Presentation is loading. Please wait.

Presentation is loading. Please wait.

Www.salga.org.za 1 The Electrification Indaba Panel discussion: Experiences & lessons learned Mthobeli Kolisa Executive Director: Municipal Infrastructure.

Similar presentations


Presentation on theme: "Www.salga.org.za 1 The Electrification Indaba Panel discussion: Experiences & lessons learned Mthobeli Kolisa Executive Director: Municipal Infrastructure."— Presentation transcript:

1 www.salga.org.za 1 The Electrification Indaba Panel discussion: Experiences & lessons learned Mthobeli Kolisa Executive Director: Municipal Infrastructure Services 15 March 2012

2 www.salga.org.za Achievement The level of access to electricity rose from 36% in 1994 to 82% at the end of 2010 (5,2 million households in 16 yrs) Stimulating economic activity in areas that were otherwise dormant Improved quality of life of the citizens at home, schools, clinics, hospitals, churches, access to pumped water, etc Provided Free Basic Electricity to the poor These are no small achievements However still need to do more – 92% of formal households by 2014

3 www.salga.org.za However... Only fiscus funding electrification in areas where municipalities are not distributors - extent of opportunities for leveraging borrowings? In areas where Eskom is a distributor, alignment of electrification investment with municipal development plans is dependent on personalities rather than inherent in processes and institutional arrangements Costs increasing as the remaining areas are becoming more challenging Urgent need for rehabilitation and refurbishment of infrastructure - put on hold as the focus was on extending services

4 www.salga.org.za Recent historical performance of the program Always behind schedule and catching up in the following years – theoretically there are funding constraints to meet targets but implementation performance is also a major issue Year Connections Target Connections completed to date% Completed 2006/776,30574,25397% 2007/866,87566,13199% 2008/948,44746,38196% 2009/1076,26367,00288% 2010/1184,23528,97634% Total352,125282,74380%

5 www.salga.org.za 2011/12 performance of the program (as @ Jan 2012) ProvinceNo. plannedProject complete with energy supply > 50% progress < 50% progress Construction not started Eastern Cape 8035%28%11%26% Free State 1650%25%6%19% Gauteng 1471%21%7%0% KwaZulu Natal 799%0%53%38% Limpopo 8560%6%8%26% Mpumalanga 2635%15%4%46% North West 683%17%0% Northern Cape 2339%13%22%26% Western Cape 3456%6%15%24% Total36340%12%20%28%

6 www.salga.org.za Some issues for consideration Discussed in terms of 1.Rural 2.Urban 3.Informal Settlements

7 www.salga.org.za Rural 75 % of backlogs Largely areas in which Eskom is a licensed distributor Municipalities (non-licensed and licensed) access money from DoE and Provincial Governments to implement projects in these Eskom areas of supply Hand over infrastructure to Eskom on completion for O&M Current situation

8 www.salga.org.za Rural Non- distributing municipalities do not have electricity departments – completely rely on consultants Also many distributing municipalities have vacancy levels of skilled resources exceeding 50% of established posts (ref: EDI Holdings ring- fencing study) – but still stretch themselves to Eskom areas Consultants approach municipalities to be appointed for designing and managing implementation of projects The design cost is purported to be at risk and the payment is recovered once the project submitted by the municipality is approved; no real risk –Desperate MMs take the first available “support” they can get –No capacity to review the appropriateness of proposed projects and quality of work –INEP offices have no capacity either to support municipalities in this regard Some concerns

9 www.salga.org.za Urban A fraction of the 25% of backlog Largely areas in which 177 municipalities are licensed distributors DoE currently does not allow upgrade of existing infrastructure required for electrification projects, but talks in place to cater for capital reinforcement projects. Infill connections –DoE reluctant to fund infill connections – demand for these connections in existing developments is increasing as more houses are built; also contrary to the objective of densification of spatial development patterns to improve urban efficiency. –Requirement for 80% occupancy of housing developments has also been a delaying factor; also leading to public protests about incomplete houses Current situation

10 www.salga.org.za Informal settlements A significant component of the remaining 25% backlog Numbers of informal settlements are increasing with a consequent requirement from political leaders and communities for `regularisation’ (including electrification) of these areas DoE currently providing for the electrification of informal settlements. Apart from providing the required electrical reticulation, each informal dwelling is also provided with a Pre-paid meter connection and basic connections for electrical fittings. Current situation

11 www.salga.org.za Informal settlements Need for the planning alignment of the Informal Settlement Upgrading Programme with the electrical reticulation programme of the Department of Energy to ensure that electrical grid is available when settlement upgrading projects commence. Will require that provincial governments to make their approved Multi Year Housing Development Plans and priority development objectives available to the DoE enable the latter to align its electrification programme accordingly. Current situation

12 www.salga.org.za Informal settlements Agreement required on the removal and recovery of the installed Pre-paid Meters from informal dwellings and the re-installation thereof in the new dwelling units, constructed through the National Housing Programme. This initiative will require that the National Housing Programme to be adjusted to include funding for the removal of the existing meters and the re- installation thereof in the new dwellings. Current situation

13 www.salga.org.za General Inequitable funding from DoE –DoE policy to partially fund electrification connections by municipalities (urban and rural subsidies) but provide the full cost of connections provided by Eskom, –Municipalities are thus required to `top-up’ funding of electrification projects which impacts the overall municipal budget –Some municipalities face severe financial constraints Limits uptake in smaller municipalities Some poor households not collecting FBS tokens – poor customer relations (service provision is not only a technical exercise) Some concerns

14 www.salga.org.za General Funding application process –Not aligned with the municipal budgeting process –Lack of certainty of three-year DoRA allocations –National Treasury will only release funding to municipalities wef 1 July of each year MFMA procurement process –Many municipalities point to the drawn out procurement processes to appoint service providers and purchase the necessary equipment and materials as reasons for the delay in completing electrification projects; need for a balance between ensuring accountability and functionality Some concerns

15 www.salga.org.za Recommendations Need some shared capacity to provide technical support to under-capacitated municipalities; capacitate INEP regional offices to play this role INEP offices should be the points of coordination/ planning alignment between various electrification projects funding agencies Provincial Housing Departments must make their approved Multi Year Housing Development Plans and priority development objectives available to the DoE enable the latter to align its electrification programme accordingly DoE should allow upgrade of existing infrastructure required for electrification projects DoE should fund infill connections

16 www.salga.org.za Recommendations Requirement for 80% occupancy of housing developments be done away with Adjustment of the National Housing Programme to include funding for the removal of the existing meters and the re-installation thereof in the new dwellings DoE policy should provide the full cost of connections in areas provided by both Eskom and municipalities Eskom to enter into SDAs with municipalities where Eskom is a distributor so as to ensure alignment of expectations That municipalities are rightfully placed at the middle of the relationship between the service and the communities

17 www.salga.org.za Recommendations Upscaled and coordinated skills development program through a partnership that includes the Department of Higher Education, Department of Energy, Eskom, Local Government, Private Sector and the Water and Energy SETA. We support the strategic way forward outlined by the DG in her presentation this morning.

18 www.salga.org.za THANK YOU


Download ppt "Www.salga.org.za 1 The Electrification Indaba Panel discussion: Experiences & lessons learned Mthobeli Kolisa Executive Director: Municipal Infrastructure."

Similar presentations


Ads by Google