Download presentation
Presentation is loading. Please wait.
Published byCordelia Dorsey Modified over 9 years ago
1
June 13, 2003 Status Report
2
Project Summary n Project to provide new 27.5 MGD blended supply to El Paso n Cooperative effort between Fort Bliss and EPWU n Presentation today is an update on project progress
3
Facilities included in Project n 12-15 MGD Desalination Plant n Rehabilitate 15 Existing Wells – 18 MGD n 12 MGD of new well supply (est. 16 Wells) n Brine Disposal Facilities n Pipelines n Water resources Learning Center
4
Facilities included in Project
5
Work Accomplished n Brine Disposal Study n Evaluation of existing well facilities n Test and Monitoring Well program n Deepwell Disposal site investigations n Pilot Studies n Preliminary Design of Desalination Facilities
6
Natural Evaporation Enhanced Evaporation Brine Disposal Option Study Brackish Water Supply From Existing EPWU Wells And Proposed Ft Bliss Wells Permeate to Transmission / distribution Brine Reject ROplant Deep Well Injection Solar Gradient Ponds Brine Concentr ator
7
Natural Evaporation Brine Disposal Option Study Brackish Water Supply From Existing EPWU Wells And Proposed Ft Bliss Wells Permeate to Transmission / distribution Brine Reject ROplant Deep Well Injection Brine Concentr ator
8
Existing EPWU Wells - Assessment and Needs Analysis
9
Test and Monitoring Well Program
11
Deep Well Injection Report
14
RO Pilot Plant Operations
15
Brine Concentrator Pilot Plant Operations
16
RO Plant Report
18
Value Engineering Session n Conducted December, 2002 n Outside Technical Review
19
Milestones n Commenced Design of Well Improvements –May, 2003 n Commence Design of Desalination Plant – July, 2003 n Ongoing Deepwell Testwell Program n NEPA Studies
20
Total Capital Cost, $x1000 Ammortized Capital Cost, $x1000 1 Ammortized Capital Cost, $/kgal blended total Annual O&M Costs, $x1000 Total Ammortized Capital and O&M Cost, $/kgal blended total Total Cost - 27.5 MGD RO $ 67,059 $ 67,059 $ 5,381 $ 5,381 $ 0.55 $ 10,183 $ 10,183 $ 1.58 $ 1.58 16 New Brackish Wells, Inc. Collector Lines $ 25,920 $ 25,920 $ 2,080 $ 2,080 $ 0.21 $ 0.21 $ 2,101 $ 2,101 $ 0.42 $ 0.42 Existing Well Facilities (Rehab) 3 $ 5,767 $ 5,767 $ 463 $ 463 $ 0.05 $ 0.05 $ 3,239 $ 3,239 $ 0.38 $ 0.38 27.5 MGD RO Facitlity $ 23,468 $ 23,468 $ 1,883 $ 1,883 $ 0.19 $ 0.19 $ 2,804 $ 2,804 $ 0.48 $ 0.48 7.5 MGD Pump Station $ 1,380 $ 1,380 $ 111 $ 111 $ 0.01 $ 0.01 $ 1,284 $ 1,284 $ 0.14 $ 0.14 Finished Water Transmission Line $ 828 $ 828 $ 66 $ 66 $ 0.01 $ 0.01 $ 5 $ 5 $ 0.01 $ 0.01 Brine Disposal by Deep Well Inj., Includiing Pipeline $ 9,696 $ 9,696 $ 778 $ 778 $ 0.08 $ 0.08 $ 750 $ 750 $ 0.16 $ 0.16 1 Based on 20 year life, 5.0% interest, A/P Factor = 0.08024 Cost Estimates
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.