Team Meeting April 25, 2014 NSTX-U Construction Progress NSTX-U Supported by Culham Sci Ctr York U Chubu U Fukui U Hiroshima U Hyogo U Kyoto U Kyushu U.

Similar presentations


Presentation on theme: "Team Meeting April 25, 2014 NSTX-U Construction Progress NSTX-U Supported by Culham Sci Ctr York U Chubu U Fukui U Hiroshima U Hyogo U Kyoto U Kyushu U."— Presentation transcript:

1 Team Meeting April 25, 2014 NSTX-U Construction Progress NSTX-U Supported by Culham Sci Ctr York U Chubu U Fukui U Hiroshima U Hyogo U Kyoto U Kyushu U Kyushu Tokai U NIFS Niigata U U Tokyo JAEA Inst for Nucl Res, Kiev Ioffe Inst TRINITI Chonbuk Natl U NFRI KAIST POSTECH Seoul Natl U ASIPP CIEMAT FOM Inst DIFFER ENEA, Frascati CEA, Cadarache IPP, Jülich IPP, Garching ASCR, Czech Rep Coll of Wm & Mary Columbia U CompX General Atomics FIU INL Johns Hopkins U LANL LLNL Lodestar MIT Lehigh U Nova Photonics Old Dominion ORNL PPPL Princeton U Purdue U SNL Think Tank, Inc. UC Davis UC Irvine UCLA UCSD U Colorado U Illinois U Maryland U Rochester U Tennessee U Tulsa U Washington U Wisconsin X Science LLC

2 NSTX-U NSTXU Construction Progress – April 25th, 2014 2 NSTXU Construction – PUMPDOWN November 1998 NSTX turned over to operations February 1999

3 NSTX-U NSTXU Construction Progress – April 25th, 2014 3 Good progress continues on NB and Machine Installations Pumpdown December 2014

4 NSTX-U NSTXU Construction Progress – April 25th, 2014 4 Recent Accomplishments & work underway Neutral Beam DI piping contract completed and tested. HVE water line installation has been completed in NTC. Flexible hoses for the HVE lines can now be measured and fabricated. Pipe connections to the DI water pumps continued in the Pump Room. Neutral Beam cabling contract completed. NB duct installation completed Neutral Beam Armor installed VV feet installation complete. PF 4/5 support installation complete. Torquing of the upper outer TF support weldments to their final torque levels has been completed The installation of the MPTS vacuum interfaces has been completed and they have passed leak check Center stack casing stud installation complete and ready for PF 1B installation (PFC’s to follow) CS pedestal prefit completed RF antennas removed. Center compliant conductor posts delivery in April. Installation in MAY.  Diagnostics incl racks and cabling re-installation underway  Bus bar fabrication continues... trial fit-ups under the vessel continue  2 PCHERS passive plates being fabricated by Major Tool with delivery expected May.  PFC installation started in the vacuum vessel.  DCPS stage I testing continued using the Autotester (AT) and waveform input files  Startup planning underway with PPPL Activity Certification Committee (ACC) and Operational Readiness Assessment

5 NSTX-U NSTXU Construction Progress – April 25th, 2014 5 Neutral beam component installation nearing completion Neutral Beam & TIV valve Neutral Beam connecting duct assembly (bellows(2),VPS duct) being lowered into position Entire assembly leak tested prior to installation Neutral Beam connecting duct assembly (bellows(2),VPS duct) being lowered into position Entire assembly leak tested prior to installation Vacuum Vessel Bay J/K port Source installation planned for June

6 NSTX-U NSTXU Construction Progress – April 25th, 2014 6 NB component installation (cont) Overhead view of duct assembly Neutral Beam Armor Installed

7 NSTX-U NSTXU Construction Progress – April 25th, 2014 7 OH Coil Winding Going Well Started winding 4 th and final layer Good progress on the centerstack

8 NSTX-U NSTXU Construction Progress – April 25th, 2014 8 Major milestones to completion Completion of OH winding should occur by May 5th VPI completed by May 31 Complete OH/TF activities: May thru July –Removing Aquapour –Final OH testing –Silver plate electrical contact surfaces, Fit-up and installation of laminate crowns –Finalization of TF fittings and bulkheads, Installation of Belleville washer assembly –Assembly and install of PF1A& C coils, Apply ground plane and diagnostics to OH surface –Install “Micro therm” insulation Install CHERS PP June Install HHFW compliant center post May-June Last Access to Vacuum Vessel June 14th Transport CS to NSTX Test Cell August 12th Install centerstack August 25th NB Ion source installation Late June NB VPS system test July Start NB He system and begin NB #1 & #2 pumpdown Mid July Readiness review September Pump down December CD-4 December Rollover schedule at; http://www-local.pppl.gov/dss/CurrentRollover.pdf

9 NSTX-U NSTXU Construction Progress – April 25th, 2014 9 Summary The project continues to make good technical progress and is on track for a December 2014 completion.