AMENDED LAWS FOR UTILITY COORDINATION 2009 AASHTO R/W & Utilities Subcommittee Conference April 22 nd
2
“You either pay now or pay later - Pick your poison” PAY NOW… Avoid unnecessary relocations Resolve all foreseeable conflicts OR PAY LATER… Delays Damages Claims Increased costs
3
DID YOU KNOW? What the State Utilities Engineer looked like in 2000?
4
DID YOU KNOW? 2000 2008
5
CWP vs. Utility Delays
6
FY 2008 Construction Time Extensions
7
RECENT EXAMPLES OF PROJECTS DELAYED US-441 Dublin:206 days - $1.18 million SR-92 Douglas Co:334 days - $1.92 million SR-166 Douglas Co:309 days - $ 113 thousand Mercer Univ. Bibb Co:577 days - $3.78 million Fury’s Ferry Road:457 days (Augusta)
8
Utility Time Extensions – Detail FY 2005 Study
9
Utility Mitigation Efforts GDOT Board & Commissioner: Initiated Utility Task Force August 2005 Internal/GDOT Policies & Procedures 43% Lack of Project/Utility Coordination
10
Utility Mitigation Efforts State Utilities Office Electronic Data Guidelines (EDG) / Automated Drafting Design System (ADDS) Plan Presentation Guide (PPG) Plan Development Process (PDP) Consultant Management Process Improvement (CMPI) Consultant Cost Proposal Standardization Geographical Information System (GIS) Performance Based Contracting Field Plan Review Checklists
11
Utility Mitigation Efforts State Utilities Office Utility Design/Build Specification Field Plan Review Inspections Office of Utilities Web Page Electronic Plans Transfer Guidelines Environmental Issues Created Utility Task Force 4 Subcommittee Teams (R/W Team – monthly reports) Training and Education Notice of Award & Authorization letters
12
Utility Mitigation Efforts State Utilities Office Electronic Receipt and Submittal of Utility Invoices Electronic Submittal of Utility Agreements Utility Plans Re-Engineering Organizational Structure Utility Redline Software Subsurface Utility Engineering (SUE) SUE Program Enhancement Utility Accommodation Policy & Standards Manual
13
Utility Mitigation Efforts State Utilities Office Utility Coordination Scope of Services Move to New GDOT Headquarters (Apr. ‘08) Georgia Utility Permitting System (GUPS) TRAQS TPRO CMIS PeopleSoft Privileges Utility Phase Funding Early Authorizations & Master Agreements for PE
14
Utility Mitigation Efforts State Utilities Office GA PSC – Large Projects Locator Certification AASHTO Best Practices SHRP – R-15 Utility Coordination Study Awards and Recognitions Senate Bill 19 – Legislative Session 2007
15
Utility Mitigation Efforts Senate Bill 19 Accountability (PIF) Contract Items $$ - GDOT fund PDP Deadlines Mediation Rule/Jan. ‘08 Project lettings May ‘08 19% Low Priority 28% Lack of Resources
16
PROPOSED MEDIATION RULE 672-19 Legislative Intent Applicability Time Period Escalation Process Mediation Board & Procedures Costs Decisions / Mediation Period
17
OVERVIEW OF MEDIATION RULE & PROCESS LEGISLATIVE INTENT Mediation less expensive than Litigation
18
OVERVIEW OF MEDIATION RULE & PROCESS APPLICABILITY Three (3) Types of Disputes WORK PLAN REVISED WORK PLAN ANY OTHER MATTER TIME PERIOD FOR APPLICABILITY May 2008 Letting
19
OVERVIEW OF MEDIATION RULE & PROCESS ESCALATION PROCESS Notice of Potential Dispute to Utility Structured Negotiation Process (Formalizing Communication) Prerequisite to the Mediation Board
20
GDOT Project Development Utility Relocation Funding & Mediation Process
21
OVERVIEW OF MEDIATION RULE & PROCESS MEDIATION BOARD & PROCEDURES 3 Member Board Qualified by State Office of Dispute Resolution Written Petition for Mediation Board established w/in 30 days Hearing held w/in 60 days No Direct Relationship (contractually or employed) w/in previous 6 months
22
OVERVIEW OF MEDIATION RULE & PROCESS COSTS Utility & GDOT – Pay for Member Selected Utility & GDOT – Equally pay for 3 rd Member Party Acts in Bad Faith May be responsible for All costs
23
OVERVIEW OF MEDIATION RULE & PROCESS DECISIONS / MEDIATION PERIOD Majority Vote – No Ties Public Document Subject to Judicial Review (Superior Court) An Agreement is reached or 60 days Can extend if mutually agreed by the parties
24
GDOT Resources – Office of Utilities – Office of Construction – Office of Construction Claims – Legal Services – District Offices
25
Time Extensions Related to Utility Delays
26
References SENATE BILL 19 http://www.legis.ga.gov/legis/2007_08/sum/sb19.htm ( Click on “ Current Version ” and you should be able to view) GDOT RULE – CHAPTER 672-19 GOVERNING UTILITIES MEDIATION PROCESS ( Georgia Secretary of State website – http://sos.georgia.gov/rules_regs.htm ) ESCALATION POLICY (GDOT website – Chapters 2 & 4 of the UAM: http://www.dot.ga.gov/doingbusiness/utilities/Pages/default.aspx)
27
Questions? State Utilities Office 404-631-1354 jbaker@dot.ga.gov web site: www.dot.ga.gov
28
THAT’S ALL FOLKS