1 CIC/VOIP/Construction Update to the IAC 9/7/12 …on behalf of the NOC noc@colostate.edu

2 VOIP…CIC…Construction Funding Methods – CIC: Upgrade building MDFs to dual 1G links – VOIP: Upgrade all network infrastructure to support VOIP – Construction Projects: new buildings or remodels/additions As we move forward: VOIP/NOC is trying to synchronize the three funding sources such that we only go into a building once and completely “VOIP Certify” it.

3 “VOIP Certification” (From the NOC’s perspective) Upgraded, server class switch in MDF with dual 1G links to campus core. All switches brought up to standards Cables color coded, labeled Power over Ethernet (PoE) provided Documentation, monitoring, inventory Network Operations Policy adhered to

4 Dual 1G links recently completed (this Summer) South/West campus core Eddy (VOIP and CIC funding) Guggenheim (VOIP and CIC funding) Johnson (VOIP and CIC funding) Chemistry (VOIP, CIC and department funding) Drake Hall (Construction Project) Industrial Sciences Lab (VOIP funding) 555 S. Howes (VOIP, CIC and department funding) UCA (VOIP, CIC and department funding) Weber (CIC and department funding) Clark C (VOIP, CIC and department funding) Visual Arts (VOIP, CIC and department funding)

5 South and West Campus Cores Switch infrastructure placed at South Campus (DMC and VTH) and West Campus (ACRC and ARBL). This infrastructure has dual 10G links back to main campus with capacity to grow to 20G, 30G,... Provides more economical ability to provide dual 1G and 10G links to buildings at these campuses.

6 Pending (This Fall) Moby (VOIP, CIC, and department funding) – Academic and Training Center – McGraw – Indoor Practice Field Student Services & Centennial Hall (VOIP, CIC funding) Education (VOIP, CIC and department funding) Forestry (VOIP, CIC and department funding) Wagar (VOIP, CIC and department funding) Natural Resources (VOIP, CIC and department funding) Microbiology (VOIP, CIC) Pathology (VOIP, CIC) Washington School (Construction project)

7 VoIP Progress – Main Campus Legend Completed VoIP Certified: Installing phones Network Upgrades in progress Next to start

8 Off Campus Progress Complete RIC Sterling 475 17 th St, Denver University Services Center Drake Hall Engines Lab CVMBS part of Lake & Center Parking Garage In Process UCA 555 Howes St Washington School Board of Governors - Denver

9 Phones Installed – 1090 Phones Remaining – 11,000 Percent Complete – 9% Goal by Year End (Calendar 2012) – 2000 Phones installed – 16% Complete