Download presentation
Presentation is loading. Please wait.
Published byDiana Haynes Modified over 9 years ago
1
Annie Griffith Infrastructure Programme Manager July 2007 UK Link Technology Refresh
2
UK Link Background UK Link applications running since 1996, last Technology Refresh completed 2001 UK Link Risk Assessment Carried out in December 2004 UK Link lifespan indicated as 2008 UK Link ownership transferred to xoserve May 2005 UK Link performance deterioration identified 3rd Quarter 2005 3 Month UK Link Technology Feasibility Review sanctioned December 2005 Review recommended upgrade to hardware, database version & application toolset
3
Scope Technology Refresh is an upgrade of the technical components that make up Sites and Meters and Invoicing systems Technology refresh is essential to Enable continued delivery of a reliable and robust set of UK Link systems Allow xoserve to continue to provide services on behalf of Networks Extend UK Link system lifetime for a further 4-6 years The Technology Refresh IS NOT an application re-write No functionality changes to be implemented alongside upgrade
4
Progress since last update Key progress made since last update: Successful conclusion of POC on 7 th May Installation and configuration of all servers at Peterborough Data Centre completed, installation at Wellingborough commenced VPN Link established between Peterborough and Bangalore ODC (interim until WAN Links Delivered) enabling development activities to continue Network Operations Centre (NOC) set up in Bangalore and all support tools selected Interface and network design agreed with National Grid
5
Proof of Concept Sign off of this milestone required successful deliveries across four areas 1.Confirmation of compatibility of selected hardware and software stack 2.Data Migration Including compatibility testing of interface between Oracle v8i and v10g Bulk data migration approach and application of Delta data migration updates 3.Upgrade of the development Toolset, AllFusion:Gen and Oracle Forms and Reports 4.Business Processes Input and Output files processed correctly and generated as per current format Online functionality same as now works on current desktop platform Oracle Reports and Forms functionalities unaffected Testing of at least one of each type of interface Online screens and batch processes perform database updates as now
6
Overall Testing Approach Full code migration and upgrade commenced (unit testing) OAT – being done in 2 phases Jun ’07 – Jan ‘08 OAT1 – machine build confirmation OAT2 – performance testing, operational running against schedules, fall back and recovery testing, testing all associated support procedures, including those across NG data centres. System testing to start : mid Aug - mid Oct UAT : Nov – end Jan to include Shipper Trials : late Nov - early Dec Minimum of 2 further full scale trial migrations planned over summer period to allow for tuning Dress rehearsal of cutover end Jan – early Feb
7
Shipper Trials Only file routing tests to be executed, limited to sample files only SPA files – inbound and outbound Invoices – outbound, with inbound delivery receipt Read files – outbound in case of data logger reads Involvement optional File test approach to be same as followed in past by other projects Use test file naming convention, such as xxx01.TN123456.IDB Shipper trials planned during UAT - late November / early December Planning for this phase due in September
8
Cut-over and Implementation Following POC, initial theoretical estimates for cut-over and implementation timescales produced based on: Data volumes Network Capacity Reconciliation checks needed Potential outage of 3 - 4 days currently Detailed implementation planning activities commenced Looking at cut-over activities and catch-up processing Timescales being challenged, seeking alternative approaches and tuning to reduce outage Minimum of 2 further full scale trial migrations planned over summer 1 or 2 non-effective days may be needed
9
Cutover Approach Data cutover Likely to start 3 weeks in advance of main cutover, then will require “delta” data updates This will have no effect upon the operational service Final cutover starts 22 nd/ 23 rd February 2008 REC invoice to be issued early on Friday 22 nd – due dates will be unchanged Other production runs on 22 nd will be unchanged Outage start time Considering what is most beneficial overall to reduce total elapsed time needed for cut-over, catch-up and return to normal operation Starting after Datalogger issue on Saturday 23 rd seen as optimal start
10
High Level Timetable (Draft) Invoices Friday 22 nd - REC Invoice issued early, due dates unchanged Non-effective Days Mon 25 th Feb - Tuesday 26 th Feb Relief from DM Read liabilities Sun 24 th – Weds 27 th Datalogger files Issued from OLD UK Link Sat 23 rd Suspend daily issue of data logger files Sun 24 th – Weds 27 th Issued from NEW UK Link Thursday 28 th Transfers Last files processed 11pm Friday 22 nd Feb on OLD UK Link Next Transfer Run – Weds 27 th Feb on NEW UK Link
11
Next Steps Code migrations and initial testing activities to continue Commissioning of Wellingborough Data Centre and WAN Links Continue with more in depth Implementation Planning Firm up on outage timings Confirm non-effective days requirement Understand catch-up and return to normal operation Report back at August UKLC with formal notification of outage
Similar presentations
© 2024 SlidePlayer.com. Inc.
All rights reserved.