DRILLING
2
Rig Selection Things To consider Water Depth : 76 m (appx : 250 ft)
3 types of major drilling rig are feasible Tender Assisted (44 MMUSD/day) Jack up rig (50 MMUSD/day) Semi Submersible (297 MMUSD/day) Tender Assisted Rig Water depth Seabed soil condition Costing rig, capacity and stability
3
Well Trajectories Factors
Target of the wells The drainage radius Well azimuth and inclination May be revised accordingly to actual well results, geological and res. modelling. All wells are proposed to be vertically drilled. Total number of producing wells = 11 wells Total number of injecting wells = 9 wells
4
Well profiles Well Name Target Layer Well TVD (m-MDDF) Profile
Name Target Layer Well TVD (m-MDDF) Profile Completion Type Remarks BE-1 M 2/3 1280.0 Vertical Single Producer BE-2 1270.0 BE-3 Dual M 7/8 1305.0 BE-4 1295.0 BE-5 1321.0 BE-6 1307.0 M 9/14 1342.0 BE-7 1318.0 BE-8 1330.0 BE-9 1350.0 BE-10 1320.0 BE-11 M 15 1338.0 BE-12 1400.0 Injector BE-13 1390.0 1410.0 BE-14 BE-15 1380.0 BE-16 BE-17 1370.0 1395.0 BE-18 1430.0 BE-19 BE-20
5
Casing Design & Bit Selection
Casing Setting Depth (m-TVD) Casing OD (in) Casing grade Bit size Type of bit Conductor 80 26” X-56/ Threaded - Surface 500 13-3/8” L-80/BTC 17-1/2” PDC Intermediate 950 9-5/8” P-110/LTC 12-1/4” Production 1328 7” V-150/ Extreme-line 8-1/2”
6
Assume Pressure Gradient (psi/ft) Proposed Mud Weight (ppg)
Drilling Fluid System Hole Size (in) Casing Size (in) Casing Type Mud Type Assume Pressure Gradient (psi/ft) Proposed Mud Weight (ppg) 26 20 Conducto r Sea water + Hi Vis Sweeps 0.433 17-1/2 13-3/8 Surface Seawater Polymer 12-1/4 9-5/8 Intermedi ate KCL / PHPA 0.478 8-1/2 7 Productio n
7
Producing Well (BE-1 – BE-11) Injector Wells (BE-12 – BE-20)
Casing Cementation Well Casing Top of Cement Lead (ppg) Tail (ppg) Producing Well (BE-1 – BE-11) Injector Wells (BE-12 – BE-20) 20” Surface 15.8 13-3/8” Lead: Surface Tail: 150m above 13-3/8 shoe 12.6 9-5/8” Lead: 150m above 13-3/8” shoe Tail: 150m above 9-5/8” shoe 7” Top of Liner
8
Type of Cement / Additive
Casing Cementation Casing OD (in) Casing ID Type of Cement / Additive Lead Slurry Volume Tail Slurry volume Total 26” 25.65” Class “G” 493 sacks Seawater 54.46 bbl Mixing Fluid 63.25 gal Fluid Loss 24.64 gal 13 3/8” 12.459” 556 sacks 462 sacks 1018 sacks 146.7 bbl 51.04 bbl bbl bbl 59.29 bbl bbl 27.8 gal 23.1 gal 50.9 gal Retarder 33.36 gal 9.24 gal 42.6 gal Dispersant 556 gal 161.7 gal 717.7 gal 9 5/8” 8.535” 397 sacks 210 sacks 607 sacks bbl 23.22 bbl bbl bbl 26.98 bbl bbl 19.83 gal 10.51 gal 30.34 gal 23.8 gal 4.2 gal 28 gal gal 73.57 gal 470.19 7” 6.366” 542 sacks 59.67 bbl 69.62 bbl 27.12 gal 10.85 gal gal
9
Potential Drilling Hazards
Shallow Gas Lost Circulation Zone CO₂ and H₂S Content Occupational Safety Hole Cleaning Stuck pipe/differential sticking
10
Time and Cost Estimation
11
Drilling Optimization
Monobore Completion Multilateral Completion Rotary Steerable System (RSS)