PT Sari Pari Abadi - WW SLN –Date & Time : Thursday, 03 August 2006 at 13:30 hrs. –Location : Duri 3Q-34A –Injured Personnel : Jefry, 25 years –Job Title.

Similar presentations


Presentation on theme: "PT Sari Pari Abadi - WW SLN –Date & Time : Thursday, 03 August 2006 at 13:30 hrs. –Location : Duri 3Q-34A –Injured Personnel : Jefry, 25 years –Job Title."— Presentation transcript:

1 PT Sari Pari Abadi - WW SLN –Date & Time : Thursday, 03 August 2006 at 13:30 hrs. –Location : Duri 3Q-34A –Injured Personnel : Jefry, 25 years –Job Title : Roustabout, 3 years experience –Company / Team : PT. Sari Pari Abadi (SPA) # 3 - North Wellwork Duri. –IP condition: Concious, burn injury grade 2 and 3, 1 % on right and left hands; grade 1 and 2, 1 % on left knee. Cardiography OK; –He is still being observed in Medical. –Description –The IP was working together with crane operator to unload the cement from cargo truck which was parked below 112.5 kVA power line. After the crane boom was erected, he was attempting to put lifting sling that hang on at the crane to the material pallet, he fell down on the cargo due to electrical shock transmitted from the lifting sling. Then, on concious condition he stood up, run to rig office and reported the incident to Wellsite Manager (company man) that was on rig office. Injured person (IP) was brought to Duri medical for further treatment. The IP got skin burnt on his right and left hands also on left knee. He was still under observation when this report is made.

2 Rig Well Power Line, 112.5 KVA Boom Crane Cargo Logging Truck Rest House P. Toilet 34 ft 87 ft 31 ft 81.3 ft 16 ft 46.6 ft Working Tank Rig Pump Boot A.Control Gate to Switching of Station Control Panel Panel Box Working Tank RIG SPA-03 LAY OUT

3 Electric Induction Electric Shock to IP Lifting sling

4 Date & Time: Friday, 04 August 2006 at 14:50 hrs. Location : Duri MSS Mill Wright Shop Vehicle involved: FOCO Truck 4X1297 Driver: Sunggul Marbun Company / Team : PT Supraco / W&FM HOOU Description: –On Friday 4 August 2006 at 14:50, FOCO Truck 4X1297 loaded with a unit of agitator which the height is higher than the normal position of the boom of the FOCO Truck. The swamper assumed that the FOCO Truck can get out from Mill Wright Shop safely without making sure the abnormal condition of the boom versus the height of the rail door beam. So, the swamper together with the operator get in the FOCO and give no guidance to the operator when suddenly they heard the boom of the FOCO Truck hitting the beam of rail door caused the beam bent. No damage at the FOCO Truck and no injury

5

6 Normal level of the boom

7 PT Siak Zamrud Pusako - WW SLS Date & Time: Tuesday, 08 August 2006 at 23:15 hrs. Location: Intersection field road of PH-30 and PH-25 Minas Driver involve: Naizul Vehicle: Foco truck ( BM 8573 DA ) Company / Team: PT. Siak Zamrud Pusako (SZP) # 2 / WW Ko-Pet Ops, SLS Wellwork Minas. Personnel involved condition: No injury for both personnels and others Description On Tuesday, 08 August 2006 at 23:15, on Rig SZP#02, a foco truck was about to transport equipments (tool box and access control post). After loaded both equipments on the foco deck, the foco truck's operator forgot that the boom was still lengthen 75% of full length and the sling was still linked to access control's post hanger. He then continued to drive the truck towards PH-41, and after passed intersection (about 400 meters from access control's previous position) the boom cut off one of three over pass power line cable. The personnel managed to escape from the truck with no injury. Small spark of fire came out from cut-off power line cable which then burned grass (naturally extinguished in short time).

8 A’ A To PH-25 PH-30 B To PH public road Legend: A’ = previous location of access control’s post A = access control’s post position on foco’s deck B = foco position after incident Distance of A’ – B = 400 meters Distance of B – power line = +/- 10 meter

9 Tool box Access Control’s post

10 Minimum Clearance For Un-Guarded Electrical Energized Part Phase Voltage Vertical ClearanceHorizontal Clearance 600 volts8 feet, & 0 inches3 feet & 2 inches 2,300 volts8 feet, & 0 inches3 feet & 3 inches 6,600 volts8 ffet, & 0 inches3 feet & 4 inches 11,600 volts9 feet, & 0 inches3 feet & 6 inches 22,000 volts9 feet & 3 inches3 feet & 9 inches 33,000 volts9 feet & 6 inches4 feet & 0 inches 44,000 volts9 feet & 10 inches4 feet & 4 inches 66,000 volts10 feet & 5 inches4 feet & 11 inches 88,000 volts11 feet & 0 inches5 feet & 6 inches 110,000 volts11 feet & 7 inches6 feet & 1 inches 132,000 volts12 feet & 2 inches6 feet & 8 inches 230,000 volts15 feet and 0 inch10 feet and 0 inch.* *CPI Standard design.


Download ppt "PT Sari Pari Abadi - WW SLN –Date & Time : Thursday, 03 August 2006 at 13:30 hrs. –Location : Duri 3Q-34A –Injured Personnel : Jefry, 25 years –Job Title."