Presentation is loading. Please wait.

Presentation is loading. Please wait.

Grant of Connectivity,LTA, MTOA Interstate Transmission system

Similar presentations


Presentation on theme: "Grant of Connectivity,LTA, MTOA Interstate Transmission system"— Presentation transcript:

1 Grant of Connectivity,LTA, MTOA Interstate Transmission system
Regulation 2009 P.S.Das, Ch.Manager ERLDC, POSOCO 4/21/2017 ERLDC: POSOCO

2 Contents Chapter 1: Definitions Chapter 2: General provisions
Chapter 3: Connectivity Chapter 4: Long-term and Medium-term Open Acces Chapter 5: Long-term Access Chapter 6: Medium-term Open Access Chapter 7: Conditions of LTA and MTOA Chapter 8: Information System Chapter 9: Repeals and Savings Contents 4/21/2017 ERLDC: POSOCO

3 Act and Regulatory Provisions
Generation was de-licensed in the Electricity Act 2003 Evacuation of power ensured through CERC notification of Long term open access in Jan 2004 Utilization of ISTS for generation projects was granted by CTU under the regulatory framework

4 Energy Resources Map Energy resources (coal, water etc.) unevenly distributed Coal – In Central India Chhattisgarh : MW Orissa : MW Jharkhand : MW Madhya Pradesh:16000 MW Hydro – In North Eastern & Northern Himalayan region Coastal based Andhra Pradesh: MW Tamil Nadu : MW Gujarat : MW Global electricity sector investment is anticipated to reach USD 10 trillion by It is estimated that investments in transmission and distribution sector would be as much as that in the generation sector during the period. In India the average investment in T&D in India during the Tenth Plan was about 32% of investment in generation The GoI intends to increase installed power generation capacity by 87,663 MW by 2012, it must also facilitate an expansion of the transmission network and inter-regional capacity to transmit power With the strengthening of inter-regional connections by 2012, the inter-regional capacity is predicted to grow from 14,100 MW to 37,150 MW Investment of Rs 1,400 billion (approx. USD 34 billion) envisaged in transmission sector in XI plan To expedite Generation addition of 100,000 MW, GOI is promoting UMPP each of 4000MW capacity to meet its mission of power for all by 2012 POWERGRID has been requested to prepare feasibility reports / detailed project reports in respect of its anticipated role in the construction of the transmission system associated with Ultra mega Power Projects

5 CERC approval for implementation
Regulatory approval was sought for implementation of the transmission system Based on grant of Open access Generation developers signing the BPTA Submission of bank guarantee The transmission scheme is under various stages of implementation Above was developed based on CERC notification, Jan 2004

6 Regulatory frame work - August 2009
Applicant-Who can apply? Connectivity Generating station >= 250MW & CPP of exportable capacity >=250MW 50MW above for hydro/renewables(vide amendment Dtd.3rd Sep,2010) Bulk Consumer – 100 MW and above for hydro/renewables < 50 MW individually but collectively aggregated to >= 50MW through lead generator Medium Term Open Access (MTOA) and Long Term Access (LTA) a generating station including captive generating plant a consumer an Electricity Trader or a distribution licensee

7 Chapter I: Definitions
Connectivity: for a generating station, including a captive generating plant, a bulk consumer or an inter-State transmission licensee means the state of getting connected to the inter-State transmission system Long Term Access: Right to use the inter-State transmission system for a period exceeding 12 years but not exceeding 25 years Consumer means any consumer eligible to avail open access as specified by the State Commission under sub-section (2) of section 42 of the Act;

8 Definitions….. continued
Long-term customer: means a person who has been granted long-term access and includes a person who has been allocated central sector generation that is electricity supply from a generating station owned or controlled by the Central Government; Medium-term open access: means the right to use the inter-State transmission system for a period exceeding 3 months but not exceeding 3 years; Medium-term customer means a person who has been granted medium-term open access;

9 Definitions….. continued
Nodal agency: means the Central Transmission Utility referred to in regulation 4 hereof Regional entity means a person whose metering and energy accounting are done at the regional level; Short-term open access has the meaning ascribed thereto in the Central Electricity Regulatory Commission (Open Access in inter-State Transmission) Regulations, 2008;

10 Definitions….. continued
State network: means the intra-State transmission system owned by the State Transmission Utility, transmission licensee or the network of any other person who has been granted licence by the State Commission to establish or operate distribution lines within the State; Stranded transmission capacity: means the transmission capacity in the inter-State transmission system which is likely to remain unutilized due to relinquishment of access rights by a long-term customer in accordance with regulation 16.

11 Chapter 2: General Provisions
Scope Provided that a generating station, including captive generating plant or a bulk consumer, seeking connectivity to the inter-State transmission system cannot apply for long-term access or medium-term open access without applying for connectivity: Provided further that a person may apply for connectivity and long-term access or medium-term open access simultaneously. Nodal Agency The nodal agency for grant of connectivity, long-term access and medium term open access to the inter-State transmission system shall be the Central Transmission Utility.

12 General provisions….. contd
Filing of Application Applications for grant of connectivity or long-term access or medium-term open access shall be made to the nodal agency an application for connectivity is not required to be made by any transmission licensee, since transmission system planning is carried out in a coordinated manner by the Central Transmission Utility and the Central Electricity Authority an inter-State transmission licensee other than Central Transmission Utility, nevertheless, shall sign a connection agreement with the Central Transmission Utility, as provided for in Clause (5) of regulation 8 of these Regulations.

13 General provisions …contd
Application Fees Sl No Quantum of power to be injected/off taken into/from ISTS Application fees ` lakhs for for for Connectivity LTA MTOA 1 Up to 100MW 2 More than 100MW and up to 500MW 3 More than 500MW and upto 1000MW 4 More than 1000MW

14 General provisions …contd
Time frame for processing

15 Chapter 3: Connectivity
Grant of Connectivity The application for connectivity shall contain details such as, proposed geographical location of the applicant, quantum of power to be interchanged, that is the quantum of power to be injected in the case of a generating station including a captive generating plant and quantum of power to be drawn in the case of a bulk consumer, with the inter-State transmission system and such other details as may be laid down by the Central Transmission Utility in the detailed procedure Provided that where after filing of an application, there has been any material change in the location of the applicant or change in the quantum of power to be interchanged with the inter-State transmission system, by more than : 100 MW in the case of generating station >= 250MW or CPP with exportable capacity of > = 250MW 40% of the Installed capacity in the case of hydro station from 50 to 250MW 40% of the aggregate Installed capacity in the case of aggregated generators individually < 50MW

16 Chapter 3: Connectivity
Grant of Connectivity Provided further that the application by the applicant in case of aggregated capacity >= 50MW but individually < 50MW defined under shall be considered by CTU only if all the generators, whose aggregate capacity is connected at the single connection point, formalize a written agreement among themselves that the lead generator shall act on behalf of all the generators to undertake all operational and commercial responsibilities for all the collective generators connected at that point in following the provisions of the Indian Electricity Grid Code and all other Regulations of the Commission, such as grid security, scheduling and dispatch, collection and payment/ adjustment of Transmission charges, UI charges, congestion and other charges, etc., and submit a copy of the agreement to the CTU, with the application of connectivity, along with a copy to the respective RLDC in whose control area it is located. Amended vide order Dtd. 3rd Sep,2010 On receipt of the application, the nodal agency shall, in consultation and through coordination with other agencies involved in inter-State transmission system to be used, including State Transmission Utility, if the State network is likely to be used, process the application and carry out the necessary interconnection study as specified in the Central Electricity Authority (Technical Standards for Connectivity to the Grid) Regulations, 2007.

17 Connectivity…. contd While granting connectivity, the nodal agency shall specify the name of the sub-station or pooling station or switchyard where connectivity is to be granted. In case connectivity is to be granted by looping-in and looping-out of an existing or proposed line, the nodal agency shall specify the point of connection and name of the line at which connectivity is to be granted. The nodal agency shall indicate the broad design features of the dedicated transmission line and the timeframe for completion of the dedicated transmission line. The applicant and all Inter-State Transmission Licensees including the Central Transmission Utility shall comply with the provisions of Central Electricity Authority (Technical Standards for Connectivity to the Grid) Regulations, 2007. The applicant or inter-State transmission licensee, as the case may be, shall sign a connection agreement with the Central Transmission Utility or inter-State transmission licensee owning the sub-station or pooling station or switchyard or the transmission line as identified by the nodal agency where connectivity is being granted. Provided that in case connectivity of a generating station, including captive generating plant or bulk consumer is granted to the inter-State transmission system of an inter-State transmission licensee other than the Central Transmission Utility, a tripartite agreement as provided in the Central Electricity Authority (Technical Standards for Connectivity to the Grid) Regulations, 2007 shall be signed between the applicant, the Central Transmission Utility and such inter-State transmission licensee.

18 Connectivity … contd The grant of connectivity shall not entitle an applicant to interchange any power with the grid unless it obtains long-term access, medium-term open access or short-term open access. A generating station, including captive generating plant which has been granted connectivity to the grid shall be allowed to undertake testing including full load testing by injecting its infirm power into the grid before being put into commercial operation, even before availing any type of open access, after obtaining permission of the concerned RLDC, which shall keep grid security in view while granting such permission. This infirm power from a generating station or a unit thereof, other than those based on non-conventional energy sources, the tariff of which is determined by the Commission, will be governed by the Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, The power injected into the grid from other generating stations as a result of this testing shall also be charged at UI rates. A thermal generating station of 500 MW and above and a hydro generating station or a generating station using renewable sources of energy of capacity of 250 MW and above, other than a captive generating plant, shall not be required to construct a dedicated transmission line to the point of connection and such station shall be taken into account for coordinated transmission planning by the Central Transmission utility and Central Electricity Authority Amended vide Order Dtd. 3rd Sep,2010

19 Chapter 4 : LTA & MTOA Criteria for Grant:
CTU to consider augmentation of ISTS proposed under the plans made by the Central Electricity Authority. MTOA shall be granted if the resultant power flow can be accommodated in the existing transmission system or the transmission system under execution: no augmentation shall be carried out to the transmission system for the sole purpose of granting medium-term open access: Construction of a dedicated transmission line shall not be construed as augmentation of the transmission system for the purpose

20 LTA & MTOA…. contd Relative Priority:
Applications for long-term access or medium-term open access shall be processed First-come-first-served basis separately for each of the aforesaid types of access: Applications received during a month shall be construed to have arrived concurrently. While processing applications for medium-term open access received during a month, the application seeking access for a longer term shall have higher priority. In the case of applications for long-term access requiring planning or augmentation of transmission system, such planning or augmentation, as the case may be, shall be considered on 30th of June and 31st of December in each year in order to develop a coordinated transmission plan, in accordance with the perspective transmission plans If an intra-State entity is applying for long-term access or medium-term open access, concurrence of the State Load Despatch Centre shall be obtained in advance and submitted along with the application to the nodal agency State Load Despatch Centre shall convey its concurrence to the applicant within ten working days Where necessary infrastructure required for energy metering and time-blockwise accounting already exists and required transmission capacity in the State network exists 3. In case SLDC decides not to give concurrence, the same shall be communicated to the applicant in writing, giving the reason for refusal within the above stipulated period.

21 LTA & MTOA… contd Interface Meters
1. Interface meters shall be installed – by the Central Transmission Utility for and at the cost of the regional entities; by the State Transmission Utility for and at the cost of the State entities. Interface meters for the regional entities shall be open for inspection by any person authorized by the Central Transmission Utility and the Regional Load Despatch Centre. 3. Interface meters for the intra-State entities shall be open for inspection by any person authorized by the State Transmission Utility or the State Load Despatch Centre.

22 Chapter 5 : Long Term Access
Application Name of the entity/ies Quantum of power to be transacted Name of the target region where electricity is proposed to be interchanged in case augmentation required but exact source/destination not firmed up Exact source of source of supply/destination of offtake to be firmed up at least three years prior to availing intended date of LTA Any other information sought by Nodal agency BG of Rs.10000/- per MW of power In favor of Nodal agency Validity till execution of LTA in case of augmentation Till operationalization of LTA when no augmentation reqd Encashment in case of withdrawal or relinquishment of LTA rights prior to operationalization for no augmentation Discharged on submission of new BG for construction ph in case of augmentation

23 Long Term Access….. contd
System Studies Nodal agency to carry out the necessary system studies through coordination with agencies including State Transmission Utility, if the State network is likely to be used Based on the system studies, the nodal agency shall specify the inter- State transmission system that would be required to give long-term access. In case augmentation to the existing inter-State transmission system is required, the same will be intimated to the applicant. The Empowered Committee established in accordance with the ‘Tariff based Competitive-bidding Guidelines for Transmission Service’ issued by the Central Government, may identify one or more elements needed for augmentation of inter-State transmission system to be developed through tariff based competitive bidding

24 Long Term Access….. contd
Communication of Estimate of Transmission Charges, etc. the date from which long-term access shall be granted an estimate of the transmission charges likely to be payable based on the prevailing costs, prices and methodology of sharing of transmission charges specified by the Commission. Execution of Long-term Access Agreement The applicant shall: sign an agreement for long-term access with the CTU. shall sign a tripartite long-term access agreement with the Central Transmission Utility and the inter-State transmission licensee in case of seeking LTA from ISTS licensee other than CTU The long–term access agreement shall contain the date of commencement of long-term access the point of injection of power into the grid point of drawal from the grid the details of dedicated transmission lines, if any In case augmentation of transmission system is required, the long-term access agreement shall specify: the time line for construction of the facilities the bank guarantee required other details in accordance with the procedure.

25 Long Term Access…..contd
Information to RLDC and SLDC Immediately after grant of long-term access, the nodal agency shall inform the RLDCs and the SLDCs concerned so that they can consider the same while processing requests for grant of short-term open access Renewal of Term for Long-term access On expiry the LTA shall stand extended on a written request provided by the long-term customer LTA customer to mention the period for extension that is required The written request shall be submitted by the customer to the Central Transmission Utility at least six months prior to the date of expiry In case no written request, access shall stand withdrawn.

26 Long-term Access… contd
Relinquishment of access rights A long-term customer may relinquish the long-term access rights fully or partly before the expiry of the full term of long-term access, by making payment of compensation for stranded capacity as follows:- Long-term customer who has availed access rights for at least 12 years (i) Notice of one (1) year – application to the CTU at least 1 (one) year prior to the date from which such customer desires to relinquish the access rights, there shall be no charges. (ii) Notice of less than one (1) year – application to the CTU at any time lesser than a period of 1 (one) year customer shall pay an amount equal to 66% of the estimated transmission charges (net present value) for the stranded transmission capacity for the period falling short of a notice period of one (1) year.

27 Long-term Access… contd
Relinquishment of access rights..ctd (b) Long-term customer who has not availed access rights for at least 12 (twelve) years – such customer shall pay an amount equal to 66% of the estimated transmission charges (net present value) for the stranded transmission capacity for the period falling short of 12 (twelve) years of access rights: shall submit an application to CTU at least 1 (one) year prior to the date in case a customer submits an application for relinquishment of long term access rights at any time at a notice period of less than one year, then such customer shall pay an amount equal to 66% of the estimated transmission charges (net present value) for the period falling short of a notice period of one (1) year, in addition to 66% of the estimated transmission charges (net present value) for the stranded transmission capacity for the period falling short of 12(twelve) years of access rights.

28 Long-term Access ….. contd
The discount rate that shall be applicable for computing the net present value as referred to in sub-clause (a) and (b) of clause (1) above shall be the discount rate to be used for bid evaluation in the Commission’s Notification issued from time to time in accordance with the Guidelines for Determination of Tariff by Bidding Process for Procurement of Power by Distribution Licensees issued by the Ministry of Power. The compensation paid by the long-term customer for the stranded transmission capacity shall be used for reducing transmission charges payable by other long-term customers and medium-term customers in the year in which such compensation payment is due in the ratio of transmission charges payable for that year by such long term customers and medium-term customers.

29 Application for Medium-term Open Access
Chapter 6: MTOA Application for Medium-term Open Access The application for grant of medium-term open access shall contain the point of injection into the grid, point of drawal from the grid and the quantum of power for which medium-term open access has been applied for. The start date of the medium-term open access shall not be earlier than 5 months and not later than 1 year from the last day of the month in which application has been made. System Studies by the Nodal Agency On receipt of the application, the nodal agency shall, in consultation and through coordination with other agencies involved in inter-State transmission system to be used, including State Transmission Utility, if the State network is likely to be used, process the application and carry out the necessary system studies as expeditiously as possible so as to ensure that the decision to grant or refuse medium-term open access is made within the timeframe

30 MTOA…… contd Grant of MTOA The applicant shall:
sign an agreement for MTOA with the CTU. shall sign a tripartite agreement with the Central Transmission Utility and the inter-State transmission licensee in case of MTOA from ISTS licensee other than CTU The MTOA shall contain the date of commencement of long-term access the point of injection of power into the grid point of drawal from the grid the details of dedicated transmission lines, if any Immediately after grant of MTOA, the nodal agency shall inform the RLDCs and the SLDCs concerned so that they can consider the same while processing requests for grant of short-term open access

31 Execution of Dedicated Transmission Line
MTOA ….. contd Execution of Dedicated Transmission Line Medium-term customer may arrange for execution of the dedicated transmission line at its own risk and cost before the start date of the mediumterm open access. No overriding preference On the expiry of period of the medium-term open access, the medium-term customer shall not be entitled to any overriding preference for renewal of the term. Exit option for medium-term customers A medium-term customer may relinquish rights, fully or partly, by giving at east 30 days prior notice to the nodal agency: Provided that the medium-term customer relinquishing its rights shall pay applicable transmission charges for the period of relinquishment or 30 days which ever is lesser.

32 Chapter 7: Conditions of LTA & MTOA
Curtailment Transmission constraints or in the interest of grid security - transactions already scheduled may be curtailed by the Regional Load Despatch Centre. Subject to provisions of the Grid Code and any other regulation specified by the Commission, the short-term customer shall be curtailed first followed by the medium-term customers, which shall be followed by the long term customers and amongst the customers of a particular category, curtailment shall be carried out on pro rata basis.

33 Conditions of LTA & MTOA
Transmission Charges The transmission charges for use of the inter-State transmission system shall be recovered from the long-term customers and the medium-term customers in accordance with terms and conditions of tariff specified by the Commission from time to time Provided that if the State network is also being used in the access as a part of inter-State transmission system for the conveyance of electricity across the territory of an intervening State as well as conveyance within the State which is incidental to such inter-State transmission of electricity, recovery of charges for such State network and terms and conditions thereof shall be in accordance with the regulation as may be specified by the Commission under 25 section 36 of the Act for intervening transmission facilities, if such charges and terms and conditions cannot be mutually agreed upon by the licensees; Provided that any disagreement on transmission charges for such State network as specified above, shall not be the sole reason for denying access and either party may approach the Commission for determination of transmission charges for such State network.

34 Conditions of LTA & MTOA
Detailed Procedure Subject to the provisions of these regulations, the Central Transmission Utility shall submit the detailed procedure to the Commission for approval within 60 days of notification of these regulations in the Official Gazette: Provided that prior to submitting the detailed procedure to the Commission for approval, the Central Transmission Utility shall make the same available to the public and invite comments by putting the draft detailed procedure on its website and giving a period of one month to submit comments; Provided further that while submitting the detailed procedure to the Commission, the Central Transmission Utility shall submit a statement indicating as to which of the comments of stakeholders have not been accepted by it along with reasons thereof.

35 Conditions of LTA & MTOA
2.The detailed procedure submitted by the CTU shall, in particular, include— The proforma for the connection agreement (b) The proforma for the long-term access agreement (c) The time line for phasing of construction/modification of the transmission elements by the Central Transmission Utility/transmission licensee, as the case may be, and the coming up of generation facilities or facilities of bulk consumer, as the case may be, so as to match the completion times of the two; (d) Aspects such as payment security mechanism and bank guarantee during the period of construction operation. Provided that the bank guarantee during construction phase shall not exceed Rs. 5 lakh per MW of the total power to be transmitted by that applicant through inter-State transmission system. The proforma for the medium-term open access: agreement, referred to in the second proviso to clause (1) of regulation 21 above. Provisions for collection of the transmission charges for inter- State transmission system from the long-term customers or medium-term customers, as the case may be, by the transmission licensee or the Central Transmission Utility as and when so designated in accordance with the first proviso to clause (1) of regulation 29 hereof and disbursement to the Central Transmission Utility and/or the transmission licensees as the case may be.

36 Conditions of LTA & MTOA
Fees and charges for the Regional Load Despatch Centre and the State Load Despatch Centre The fees and charges for the Regional Load Despatch Centre including charges for the Unified Load Despatch and Communication Scheme shall be payable by the long-term customer and medium-term customer as may be specified by the Commission. The fees and charges for the State Load Despatch Centre shall be payable as applicable.

37 Conditions of LTA & MTOA
Payment of transmission charges and Fees and Charges for the Regional Load Despatch Centre The transmission charges in respect of the LTA and MTOA customer payable directly to the transmission licensee: CTU may be designated by the Commission as agency for the purpose of collecting and disbursing the transmission charges for ISTS CTU shall enter into agreements with the long-term customers and medium-term customers for collection of transmission charges and with the transmission licensees whose inter-State transmission system is being used disbursement of transmission charges: pro rata to the transmission charges payable to the transmission licensees and to the Central Transmission Utility Provided also that the CTU shall be entitled to reimbursement of reasonable costs incurred by it in collecting the transmission charges 3. The fees and charges for RLDCs (including the charges for Unified Load Despatch Scheme) and SLDCs shall be payable by the long-term customer and medium-term customer directly to the RLDCs or the SLDCs concerned.

38 Conditions of LTA & MTOA
Unscheduled Inter-change (UI) Charges Scheduling of all transactions pursuant to grant of long-term access and medium-term open access shall be carried out on day-ahead basis in accordance with the Grid Code. Based on net metering on the periphery of each regional entity, composite accounts for Unscheduled Interchanges shall be issued for each regional entity on a weekly cycle: Provided that Unscheduled Inter-changes accounting for intra-State entities shall not be carried out at the regional level. The State utility designated for the purpose of collection or disbursement of the Unscheduled Interchanges charges from or to the intra- State entities shall be responsible for timely payment of the State’s composite dues to the regional Unscheduled Interchanges Pool Account Fund.

39 Conditions of LTA & MTOA
Any mismatch between the scheduled and the actual drawal at drawal points and scheduled and the actual injection at injection points for the intra- State entities shall be determined by the concerned State Load Despatch Centre and covered in the intra-State Unscheduled Interchanges accounting scheme. Unless specified otherwise by the State Commission concerned, the Unscheduled Interchanges rate for intra-State entity shall be 105% (for overdrawals or under generation) and 95% (for under-drawals or over generation) of the Unscheduled Interchanges rate at the periphery of regional entity. Transmission Losses The buyers of electricity shall bear apportioned losses in the transmission system as estimated by the Regional Power Committee. Redressal Mechanism All disputes arising out of or under these regulations shall be decided by the Commission on an application made in this behalf by the person aggrieved.

40 Chapter 8: Information System
The nodal agency shall post the following documents / information on its website in a separate web-page titled “Long-term access and Medium-term open access information”: These regulations; Detailed procedure; List of applications, separately, for LTA and MTOA received by the nodal agency along with necessary details. Separate lists for LTA and MTOA granted, indicating- (i) Name of customers; (ii) Period of the access granted (start date and end date); (iii) Point or points of injection; (iv) Point or points of drawal; (v) Transmission systems used (in terms of regions and States); (vi) Capacity (MW) for which access has been granted. e) List of applications where approval for connectivity or LTA or MTOA, as the case may be, has not been granted along with reasons thereof. nodal agency to take steps in accordance with the requirements herein to provide as much information suo motu to the public at regular intervals through various means of communications, including internet, so that information is disseminated widely and in such form and manner which is easily accessible to the public.

41 Chapter 9: Repeal and Savings
(1) On commencement of these regulations, Regulation No.’s 4(1)(a), 4(ii), 5(i), 6(i), 7, 8(i), 9, 10, 11, 12, 16(i), 18, as far as it applies to long-term customers, and 31(i) of the Central Electricity Regulatory Commission (OpenAccess in inter-State Transmission) Regulations, 2004, shall stand repealed. (2) Notwithstanding anything contained in clause (1), long-term access granted in accordance with the Central Electricity Regulatory Commission (Open Access in inter-State Transmission) Regulations, 2004 shall continue to be valid till the expiry of the term of long-term access.

42 Issues Ensuring commitment of either parties (Jan 2004 regulation)
BPTA was signed and BG was submitted In the new regulation (Aug 2009) : Readiness of the generation is more critically monitored for aspects like land under possession, water , coal , environmental Developers should realistically bring out the factual position so that an adequate transmission proposal can be evolved and taken further after examination from various aspects. Any under-provision or over-provision of transmission network leads to Grid operational problems like congestion, over-voltage situation – Ultimately causing constraints in generation or ensuring power availability to consumer. As per IEGC ; Generation developers have apply for signing of connection agreement also ensureapproval under Sec 68 of Act from Govt of India is obtained

43 PROCEDURES FOR CONNECTIVITY/LTA/MTOA

44 CONNECTIVITY PROCEDURES
Eligibility Nodal agency No additional connectivity for same capacity Connection agreement / tripartite agreement Information to be submitted alongwith connectivity application: Site identification and land acquisition Environmental clearance Forest clearance(if applicable) Fuel arrangements Water linkage Affadavit alongwith these docs as per format CON-1 Application as per Format CON-2 Application during a month treated as received concurrently

45 PROCESSING TIMEFRAMES

46 CONNECTIVITY PROCEDURES
change in connectivity requirement Eligibility fresh application for change in requirement by > 100Mw/40% of IC, aggregate IC as per format CON-2 Intimation to applicant for grant of connectivity within 60days of last day of month on which app. Received as per –CON3 Additional information as per CON-4 at least > 2 years prior to physical connectivity Further processing by CTU & intimation of connectivity details as per CON-5 Connection agreement as per CON-6 & tripartite agreement in case of any other ISTS licensee Nodal agency to provide copy of connectivity agreement to concerned SLDC/RLDC

47 CONNECTIVITY PROCEDURES
No interchange of power except LTA/MTOA/STOA A generating station, including captive generating plant which has been granted connectivity to the grid shall be allowed to undertake testing including full load testing by injecting its infirm power into the grid before being put into commercial operation, even before availing any type of open access, after obtaining permission of the concerned Regional Load Despatch Centre, which shall keep grid security in view while granting such permission. This infirm power from a generating station or a unit thereof, other than those based on non-conventional energy sources, the tariff of which is determined by the Commission, will be governed by the Central Electricity Regulatory Commission (Terms and Conditions of Tariff) Regulations, The power injected into the grid from other generating stations as a result of this testing shall also be charged at UI rates. In the procedures drawal of power for commissioning activities mentioned as allowable without OA Station shall submit likely date of synchronization, likely quantum and period of injection of infirm power before being put into commercial operation to the SLDC and RLDC concerned at least one month in advance.

48 CONNECTIVITY PROCEDURES
Conditions for construction of dedicated transmission system by CTU BG as per con-7 2.5L/mw FOR < 20kM & 5L/MW for > 20MW or only for connectivity work in case line constructed by applicant Agreement with CTU as per CON-8 For Connectivity/LTA concurrently max 5L/MW Time frame for commissioning from dt. of signing of BPTA/TSA Sharing of dedicated line

49 MTOA PROCEDURES Nodal agency : CTU
earlier than 5 months and later than 1 year from the last day of the month in which application has been made MTOA  > 3 mo & < 3yrs with exception cl. For delay in CTU construction MTOANo augmentation of transmission system is envisaged & Construction of dedicated transmission line shall not be construed as augmentation of the transmission system. A power transaction involving combination of both multiple injections and one drawl point in case the MTOA is sought by a single bulk consumer shall not require filing of separate applications. Eligibility for MTOAgenerating station/captive generating plant/ consumer/Electricity Trader/distribution licensee/State Government owning some quantum of power (like free power given to the State Government in which the hydro station is located, equity power given to a State for allowing a power station to be set up in the State), who desires to utilize ISTS for Inter state transfer of power, provided the power station from which the power is being sourced or the load, as the case may be, is already connected to the grid, whether the State grid or the inter-State grid, or is likely to get connected to the grid before the intended start date of MTOA Documentary evidences

50 MTOA PROCEDURES No application for medium-term open access without applying for connectivity(if not connected) Whether connectivity reqd. in case embedded in a control area? Correctness of Application info to affirmed vide affidavit MTOA-I Application  MTOA-II with SLDC clearances SLDC clearances  MTOA-III within 10days or reasons for refusal Application fees:

51 MTOA PROCEDURES MTOA timelines:
All apps. In a month construed to have come together on last day of month(M0) Approval on FCFS basis CTU studies & circulation to SLDC/RLDCs 15th of M1 Calculation methodology for TTC , RM Comments on studies upto 25th of M1 Provisional decision to grant MTOA  10th of M3 Within a month, priority more for those seeking MTOA for longer duration CTU shall notify the following on 31st day of March of each year: Total Transfer Capability (TTC) for 4 (four) years. This may be revised by CTU due to change in anticipated network topology or change of anticipated generation or load at any of the nodes, giving reasons for such change. Transmission Reliability Margin considered along with basis. Available Transfer Capability (ATC) for MTOA will be worked out after allowing the already approved applications for Long-term access, Medium Term Open Access and Transmission reliability margin. The grant of MTOA shall be subject to ATC as per MTOA-IV Sharing of transmission charges agreement  MTOA-V-30days BG for 2 months transmission charges – 30days bi-annual review Informtion to RLDC/SLDCs Tripartite agreement for other ISTS licensee No over-riding preference for previous holder

52 MTOA SCHEDULING Priority Underutilization of corridor
If request for scheduling is consistently (for more than 5 days) lower than the capacity granted by the Nodal Agency (i.e.; CTU), RLDC may issue a notice to such MTOA customer asking the reasons for such under-utilization. The MTOA customer shall furnish the reasons for such under-utilization and will provide such details like the reduced requirement, likely period, etc. by the following day. The un-utilized transfer capability will then be released for scheduling of Short-term open access transaction. No refund of transmission charges shall be made due to above curtailment Transmission cherges as per Terms & conditions of Tariff-9-14 Billing/collection & disbursement by CTU & adminstrative charge payable STU charges as per SERC norms Irrevocable revolving LC for 105% of average monthly charges 15 days before MTOA commencement BG of 2mo also to be concurrently < 3mo prior to scheduled commencement date and > 1mo after expiry of MTOA period RLDC/ULDC fees & charges payable to RLDC BG encashed in case of default & to be recouped Downsizing of application BG adjusted after expiry of MTOA period

53 MTOA EXIT/DOWNSIZING At least 30 days notice
Exit charges  minimum of [30 days of period of relinquishment] Exit charges used for reducing transmission charges payable by other long-term customers and medium-term customers in the year in which such compensation payment is due in the ratio of transmission charges payable for that year by such long term customers and medium-term For upward revision fresh application

54 LTA PROCEDURES Eligibility conditions same as MTOA For LTA applicant:
(i) already be connected to grid, whether the State grid or the inter-State grid, (ii) have already been granted permission for connectivity to the grid (iii) have already applied for connectivity to the grid (iv) be making application for connectivity to the grid simultaneously with this application in line with the Regulations Documents with application LTA Yrs period May require Transmission augmentation Provision of target regions in case PPAs(purchasing entities) not firmed up applicant shall have to firm up exact source of supply or destination, as the case may be, at least 3 years prior to the intended date of availing long term access at least for a capacity equivalent to 50% of the quantum of power for which LTA has been sought for through signing of PPA with such grid connected entity(ies)/ State Utilities.

55 LTA PROCEDURES The augmentation of the transmission system as identified for grant of LTA shall be undertaken only after fulfillment of above condition. In case a common system augmentation/strengthening has been identified for more than one generator, then the above condition of signing of PPA for at least 50% of LTA sought for, with the grid connected entity(ies)/ State Utilities, shall have to be met by all the generators. In the event of failure of any generator meeting above condition of 3 years prior to the intended date of availing long term access, the implementation of augmentation/strengthening of system shall be undertaken in due consideration of the same and if necessary with the approval of CERC for the same.(Grant of regulatory approval for execution of ISTS schemes to CTU) For the balance capacity (not exceeding 50% of LTA sought for) for which exact source of supply or destination could not be firmed up on long-term basis, the augmentation/system strengthening further from the target region shall be taken up only after identification of exact source/destination. CTU shall be allowed up to 3 years time for such augmentation/system strengthening from the target region to the exact source/destination. During such period the applicant shall be liable to pay the transmission charges up to the target region.

56 LTA PROCEDURES Payment of such transmission charges for the balance capacity for which exact source on long term basis is not known, shall not entitle the applicant any right over the transmission system up to the target region and CTU may release this balance transmission capacity up to target region for short-term open access or the medium term open access till the applicant firms up source/destination on long-term basis and its operationalisation. However, applicant may seek short-term open access or the medium term open access separately till such time it gets long-term access for the balance capacity as any other short-term open access customer or the medium term open access customer. As it takes about 9 months for pre-investment activities and in addition construction time for the transmission project as given in the CERC (Terms and Conditions of Tariff)Regulations, 2009, applicant should expedite the finalization the beneficiaries and intimate to CTU. The date of commencement of LTA shall be applicable from atleast 3 years and 9 months (9 months time required for project preparation and investment approval) from firming up beneficiaries and signing of BPTA/TSA with them. Application for change in quantum/location as per MTOA procedures Nodal agency  CTU

57 LTA PROCEDURES Application in Format LTA-2 with affidavit as per LTA-1
Period for 12 to 25 yrs Not earlier than 3 yrs from last date of month of receipt of application Multiple injection to single pt or single injection to multiple point allowable Connectivity information to be furnished Embedded utilities  concurrance as per LTA-3 BG of Rs.10,000/MW as per LTA-4 BG will stand discharged with operationalization of long-term open access, when augmentation of transmission system is not required or the submission of appropriate bank guarantee required to be given by the applicant to the CTU during construction phase when augmentation of transmission system is required The bank guarantee may be encashed by the nodal agency, (i) if the application is withdrawn by the applicant or (ii) the long-term access rights are relinquished prior to the operationalisation of such long-term access when augmentation of transmission system is not required.

58 LTA PROCEDURES (iii) If the applicant fails to sign the Long Term Access Agreement with CTU or a tripartite agreement with CTU and transmission licensee, as the case may be, and fails to furnish appropriate BG for construction phase, within stipulated time as indicated in the intimation letter. (iv) If the applicant fails to revalidate the earlier furnished BG at least 30 days prior to its expiry. (v) If the applicant fails to firm up beneficiaries,3 years prior to intended date of Long Term Access. Genuine requests for extension of time shall be suitably accommodated on merit upon furnishing of documentary evidence(s). Empowered Committee established in accordance with the ‘Tariff based Competitive-bidding Guidelines for Transmission Service’ issued by the Central Government, may identify one or more elements needed for augmentation of inter-State transmission system to be developed through tariff based competitive bidding: Provided that the agency identified to construct one or more elements needed for augmentation of the inter-State transmission system for long-term access shall be eligible for grant of transmission licence in accordance with the regulations specified by the Commission from time to time and the guidelines for competitive bidding for transmission issued by the Central Government.

59 LTA - APPLICATION PROCESSING
The applications shall be processed on first-come-first-served basis. The applications received during a month and upto the last day of the month shall be construed to have arrived concurrently. System studies to be carried out by CTU methodology for TTC, RM calculations similar to MTOA In case system augmentation not reqd CTU proposal to be discussed in RPCs & planning forum & grant to be given within 120days Transmission system augmentation planning shall be considered on 30th of June and 31st of December in each year in order to develop a coordinated transmission plan. The applications received during 1st half of the calendar year shall be considered together by 30th June and finalized by 31st Dec of the same calendar year. Similarly application received during the 2nd half of the calendar year shall be considered together by 31st December and finalized by 30th June of the next calendar year. The intimation for grant of LTA as per the provisions of Regulations shall be communicated to the applicant and RLDC/NLDC with copy to all the constituent States of the region(s) involved, transmission licensee (if any), concerned RPC(s) and CEA While granting long-term access in ISTS, the nodal agency shall communicate to the applicant, the date from which long-term access is granted and an estimate of the transmission charges likely to be payable

60 LTA - APPLICATION PROCESSING
Confirmation of LTA where system strengthening not required: Grant of LTA within 120days as per LTA-5 Applicant to enter into BPTA/TSA within 30days LTA agreement/tripartite agreement within 30days Confirmation of LTA where system strengthening required: Same with system strengthening elements identified Nodal agency may further optimize without disadvantage to applicant Cosntruction Ph BG to be restricted to Rs.5L/MW in case of concurrent application of connectivity/LTA & construction of dedicated line not required UI accounting: Unless specified otherwise by the State Commission concerned, the Unscheduled Interchanges rate for intra-State entity shall be 105% (for overdrawals or under generation) and 95% (for under-drawals or over generation) of the Unscheduled Interchanges rate at the periphery of regional entity

61 LTA - APPLICATION PROCESSING
In case of applicants who have already firmed up the entity or entities to whom electricity is proposed to be supplied or from whom electricity is proposed to be procured for the entire quantum of power for which LTA has been sought through signing of PPA or, in the case of Inter-State Generating Stations owned by the Central Government or Ultra Mega Power Projects coming up through the initiative of the Central Government, allocation of power to various beneficiaries as notified by it, then the applicant shall not be required to submit Bank Guarantee(BG) with the application form or the Construction Stage BG. In such cases, however, the augmentation of the transmission system as identified for grant of LTA shall be undertaken only after agreement of the beneficiaries in Standing Committee on Power System Planning/Regional Power Committee for bearing its transmission charges. The applicant shall submit a copy of PPA or notification made by Govt. of India, whichever is applicable. The long-term access agreement, may, in such cases be directly signed by the beneficiaries with the CTU or tripartite agreement with the CTU and ISTS, as the case may be System strengthening work to be taken up by CTU/Licensee/empowered committee or on basis of competitive bidding Applicant  90days ahead w.r.t COD/commercialization Nodal 60days ahead intimation w.r.t payment security mech & intimation to RLDCs/SLDCs

62 LTA - APPLICATION PROCESSING
Priority Transmission constraintsCurtailment nor refunds LTA may be extended as per the desired extension period on request by LTA holder at least 6months in advance Surrender of LTA rights Compensation for stranded transmission capacity for LTA customers having availed access rights for 12yrs min Notice period of 1yrs no charges 66% of transmission charge(NPV) corr. to period which fell short of the notice period of 1 year Compensation for stranded transmission capacity for LTA holders who have availed access rights for less than 12yrs With a notice period of 1 yr transmission charges(NPV) corr. to 66% of transmission charges for the period falling short of 12yrs For notice < 1yr, 66% of transmission charges(NPV) for the period short of notice period of 1 year discount rate for NPV  the discount rate to be used for bid evaluation in the Commission‟s Notification issued from time to time in accordance with the Guidelines for Determination of Tariff by Bidding Process for Procurement of Power by Distribution Licensees issued by the Ministry of Power

63 LTA - APPLICATION PROCESSING
Compensation reducing transmission charges payable by other long-term customers and medium-term customers in the year in which such compensation payment is due in the ratio of transmission charges payable for that year by such long-term customers and medium-term customers However, some of the dedicated transmission system indicated at Annexure-3 i.e. from the generation switchyard up to various pooling points/substations shall be built, owned and operated by POWERGRID. The transmission charges for these dedicated transmission system shall be paid by the concerned generation developers. The charges for the transmission system (other than the dedicated system) indicated at Annexure-3 would be borne by the generation developers in proportion to capacity for which long term open access has been sought. The transmission charges will be corresponding to phased development of transmission system and in each time frame, charges should be shared by all the generation developer whose generation projects are scheduled to come up in that time frame or earlier. The long term Open Access Applicants would also have to share the applicable Regional transmission charges in proportion to the Long term capacity sought by them as per CERC norm.

64 LTA - APPLICATION PROCESSING
As the transmission system has been evolved considering target beneficiaries and tentative allocation indicated by the developer(s) in their application, some transmission strengthening may be required in the receiving end/region once the beneficiaries/quantum of allocation is finalized. The cost/tariff of such system strengthening would also have to be borne by the developer(s) as and when identified. In the event of default by any developer under Clause 5 and 6 of this Agreement, the transmission charges for the system mentioned at Annexure-3 would be shared by balance developers. However, the damages collected (if any) from the defaulting developer(s) under clause 5 & 6 of this agreement shall be adjusted for the purpose of claiming transmission charges from the balance (remaining) developers.

65 QUESTIONS?


Download ppt "Grant of Connectivity,LTA, MTOA Interstate Transmission system"

Similar presentations


Ads by Google