Download presentation
1
PROJECT CYCLE MANAGEMENT
An introduction
2
Overview Definitions Project Cycle Log Frame Approach – analysis phase
stakeholder analysis problem analysis analysis of objectives Log Frame Approach – planning phase assumptions indicators sources of verification activity scheduling Project Charts
3
PROJECT APPROACH Project = a series of activities aimed at bringing about clearly specified objectives within a defined time-period and with a defined budget. A project should have: Clearly identified stakeholders (primary target group & final beneficiaries); Clearly defined coordination, management and financing arrangements; A monitoring and evaluation system; An appropriate level of financial and economic benefits (indicating that the project‘s benefits will exceed its costs).
4
PROJECTS AND PROJECT MANAGEMENT
- Funding and contributions that are additional to ongoing activities - Funding = limited in time and resources Contribute to process of change taking place in a context that is complex because: it is changing continuously many actors are involved and may have an influence Project management can therefore be defined as the facilitation of such processes of change in order to attain objectives in the most effective and efficient way
5
Management tools Logical framework approach
A methodology for analysing, planning, managing and evaluating programmes and projects, using tools to enhance participation and transparency and to improve orientation towards objectives Developed in early 70s by USAID and widely adopted Project cycle management (PCM) Defines different phases in the project life with a well-defined process of involvement of different stakeholders, management activities and decision making procedures Uses the LFA (as well as other tools such as the Pert chart and Gantt diagram) Developed in early 90s and adopted by most development agencies and the EC
6
Project cycle management
Not revolutionary but likely to frame and articulate ongoing practices Not an exact science but a supporting tool to structure learning processes Many agencies talk about it, few are actually good at it Widely applicable – usefulness goes beyond development Value added depends on quality of its application
7
PCM Principles Respect for different phases in project cycle...
Stakeholder orientation... Consistent project design using logical framework... Attention for sustainability... Integrated approach using standarised documentation... TO ENSURE... informed decision-making at different stages of project management involvement and commitment of stakeholders a comprehensive and consistent analysis and planning that from design onwards mechanisms are considered that will continue the flow of benefits linkage with wider efforts, simplified and transparant documents
8
PROJECT CYCLE Programming Identification Formulation Evaluation
Implementation Monitoring
9
PROJECT CYCLE Appraisal Formulation l Ex-post evaluation Ex-ante
Monitoring by stakeholders End of project evaluation Ex-post evaluation l Ex-ante evaluation Appraisal Formulation
10
PCM/LFA APPROACH
11
Logframe Approach ANALYSIS PHASE PLANNING PHASE
Stakeholder Analysis - identifying & characterising major stakeholders, target groups & beneficiaries, defining whose problems will be addressed by a future intervention, and which potentials can be used Problem analysis - identifying key problems, constraints and opportunities; determining cause and effect relationships Analysis of objectives - developing objectives from the identified problems; identifying means to end relationships Strategy analysis - identifying the different strategies to achieve objectives; selecting the most appropriate strategy(ies); determining the major objectives (overall objectives and project purpose) Logframe - defining the project/ programme structure, testing its internal logic, formulating objectives in measurable terms, defining means and cost (overall) Activity scheduling - determining the sequence and dependency of activities; estimating their duration, setting milestones and assigning responsibility Resource scheduling - from the activity schedule, developing input schedules and a budget Define the project logic Identify stakeholders Deduct Specifying and operationalising Select the option
12
Stakeholder Analysis (4 steps)
Identifying Key Stakeholders (beneficiaries, vulnerable groups, possible adversely effected groups, socio-economic characteristics, relationships etc.) Determining Stakeholder Interests (benefits, expectations, resources they could mobilise etc) Determining Stakeholder Power and Influence (power and dependency relationships, control of decision making, resources etc.) Formulating a Stakeholder Participation Strategy in view of analysis, planning and implementation
13
STAKEHOLDER ANALYSIS STAKEHOLDER INTEREST AND ATTITUDE TOWARDS PROJECT
ROLE IN PREPARATION PROCESS INVOLVEMENT DURING PROJECT IMPLEMENTATION
14
1. PROBLEM ANALYSIS Should involve key stakeholders (identified through analysis) Typically in a workshop setting with possible external facilitation Given the capacity building orientation, multilevel problem analysis (subject and capacity)
15
Step 1:Problem analysis (I)
Is a procedure which allows to : analyse an existing situation identify key problems in this context visualise the problems in form of a diagram/tree (cause-effect relationships)
16
Problem analysis Effects Causes
Establishing cause-effect relations between problems Decreasing in-comes of artisanal fisherfolk Effects Decreasing fish stocks Low price received by artisanal fisherfolk in the village Destruction of coral & mangrove habitats Illegal fishing methods applied Processed fish is of bad quality Limited access to markets Causes
17
Problem analysis agree on the unit of analysis
identify major problems existing within a given situation (brainstorming) select a starter problem look for related problems to the starter problem establish hierarchy of cause and effects problems which are directly causing the starter problem are put below problems which are direct effects of the starter problem are put above complete with all other problems accordingly connect the problems with cause-effect arrows review the diagram and verify its validity and completeness
18
PROBLEM TREE ANALYSIS
19
2. Analysis of objectives
Turning the negative aspects into future desired, but realistic situations Incomes of artisanal fisherfolk increased Ends Rate of decline in fish stocks arrested Price received by artisanal fisher-folk increased Access to markets improved Coral & man-grove habitats conserved Incidence of illegal fishing reduced Quality of fish processing improved Means
20
3: Analysis of Strategies
The purpose is: to identify possible alternative options or ways to contribute to the overall objectives to agree on priority strategies based on an assessment of the relevance, the feasibility and the sustainability of each of them to concentrate the means of the project on what is really important, effective and feasible
21
Analysis of Strategies (III)
OUT IN Incomes of artisanal fisherfolk increased OVERALL OBJECTIVE Rate of decline in fish stocks arrested Price received by artisanal fisher-folk increased SPECIFIC OBJECTIVE Coral & man-grove habitats conserved Incidence of illegal fishing reduced Quality of fish processing improved Access to markets improved RESULTS Decision based on: budget, priorities, human resources available, social acceptability, urgency, ...
22
Logframe Approach ANALYSIS PHASE PLANNING PHASE
Stakeholder Analysis - identifying & characterising major stakeholders, target groups & beneficiaries, defining whose problems will be addressed by a future intervention, and which potentials can be used Problem analysis - identifying key problems, constraints and opportunities; determining cause and effect relationships Analysis of objectives - developing objectives from the identified problems; identifying means to end relationships Strategy analysis - identifying the different strategies to achieve objectives; selecting the most appropriate strategy(ies); determining the major objectives (overall objectives and project purpose) Logframe - defining the project/ programme structure, testing its internal logic, formulating objectives in measurable terms, defining means and cost (overall) Activity scheduling - determining the sequence and dependency of activities; estimating their duration, setting milestones and assigning responsibility Resource scheduling - from the activity schedule, developing input schedules and a budget Define the project logic Identify stakeholders Deduct Specifying and operationalising Select the option
23
The Logical Framework? The Logical Framework Matrix provides a summary of: why a project is carried out what the project is expected to achieve how the project is going to achieve it which external factors are crucial for its success where to find the information required to assess the success of the project which means are required what the project will cost
24
From Strategy Analysis to Intervention Logic
HOW? Complete formulation of objectives Transfer objectives to logframe (intervention logic): OO, SO, Results Review and complete the objectives at different levels Identify possible activities
25
Logical framework Specific Objective Results Activities Means Costs
Intervention Objectively Sources of Assumptions Logic Verif. Indicators Verification Overall Objective Specific Objective Results Activities Means Costs Pre-conditions
26
Intervention Logic Overall objective: the project’s contribution to policy or programme objectives (impact) Specific objective: direct benefits to the target group(s). S.O. is consequence of results, not the sum of the results. Results: the services or products to be realised by the project. Activities: the tasks (workprogramme) that need to be carried out to deliver the planned results. (detailed activities are often better presented seperatly. e.g. Gantt chart format)
27
Logical framework Activities Means Costs Pre-conditions
Intervention Objectively Sources of Assumptions Logic Verif. Indicators Verification Incomes of artisanal fisherfolk increased Price received by artisanal fisher-folk increased Quality of fish processing improved Access to markets improved Activities 1.1. To train fish handlers 1.2. To install appropriate Equipment etc. Means Costs Pre-conditions
28
Logframe Logframe Basics Overall Objectives Specific Objective Results
Objectively Verifiable Indicators Intervention Logic Sources of Verification Assumptions Overall Objectives Specific Objective Results Activities Means Cost Pre-conditions ‘... IF results are delivered, AND assumptions hold true, THEN the project purpose will be achieved ...’
29
Logframe Basics Logframe Means Cost
Objectively Verifiable Indicators Intervention Logic Sources of Verification Assumptions Incomes of artisanal fisherfolk increased Price received by artisanal fisher-folk increased Rate of decline in fish stocks arrested Quality of fish processing improved Leaders of fish co-ops Collaborate 1.1. To train fish handlers 1.2. To install appropriate Equipment etc. Means Cost ‘... IF results are delivered, AND assumptions hold true, THEN the project purpose will be achieved ...’ Prmission local Gov. Obtained Project facilities provided
30
HOW? Assumptions • Assess the importance of the external factors by using the assessment algorithm • Check the intervention logic and assumptions on completeness
31
Assessment of Assumptions
Is the external factor important? Yes No Will it be realised? Do not include in logframe Almost certainly Do not include in logframe Likely Include as an assumption Unlikely Is it possible to redesign the project in order to influence the external factor? Redesign the project by adding activities or results; reformulate the Project Purpose if necessary Yes No The project is not feasible
32
Project assumptions: Project assumptions may be outside of the project control (policy, collaboration external actors etc.) Other assumptions may have university policy implications (staffing policies, incentives, space for resources generation etc.) – Should be taken up prior or during implementation
33
Indicators WHY? To: • Clarify the characteristics of the OO, SO and R
• Manage the project more objectively • Provide a basis for performance measurement, monitoring and evaluation OVI’s describe the project’s objectives in operationally measurable terms (quantitiy, quality, time) Note: Often, it is necessary to establish several indicators for one objective. Together, these will provide reliable information on the achievement of objectives.
34
Indicators: An Example
Objective: Pollution load of wastewater discharged into the Blue river is reduced Select the indicator: Concentration of heavy metal compounds (Pb, Cd, Hg) Define the targets: Define the quantity: Concentration of heay metal compounds (Pb, Cd, Hg) is reduced by 75% compared to year x levels …(particular attention should be paid to the availability of baseline information) Define the quality: . to meet the limits for irrigation water .. Define the target group: ... , used by the farmers of Blue village, ... Define the place : . in the Blue river section of the District .. Determine the time: years after the project has started
35
Indicators: An Example
Objective: Efficiency and effectiveness of the learning and and administration processes/practices have been enhanced Select the indicator: Amount of administrative paperwork… Define the targets: Define the quantity: …is reduced by 20% annually particular attention should be paid to the availability of baseline information) Define the quality: ... Define the target group: ... , as used by the UNZI staff both acacemic and administrative ... Define the place : ... at UNZI... Determine the time: ... following full implementation of e-administration
36
Some criteria for good indicators
Do partners and stakeholders agree that this indicator makes sense to use? Owned Will the data have utility for decision-making and learning? Useful Can data be collected easily, on a timely basis at reasonable costs? Accessible Are the data consistent or comparable over time? Reliable Is the definition precise and unambiguous about what is to be measured? Objective Does the indicator directly represent the objective it is intended to measure? Valid
37
Sources of Verfication
They describe where and how to find the information with regard to the indicators Issues to be analysed: Do there exist external sources of verification? If so, are they specific enough, reliable and accessible? If not, how can the information with regard to the indicators be obtained?
38
Multi (annual) Operational plan
Logframe Results-based workplans & budgets 5500 1750 4250 750 400 1100 3100 Budget Salaries Allowances Vehicle Op. Office Tel/Fax Seeds Fertiliser Workplan 30
39
Activity Scheduling An activity schedule:
Maintains objective-oriented approach of logframe Breaks activities down into operational detail Clarifies sequence, duration and precedence of activities Identifies key milestones Assigns management responsibility and implementing responsibilities and should include management tasks USE project charts Workplan
40
Project charts Gantt chart = common technique for representing the phases and activities of a project In this example : What are the different tasks; What is the start and end date of the tasks.
41
Project charts Gantt chart can also include: Who is responsible?
What is the relation between ≠tasks? Are the deadlines met?
42
Project charts PERT = Project Evaluation and Review Technique
Gives an answer on: - What is the relation between the different tasks?
43
Project charts Gantt versus PERT Gantt : tasks in relation to time
Pert : tasks in relation to other tasks
44
LFA link to evaluation
Similar presentations
© 2025 SlidePlayer.com. Inc.
All rights reserved.