THE BUREAU OF ENERGY EFFICIENCY HAS ANNOUNCED NATIONAL ENERGY CONSERVATION AWARD 2007
4
CTO BDLG. MADURAI CTO BUILDING MADURAI IS ONE OF THE TWO BUILDINGS SELECTED BY THE PCE(E) FOR NOMINATION TO THE AWARD
5
BUILDING PROFILE CTO COMPLEX CTO BUILDING CTMX BUILDING LEVEL IV BUILDING CTO COMPLEX IS COMPRISING OF THREE BLOCKS
6
BUILDING PROFILE A- CTO BUILDING G- FLOORPROPOSED SIGNLE WINDOW CSC I FLOORSFMSS EQPT+ ADMN. OFFICE+ IQ II FLOOROFFICE + IQ III FLOORO/oGM(DEV)+CONFERENCE HALL
7
BUILDING PROFILE B - CTMX BUILDING G - FLOORCELL MSC-II + EWSD MDF I - FLOOR STR EQUIPMENT ( IN PROG ) + INTERNET EXCHANGE ( PROPOSED ) II - FLOOREWSD EXCHANGE - 10K III - FLOORADMN. OFFICE
8
BUILDING PROFILE C - LEVEL-IV BLDG. G - FLOORSTR POWER ROOM + OUTDOOR OFFICES I - FLOORCELLONE CSC + STR MUX EQUIPMENT II - FLOORSTR OFFICE + GM (DEV) OFFICE III - FLOORCONFERECCE HALL + STR OFFICE
9
ENERGY CONSUMPTION CHART
10
CONSUMPTION PATTERN
11
REDUCTION IN SPECIFIC ENERGY CONSUMPTION AS A RESULT OF VARIOUS ENERGY CONSERVATION MEASURES ADOPTED THE ENERGY EXPENDITURE HAS COME DOWN DESPITE INCREASE IN CONNECTED LOAD
12
CTO BUILDING - MADURAI ON THE BASIS OF THE ACHIEVEMENTS OF VARIOUS ENERGY CONSERVATION MEASURES ADOPTED, THIS BUILDING HAS BEEN SELECTED FOR THE CONTEST
13
MAJOR ENERGY SAVING MEASURES ADOPTED REPLACEMENT OF 54 NOS. OLD W/T A/C UNITS BY 34 NOS. NEW SPLIT A/C UNITS REPLACEMENT OF CONVENTIONAL TYPE POWER PLANT WITH SMPS POWER PLANT REPLACEMENT OF ( 6 X 7 TR)OLD PACKAGE A/C PLANT WITH ( 4 X 7 TR ) NEW PACKAGE A/C PLANT REPLACEMENT OF DEFECTIVE CAPACITORS BY NEW CAPACITORS AND GOOD PF MAINTAINED
14
REPLACEMENT OF AC UNITS OLD UNIT REPLACED BY NEW S/T AC UNIT
15
REPLACEMENT OF AC UNITS 54 NOS. OUTLIVED A/C UNITS UNITS HAVE BEEN REPLACED BY 34 NOS NEW S/T A/C UNITS RESULTING IN A SAVING OF RS.8,99,360/- PER YEAR.
16
REPLACEMENT OF AC UNITS Energy consumption details for W/T,S/T AC Units DescriptionsOld After replacement NewExisting No. of units1073453 Power consumption (in KW)2.42 No of working hrs/day888 No. of days working365 Total Energy consumption in KWh749856198560371424 Total Energy consumption before replacement (for107 AC units) in KWh 749856 Total Energy consumption after replacement for(34 new units +53 old units) 87 Ac units in KWh 569984 Savings in energy 179872 Savings in cost @ Rs.5/- 899360
17
REPLACEMENT OF CONVENTIONAL POWER PLANT WITH SMPS POWER PLANT
18
THE EXISTING CONVENTIONAL TYPE POWER PLANT HAS BEEN REPLACED WITH SMPS POWER PLANT RESULTING IN A SAVING OF RS.62,550/- PER YEAR
19
REPLACEMENT OF CONVENTIONAL POWER PLANT WITH SMPS POWER PLANT Power saving by replacing conventional power plant by SMPS power plant Description Conventional Power plantSMPS power plant Efficiency of power plant82.64%95% Output power ( KW)7.5 Input power (KW)9.087.89 Total energy consumption/year (Kwh)7954169116 Total cost of the energy (Rs.)477246414696 Savings in Energy /year (Kwh) 10425 Savings in cost/year (Rs.) 62550
20
REPLACEMENT OF DEFECTIVE CAPACITORS
21
THE DEFECTIVE CAPACITORS IN THE POWER FACTOR IMPROVEMENT PANEL HAVE BEEN REPLACED RESULTING IN A SAVING OF RS. 30,799/- PER YEAR. POWER FACTOR ALWAYS > 0.98
22
REPLACEMENT OF PACKAGE AC UNITS 4+2 X 7 TR REPLACED WITH 3+1 X 7 TR
23
REPLACEMENT OF PACKAGE AC UNITS THE EXISTING 4+2 X 7 TR PACKAGE AC PLANT HAS BEEN REPLACED WITH 3+1 X 7 TR PACKAGE AC PLANT RESULTING IN A SAVING OF RS.1028500/- OLDNEW EXPENDITURE
24
REPLACEMENT OF PACKAGE AC UNITS Energy consumption details for PAC units DescriptionOldNew No. of units43 Power consumption (in KW)12.610 No of working hrs/day18 No. of days working365 Total Energy consumption in KWh331128197100 Savings in energy 134028 Cost of Energy @ Rs.5/-unit1655640985500 Savings in cost 670140 other savings Cost of not providing 2 nos 7TR PAC units @ Rs.3,50,000/unit (A) 700000 Saving in energy for 1 units @18 hrs/day working for 365 days. 65700 Cost of Energy @ Rs.5/-unit (B)328500 Total savings (A+B) 1028500
25
PROPOSED ENERGY SAVING MEASURES IN 2007-08 1. CHANGE OF EB TARIFF OF 21 NOS S/Q 2. REPLACEMENT OF FL. FITTINGS WITH ENERGY EFFICIENT FITTINGS 3.PROVISION OF WATER LEVEL CONTROLLER FOR PUMPS 4. CREATING AWARENESS AMONG STAFF BY CONDUCTING PROGRAMMES & THROUGH SLOGANS
26
CHANGE OF EB TARIFF OF S/Q AT PRESENT 21 NOS S/Q ARE BEING FED FROM SUB STATION & ENERGY COST IS RS.5/- PER UNIT ALL ELECTRICAL WORKS FOR GETTING SEPARATE SERVICE CONNECTION FOR S/Q ARE COMPLETED WHEN SERVICE CONNECTION WITH RESIDENTIAL TARIFF IS EFFECTED THERE WILL BE A BI-MONTHLY SAVING OF RS 14,700/- [ 21 S/Q X (RS 5 - RS 2.8) X 250 UNITS ]
27
WATER LEVEL CONTROLLER FOR PUMPS NEARLY 225 EMPLOYEES ARE WORKING & 13 NOS PUMPS ARE AVAILABLE ALL THE PUMPS ARE BEING OPERATED MANUALLY THERE IS A GOOD SAVING POTENTIAL BY PROVIDING WATER LEVEL CONTROLLER FOR THE PUMPS
28
INSTALLATION OF ENERGY EFFICIENT LIGHT FITTINGS 598 NOS TWIN FITTINGS & 316 NOS SINGLE FLUORESCENT TUBE LIGHT FITTINGS ARE AVAILABLE CONNECTED LOAD OF THESE FITTINGS WORKS OUT TO 60 KW IT HAS BEEN PROPOSED TO REPLACE THE ABOVE WITH ENERGY EFFICIENT FITTINGS IN A PHASED MANNER ON COMPLETION OF THE TASK THERE WILL BE A REDUCTION OF 18 KW OF LOAD
29
AWARENESS PROGRAMME ENERGY CONSERVATION AWARENESS WILL BE CREATED THROUGH PROGRAMMES AND SLOGAN STICKERS
30
APPLICATION SENT IN VIEW OF THE ABOVE MEASURES & ACHIEVEMENTS & AS PER THE INSTRUCTIONS OF THE PCE(E) & SE(E), APPLICATION FOR THE ENERGY CONSERVATION AWARD HAS BEEN SENT TO BUREAU OF ENERGY EFFICIENCY