Presentation is loading. Please wait.

Presentation is loading. Please wait.

Edward B. Farkas, Managing Director, Project Management Practice

Similar presentations


Presentation on theme: "Edward B. Farkas, Managing Director, Project Management Practice"— Presentation transcript:

1 Edward B. Farkas, Managing Director, Project Management Practice
How to Develop a Winning Project Plan Edward B. Farkas, Managing Director, Project Management Practice ETR Technology Center

2 Perform a scope analysis BEFORE any planning begins
Review the scope documents Scope analysis facilitates identification of…. Deliverables Stakeholders Assumptions Constraints Risks This information is key to the first planning steps: What do you think they are?

3 Work Breakdown Structure (WBS)
A deliverable-oriented grouping of project elements which organizes and defines the total scope of the project Each descending level represents an increasingly detailed definition of a project component Project components may be products or services -References: PMBOK, 1996.

4 Work Package A deliverable at the lowest level of the work breakdown structure A work package may be divided into activities Reference: PMBOK, Glossary

5 Importance of the WBS The WBS is the foundation so that:
The responsibility assignments for each deliverable can be established Estimated costs and budgets can be established Planning can be performed The total program can be described as a summation of subdivided deliverables The organizational structure can best fit the deliverables

6 Importance of the WBS (Cont'd)
Coordination of objectives so that objectives can be linked to company resources in a logical manner Clarify specification tree and contract line items Structure contractors’ proposals around WBS thus simplifying source selection Facilitate progress status reporting and problem analysis (cost/schedule control system) - the tracking of time, cost, and performance

7 WBS Benefits Prevents omitted deliverables
Gains commitment of project personnel Enables development of a basic project plan Ensures deliverables visibility Results in risk reduction

8 Level of Effort (LOE) Support-type activity that does not readily lend itself to measurement of discrete accomplishment Generally characterized by a uniform rate of activity over a specific period of time. Reference: PMBOK, Glossary

9 Leverage the WBS To identify additional risk issues
To validate or create an OBS To understand relationships between deliverables and activities

10 Create a Risk Management Plan
Identify risks (scope analysis, leveraged WBS) Quantify or Prioritize Determine Impact Manage i.e. transfer, mitigate, accept may yield tasks that are schedule inputs

11 We can define communication protocols
Escalation Paths Contact Points (PPOC Concept) Reporting Requirements (may be contractual)

12 What do have now? We have identified the stakeholders
We are aware of assumptions We are aware of constraints We know all required deliverables We have a complete WBS We have a risk management plan (RBS) We have an OBS We have a communications plan next?

13 A Project Schedule Includes:
A List Of Tasks A Timeline Relationship To Scope

14 Tasks Defined Activity Assigned Resource Duration
Degree of Importance/Relationship

15 TASK COMPONENTS Activity: What Will Be Done
Resource: Who (what is needed) Will Do It Duration: When Its Done Importance: Relationship To Other Tasks

16 Activity Resource Duration Importance
John will test the Software Code Module 7 panel on Monday to complete the project. Activity Resource Duration Importance

17 Task Relationships determines....
How Fast The Project Moves, or How Slow The Project Moves

18 Task Relationships Finish To Start: ‘from’ finish before ‘to’ starts
Finish To Finish: ‘from’ finish before ‘to’ finishes Start To Start: ‘from’ start before ‘to’ starts Start To Finish: ‘from’ starts before ‘to’ finishes

19 S F S S F S F GRAY = A BLACK = B F

20 Task Relationship Terms
Dependencies Predecessors Successors Concurrencies Sequencing

21 Prompt with questions….
Can This Task Start Before Another Is Completed? Can I Start This Task At The Same Time As Other Tasks? Does This Task Have To Be Completed Before Another Task Starts? Should This Task Happen Earlier Than Another?

22 What Is A Critical Task? Does Not Completing This Task Hold Up Or Delay Another/ or Preclude Project Completion - (delays completion) ? If So, Its Critical!

23 How To Sequence Tasks PDM: Precedence Diagramming Method
AON: Activity On Node ADM: Arrow Diagramming Method CDM: Conditional Diagramming Method WBS: Work Breakdown Structure CPM: Critical Path Methodology

24 Visual Task Development Tools
Network Logic Diagrams Gantt Charts Flow Charts PERT: Program Evaluation Review Techniques

25 Determine Task Durations
Identify Time Sensitive Tasks Identify Scope Constraints Identify Lead Time Tasks Correlate To Labor Plan

26 Assign Resources To Tasks
Assign A Person(s) For Each Task Assign Corresponding Material(s) Assign Matrix (sub-contract/vendor) Resource

27 Task Update Defined Activity Specific Duration Assigned Resource
Importance Level/ Task Relationships

28 Schedules.... Provide the raw data for the Cost To Complete estimates, labor/financial forecasts.

29 Total Project Planning
Summary of conditions defining project Scope and objectives of a project Organization and authority relationships Authority and responsibility of a project manager Functions to be performed Authority and responsibility of other organizations

30 Planning Saves... Time Dollars

31 Acronyms CPM: Critical Path Method FF: Finish to Finish
FS: Finish to Start LOE: Level of Effort OBS: Organization Breakdown Structure RBS: Risk Breakdown Structure SF: Start to Finish SS: Start to Start WBS: Work Breakdown Structure

32 Q&A For additional information & copies of this presentation:
Edward B. Farkas, Managing Director, Project Management Practice: ETR Technology Center, Inc. 180 Oser Avenue Hauppauge, NY A certified WBE firm established in 1980


Download ppt "Edward B. Farkas, Managing Director, Project Management Practice"

Similar presentations


Ads by Google