1
FLORIDA TECH COMMONS PROJECT Prepared for: Mr. Fran Lemieux Shaw Group
2
Client’s Project Goals Shaw Group Development Corp. Design & construct 62,523 sf commercial office building MS Project construction schedule Project cost & cash flow analysis Develop construction contract & terms
3
Project Management Plan Project Consists of 3 parts Project Controls Project Scope Project Schedule Cash Flow Report Transportation Design Traffic analysis Pavement design Parking lot design Legal Aspects Contract development & terms Preparation for negotiations Regulatory Agencies
4
Project Size and Cost Structure 3 Stories 62,523 sqft total Estimated cost - $479,000 Parking Lot Aggregate cost - $38,000 Asphalt cost - $95,000 Total Estimated Project Cost - $612,000
5
Project Schedule
7
Transportation Design Key Elements of the Design Traffic Analysis Pavement Design & Cost Estimating Parking Lot Design
8
Traffic Analysis Observed Traffic Counts Space Coast TPO Transportation Data Management System FDOT Trip Calculation Software Pre/Post LOS Analysis for Babcock St. and University Blvd.
9
Pavement Design AASHTO Guide For Design of Pavement Structures Use of RAP (Recycled Asphalt Pavement) 2007 RS Means Precision Rock and Dredge – Palm Bay (Lime Stone) VA Paving – Cocoa (HMA)
10
Pavement Design
11
Parking Lot Design City of Palm Bay Codes ADA Guidelines Lights by Outside Source Using ECO Lighting Solutions
12
Parking Lot Design
13
Legal Aspects Contract Development Preparations for Negotiations Permits, Licenses, Agencies
14
Contract Development-1 Contract Development for Florida Tech Commons Description of lands/site Contractors Responsibilities Labor Schedule Permits Owners Responsibilities Communication Payments Insurance
15
Contract Development-2 Tests and Inspections Change Orders Claims – settle orally if possible Dispute Resolution Good Faith Negotiations Mediation Arbitration Litigation Liquidated Damages
16
Negotiations Preparation for Negotiations Gather outside information on possible alternatives and prices to compare to. Establish points of leverage that can be used during negotiation. Set a goal or target maximum/minimum value that you are willing to buy/sell at. Decide initial approach method (friendly negotiation/good cop-bad cop/etc…) Through negotiations try to determine the oppositions stand point (do they NEED an agreement? do they have other options? Etc…) Most importantly, always shoot for a Win/Win conclusion. If both parties can improve their situation and keep a friendly position with each other it will make it easier to negotiate again in the future.
17
Permits, Licenses, Agencies Follow municipal & state codes and regulations Acquire permits and licenses Keep in good standing with agencies and the public
18
Project Summary Schedule Timing Cash Flow Traffic Summary Pavement Features Parking Lot Design Contract Development Negotiation Tactics Acquire Permits and Licenses
19
Thank you for choosing Shaw group Project plan meets client’s goals We will produce a quality project We appreciate your business I will be your project manager My contact information is: Michael Matern 570-493-2053 mmatern23@hotmail.com mmatern23@hotmail.com