Route 7 Corridor Projects Fairfax County Transportation Advisory Commission April 15, 2014 Leonard (Bud) Siegel Jr., PE Virginia Department of Transportation
2
Presentation Overview Route 7 Corridor General Remarks Three Active Projects: Rt. 7 Improvements (Rolling Holly Dr. – Reston Ave.) Rt. 7 Bridge Rehab/Capacity Improvement (over DTR) Rt. 7 Improvements (Reston Ave. – Jarrett Valley Dr.) Questions & Answers 2
3
3 Rt. 7 Improvements Rolling Holly Dr. – Reston Ave.
4
Status: In Construction Schedule: May 23, 2013: Start of Construction Nov. 12, 2015: Substantial Completion Dec. 16, 2015: Final Completion Cost: 4 PhaseCost Engineering (PE)$5.8M Property Rights (ROW) & Utilities$3.6M Construction$24.9M Total$34.3M
5
Rt. 7 Bridge Rehab/Capacity Improvement over Dulles Toll Road (DTR) 5
6
Status: Preparing for Design/Build (D/B) Delivery Schedule: Feb. 20, 2014: Public Hearing May 2014: Advertise D/B RFQ Aug. 2014: Advertise D/B RFP Cost: 6 Estimated Costs Engineering$1.7M Property Rights (ROW) & Utilities$0.6M Construction$32.1M Total$34.4M
7
7 Rt. 7 Improvements (Reston Ave. – Jarrett Valley Dr.)
8
Rt. 7 Improvements Reston Ave. - Jarrett Valley Dr. Schedule: Nov. 6, 2013: Citizen Information Meeting Late 2014/Early 2015: Public Hearing Cost: 8 Estimated Costs Engineering$30M Property Rights (ROW) & Utilities$50M Construction$220M Total$300M
9
Thank You! Questions & Answers 9