1 Technology Projects January 1, 2015 – June 30, 2015 MEASURE I CITIZEN’S OVERSIGHT COMMITTEE MEETING

2 TECHNOLOGY AND INSTRUCTIONAL EQUIPMENT MODERNIZATION 2

3 Technology and Instructional Equipment Modernization Technology Advisory Committee (TAC) Recommended:  80 projects for $336K –Rosetta Stone and English Discoveries for Language Lab ($19K) –RAVE Emergency/Mass Notification System ($17K) –Streaming Video Equipment ($18.5K) –Virtual Tour nuCloud system($5K) –Caching system with Solid State Drives for vm servers ($36K) –AV equipment for LVC podiums ($8K) –Eighty computers/printers for student labs ($93K) –Seventy computers/printers for faculty/staff offices ($86K) –Four copiers ($12K) 3

4 4

5 5 myHancock pop-up to collect numbers for Texting

6 6

7 Streaming Video 7

8 VOICE OVER INTERNET PROTOCAL (VOIP) TELEPHONE SYSTEM 8

9 VOIP Telephone Project Progress –  New network core switch live June 3rd Look ahead  Purchase additional telephones  911 location testing  Conference Bridge training material  Fax Server implementation 9

10 10 New Core Switch

11 11 Core Switch Change

12 TECHNOLOGY GENERAL PROJECTS 12

13 Technology General Projects Progress –  Building O-308 iMACs (3.9K) Look ahead  This project is now completed ($400.6K)  Computers/copiers/digital displays for new buildings  ONESolution installation/customizations  Banner workflow/customizations 13