1 IPEK energy GmbH Development and Implementation of a Wind Farm 3rd International Conference on Alternative Energy & Power ICAEP 28 March 2009
2
2 Content Company Profile Wind energy - an introduction Steps to install a wind farm Selection of wind turbines Selected wind turbine for ZORLU: VENSYS Project implementation
3
3 Content Company Profile Wind energy - an introduction Steps to install a wind farm Selection of wind turbines Selected wind turbine for ZORLU: VENSYS Project implementation
4
4 IPEK energy GmbH We are an independent engineering & consultancy company support you from acquisition to turnkey ready construction of renewable power generation systems world wide offer skilful support with international financing and after commissioning take the technical business management are very flexible and act in close cooperation with our clients exactly to the requirements of the international markets
5
5 Key Services Engineering & Consulting acquire suitable sites design of whole wind farm (micro-siting, electrical, civil) complete permitting procedures negotiate required Power Purchase Agreement (PPA) organize international funding supervision of construction till take over of the plan control operations management Wind Measuring standard IEC confirm measuring trough Wind Mast and SODAR measuring Bankable Feasibility Studies Due Diligence Emissions Trading
6
6 Osman Ipek – Managing Director Electrical Engineer (Main Branch Renewable Energies) Active in Wind Branch since 2000 project development project management project implementation engineering due diligence measurement and monitoring systems wind resource assessment teaching and education, concepts; strategies; system layout 18 Wind farm Projects realized More than 800MW projects developed in 6 countries Due Diligence of more than 220MW wind projects Feasibility studies for more than 40 wind farms Currently on going Projects of >400MW in Turkey, Romania and Pakistan
7
7 Countries of Work Experience
8
8 Membership/ Partners Memberships Partners German Wind Energy Association The Association of German Engineers Pakistan Wind Energy Association WINDTEST Grevenbroich GmbH
9
9 Company Profile Wind energy - an introduction Steps to install a wind farm Selection of wind turbines Selected wind turbine for ZORLU: VENSYS Project implementation
10
10 A wind turbine obtains its power input by converting the force of the wind into a torque acting on the rotor blades The amount of energy which the wind transfers to the rotor depends - on the density of the air - the rotor area - and the wind speed. In other words you can get more energy: - the "heavier" the air - the “bigger” the rotor - the “higher” the wind speed How does it work
11
11 690V Components of a Wind Turbine
12
12 Components of Wind Turbine
13
13 Company Profile Wind energy - an introduction Steps to install a wind farm Selection of wind turbines Selected wind turbine for ZORLU: VENSYS Project implementation
14
14 12 Steps to install a wind farm 1. WIND ASSESSMENT... available wind data will be used to estimate how much energy the wind farm will produce. 2. WIND FARM DESIGN Wind data combined with topographical information to design the wind farm..... to model wind flow,... turbine performance... sound levels... to optimize the location of WTG... design the access roads... turbine foundations... local electric network... grid connection
15
15 3. ENVIRONMENTAL STUDY... to identify any impacts on landscape, plants and wildlife, soil and water, land use, aviation, telecommunications, etc. 4. LAND ACQUISITION... to negotiate “option” agreements to use land 5. PERMITTING AND PUBLIC CONSULTATION... seek municipal, provincial and federal permits before the project can go ahead.... meet the local communities to present the project, solicit their feedback and seek community support. 12 Steps to install a wind farm
16
16 6. ECONOMIC AND FINANCIAL ANALYSIS … demonstration of the economic viability of the project to raise the funds … estimate the cost of turbines and their installation, as well as roads, electrical system, operation and maintenance, etc.... estimate the income by using the energy production of the wind farm over the lifetime of the project 7. MANUFACTURING WTG parts are manufactured and pre-assembled into the main components at the factory and shipped to the wind farm site where the final assembly will take place. 12 Steps to install a wind farm
17
17 8. SITE PREPARATION The wind farm site will be prepared before the WTG will arrive to site.... access roads, clear the areas where turbines will be erected... preparation of the foundations (do the excavating; installing the formworks; pouring concrete) 9. CONSTRUCTION After arrival of all components, the assembly can take place by using a crane to erect the tower and install the nacelle and rotor with its hub and blades. Same time the electrical works will be performed 12 Steps to install a wind farm
18
18 10. COMMISSIONING The wind farm will tested before becoming fully operational. 11. OPERATION AND MAINTENANCE A variety of skill sets are required to ensure the effective operation of a Wind Farm (activities be performed on a regular basis throughout the project’s, monitoring and analyzing performance, performing preventive maintenance and repairs on the turbines) 12. ….. 12 Steps to install a wind farm visit Hall 1 – A36
19
19 Steps from LOI to Implementation
20
20 Company Profile Wind energy - an introduction Steps to install a wind farm Selection of wind turbines Selected wind turbine for ZORLU: VENSYS Project implementation
21
21 On Site Wind Measuring (example)
22
22 Compliance with the site wind conditions Specific costs (e. g. costs per kWh) Readiness of supplier to offer turbines Commitment to the market Delivery time Warranties: power curve, availability, grid compliance Completeness of technical documentation Track record of WTG model Company: position in market, financial strength, etc. Operation and Maintenance concept Crane availability Selection Criteria for Wind Turbines
23
23 Different size of WTGs / Cost per kW WTG: 1MW, 70m hub WTG: 2MW, 100m hub
24
24 Large wind farm vs. smal wind farm Source: www.awea.org
25
25 Selection Criteria for Wind Turbines Availability of 400t cranes is higher than 600t WTG <2MW should be selected for Pakistan
26
26 Company Profile Wind energy - an introduction Steps to install a wind farm Selection of wind turbines Selected wind turbine for ZORLU: VENSYS Project implementation
27
27 No Gearbox Synchronous Generator Self Cooling No Pitch gear Selected Wind Turbine: VENSYS
28
28 Generator is fully encased (protected against dust/sand) Generator & Cooling system
29
29 Maintenance friendly No Crane needed AC Pitch motor Capacitor instead Batteries Less maintenance
30
30 Compliance with the site wind conditions Specific costs (e. g. costs per kWh) Readiness of supplier to offer turbines Commitment to the market Delivery time Warranties: power curve, availability, grid compliance Completeness of technical documentation Track record of WTG model Company: position in market, financial strength, etc. Operation and Maintenance concept Crane availability Selection Criteria for Wind Turbines - the shortest delivery time comparing to other - OK - optimal - OK – Less maintenance - OK for 400t crane
31
31 Draft Time Table
32
32 Company Profile Wind energy - an introduction Steps to install a wind farm Selection of wind turbines Selected wind turbine for ZORLU: VENSYS Project implementation
33
33 WF site of Zorlu together with neighbors FFC and Masterwind North
34
34 Wind resource map at 69m
35
35 Wind resource map at 85m
36
36 Wind turbine siting
37
37 Noise and Shadow analysis
38
38 Scales of noise emissions 150 140 130 120 110 100 90 80 70 60 50 40 30 20 10 Jet Airplane Industrial Noise Typewriter Leaf Fall Whispering Air Hammer Inside Car Home Office Wind Turbine Jet Airplane Industrial Noise Typewriter Home Whispering Air Hammer Inside Car Wind Turbine
39
39 85m wind measuring mast of ZORLU The highest wind measuring mast in Pakistan
40
40 Ground Breaking Ceremony ZORLU January 2007
41
41 Transportation study
42
42 Transport problems identified and solved
43
43 Implementation - Soil Study
44
44 Implementation- Seismic Study
45
45 Implementation - Public Consultation
46
46 Impressions
47
47 Foundation works
48
48 Wind Farm cabling
49
49 Coordination Meetings & start of Installation
50
50 Installation of WTG
51
51 Installation
52
52 Internal electrical works
53
53 Pakistan first wind turbine
54
54 The first wind farm of Pakistan
55
55 Thank you for your attention
56
56 Contact IPEK energy Pakistan Pvt. Ltd. 89/II Khayaban-e-Shujaat DHA Phase VI Karachi - Pakistan Tel.: +92.21.543 20 91 Fax: +92.21.543 20 92 For any further information please contact us: www.ipek-energy.com Hall-1 A60