed by the private sector at the time that PERT was started –has become synonymous with PERT –referred to as any of CPM, PERT or PERT/CPM l critical path is the set of individual tasks (each dependent on the preceding one) which taken together require the longest time to complete (i.e. minimum time) l can be much more difficult to interpret than a Gantt chart.
14
Node in a PERT chart
15
Network diagram for printer Figure 10.1 from Curtis book
16
Activity on node structure Figure 10.2 from Curtis book
17
Printer project activity on node activity times Figure 10.3 from Curtis book
18
Printer project activity on node earliest start times Figure 10.4 from Curtis book
19
Printer project activity on node latest finish times Figure 10.5 from Curtis book
20
Float for manufacture of the prototype Figure 10.6 from Curtis book
21
Bar chart for printer project Figure 10.7 from Curtis book
22
Projects and resource loading Figure 10.8 from Curtis book
23
Resource levelling Figure 10.9 from Curtis book
24
Basic CPM diagram Figure 3-18 from Hicks book
25
CPM Diagram with timings Figure 3-20 from Hicks book
26
Tabular analysis Table 3-8 from Hicks book
27
Time-scaled CPM network Figure 3-21 from Hicks book
28
A beta distribution in PERT Figure 3-22 from Hicks book
29
Beta distribution calculation A = most optimistic time M = most likely time B = most pessimistic time X = mean = (A + 4M +B)/6 S 2 = variance = [(B - A)/6] 2 Times A and B expected to occur only 1% of the time
30
Density function for project completion time Figure 3-23 from Hicks book
31
References l Tony Curtis, Business and Marketing for Engineers and Scientists, McGraw-Hill, Maidenhead, 1993. ISBN 0-07-707-868-3. l Philip E Hicks, Industrial Engineering and Management - a new perspective, McGraw-Hill, 1994. ISBN 0-07-028807-0. l Richard Pettinger, Introduction to Management, Macmillan, Basingstoke, 1994. ISBN 0-333-59769-9.
32
Technology Road Maps (TRM) l the most basic form can be considered as a time-based chart consisting of a number of layers –commercial, –technological, –legislative, and –environmental perspective
33
Technology Road Maps (TRM) l Developing a Technology Road Map requires three steps: –Market requirements forecast, –Product implications forecast, and –Technology implications forecast.