MIS5102: Process Improvement and Innovation Project Planning
2
“Magical”(?) Interdisciplinary View
Business Technology Customer How does this view positively affect the project portfolio management process? How does this view positively affect the project planning process? How do organizational dynamics play a role? (Berkun, Chapter 3.3)
3
What do you do? When do you do it? Who does what?
Recall our party planning exercise from the beginning of the semester… What do you do? When do you do it? Who does what?
4
Elements of a Project Plan
What do you do? When do you do it? Who does what? Process decomposition Swim lane diagrams RACI charts We already have some tools we can use You wouldn’t always use these specific tools, but many of the concepts are the same!
5
Work Breakdown Structure (WBS)
Aircraft System Air Vehicle Receiver Fire Control Communication Training Equipment Services Peculiar Support Equipment Depot How is this like process decomposition? How is it different? What do you learn from this?
6
Design principles 100% rule Mutual exclusivity Outcomes, not actions
Level of detail Why is each important in building a useful WBS? How far should you break down a project? What is the “problem” with estimation?
7
Understanding Dependencies
What are task dependencies? Why is it important to understand them? How are they used to turn a WBS into a project plan?
8
What does it mean for the task to be on the critical path?
Critical Path Analysis using PERT (Program Evaluation and Review Technique) 10 days 36 days Create module 1 Software Unit Testing 15 days 15 days 15 days 15 days System Test Design Create module 2 Software Unit Testing 7 days 5 days 3 days Buy hardware Hardware Config. Hardware Testing 30 days Write Manual The work units on the longest path through the diagram are on the critical path. What does it mean for the task to be on the critical path?
9
Allocating Work Assigning people to tasks
Build off of the work breakdown structure What can a RACI chart tell you about allocation? What can a Swim Lane Diagram tell you about allocation?
10
Allocating Work and the Critical Path
10 days 36 days Create module 1 Software Unit Testing 15 days 15 days 15 days 15 days System Test Design Create module 2 Software Unit Testing 7 days 5 days 3 days Buy hardware Hardware Config. Hardware Testing 30 days Entire Team How does adding this information help the planning process? Write Manual Software Team 1 Software Team 2 Hardware Team Communications
11
Key Considerations about Estimating
“Few people enjoy estimating complex things that they will be accountable for.” (Berkun, Chapter ) What is the result of that? What can go wrong with estimation? Two scenarios where we build a 95% confidence interval 10 days Create module 1 -2 standard deviations from the mean +2 standard deviations from the mean Explain the difference between the scenarios What are the implications for project planning? For the triple constraint? For allocating resources? 9 10 11 -2 standard deviations from the mean +2 standard deviations from the mean 6 10 14