DEPARTMENT OF HUMAN SETTLEMENTS ANNUAL PERFORMANCE REPORT FOR THE PORTFOLIO COMMITTEE FINANCIAL YEAR 2013/14 DIRECTOR-GENERAL: T ZULU.

Similar presentations


Presentation on theme: "DEPARTMENT OF HUMAN SETTLEMENTS ANNUAL PERFORMANCE REPORT FOR THE PORTFOLIO COMMITTEE FINANCIAL YEAR 2013/14 DIRECTOR-GENERAL: T ZULU."— Presentation transcript:

1 DEPARTMENT OF HUMAN SETTLEMENTS ANNUAL PERFORMANCE REPORT FOR THE PORTFOLIO COMMITTEE FINANCIAL YEAR 2013/14 DIRECTOR-GENERAL: T ZULU

2 STRUCTURE OF THE PRESENTATION
Overview of Departmental Performance (April 2013 – March 2014 Performance of the National Department as per Approved Annual Performance Plans 2013/14 Departmental Expenditure vs Performance (Targets/Outcomes) HS Sector Performance 4.1 Communication and Outreach key 4.2 Delivery Agreement (Outcome 8) 4.3 Job Creation 4.4 Accreditation of Municipalities 5. Financial issues Responses to Audited Outcomes / Action Plan

3 Overview of Departmental Performance (April 2013 – March 2014)
The 2013/14 financial year marks the coming of age of the South African Democracy. While on the other hand it marks the ongoing process of government’s efforts to provide shelter as a socio-economic right. Provinces as guided by the National Department, embraced principles of integrated planning, project implementation and synergy in deploying funding. Through collaboration and coordination, Provinces as delivery agents were brought in the outcomes based approach as they discharge their responsibilities to change the Human Settlements space. The department has also revised the finance linked individual subsidy programme to improve the ability of households in the income category R3 501-R to access mortgage finance for housing thus increasing access to housing finance and the provision of shelter and basic services

4 Overview of Departmental Performance (April 2013 – March 2014)
Engagements were held with the private sectors such as Pathfinder Development Company as well as employers such as Harmony Golden to encourage investments and encourage access to affordable housing finance. The NSPU planned to monitor 144 Municipal Infrastructure Grant (MIG) projects and a total number of 152 MIG projects were monitored across 9 Provinces The RHIG Business Plans were received from 24 benefitting municipalities and funds were transferred to municipalities to implement RHIG. The management of the Urban Settlement Grant continued to receive attention in the devolution of powers to the local sphere of government. South Africa is a prominent member of UN HABITAT and continues to advocate and play an instrumental role for the support of human settlements programmes in Africa.

5 Overview of Departmental Performance (April 2013 – March 2014)
The Department of Human Settlements hosted a delegation from Angola’s Ministry of Construction in March 2014.South African and Angola signed a Memorandum of Understanding (MoU) on Co-operation in the field of Human Settlements The Rental Housing Amendment Bill, 2014 has been formally introduced into Parliament on the 20th November 2013, and subsequently referred to the Portfolio Committee on Human Settlements for deliberations New Policy for Backyard Rental Programme was developed and approved by Task Team The CRU policy was adjusted in regard to the grant quantum levels. The Department embarked on filling all the vacant positions to address the challenge of skills. The strengthening of inward and capacity development initiatives is aimed to achieve the mandate of the department of human settlements.

6 Performance of the National Department as per Approved Annual Performance Plans 2013/14
The overall achievement by the National Department of Human Settlements during the financial year 2013/14 is seventy nine (79%). Out of one hundred and twenty-six (126) targets which were planned for the period under review, ninety nine (99) targets were achieved whilst twenty seven (27) targets were not achieved.

7 DEPARTMENTAL EXPENDITURE VS. PERFORMANCE (TARGETS / OUTCOMES)
Branch Final Allocation (Operational) Expenditure Variance % Spent Planned Targets Achieved Variance/ Targets Not achieved % Achieved Targets 1: Administration 71% 25 24 1 96% 2: Human Settlements Delivery Frameworks 98% 13 11 54% 3: Human Settlements Strategy And Planning 76% 17 8 9 47% 4: Programme Management Unit 41% 12 5 5: Office Of The Chief Financial Officer 85% 30 29 97% 6: Office Of The Chief Operations Officer 80% 100% Total 70% 126 99 27 79%

8 HS SECTOR PERFORMANCE

9 COMMUNICATION AND OUTREACH
The Chief Directorate participated in all Ministerial outreach programmes and face to face communication was done with communities with the help desk was set up and individuals queries were logged in for further investigation or solved on site. This was done in collaboration with Municipalities and Provincial Departments of Human Settlements. Public engagements included exhibiting during the annual Rand Show, Pretoria Show, South African Housing Foundation, BRICS Conference. About 4500 generic publications were distributed to GCIS library in Parliament and Thusong Service Centres in Mpumalanga and Limpopo in their regional languages.

10 COMMUNICATION AND OUTREACH CONT
Door to door campaigns were done and publications were handed over to members of the communities during the campaign like on 06 August in Oudtshoorn and 02 October in Lerato Park in Kimberley. Community Imbizos hosted by the Minister and Deputy Minister were held across the country. Other outreach programmes were done by officials during Youth And Women Builds.

11 COMMUNICATION AND OUTREACH CONT
Sanitation Week held in Ward 5 at Makhaza in Khayelitsha - 25 April 2013 Launched Walmer Link FLISP project - 09 May 2013 Community engagements on the Budget Vote in Du-Noon – 22 May 2013

12 STRATEGY Draft Terms of Reference for the Green Paper developed
Rental Housing Strategy Framework developed; the discussion paper about the affordability of rental housing and discussion paper about object subsidies in rental housing Draft sector wide reporting indicators developed Consultation on Draft Strategic Plan across the sector Draft evaluation report submitted to the Technical Working Group for comments

13 PLANNING Draft ToR for the review of the Programme for Human Settlements Chapter of Municipal IDPs developed Progress report on the support rendered to municipalities on the assessment of the Housing Chapters of the IDPs drafted.

14 ENHANCED PEOPLE HOUSING PROCESS
Finalisation of the Human Settlements Policy on community based housing Cooperatives Engaged the Service Provider developing the Policy Engaged SEDA to explore possible collaborations and funding mechanisms for Human Settlements Cooperatives Participates in the DTI Inter-governmental Coordination Committee on Cooperatives to provide an update on Human Settlements Cooperatives Advancement of the self-built methodology Oversight visits conducted in the Western Cape, KZN and North West Provinces to evaluate the implementation of the programme and deliver the required PHP capacity development workshops Support to Provinces in the upgrading of informal settlements through PHP KZN Province and eThekwini Metro to evaluate progress regarding the upgrading of informal settlements through PHP Assessing the M&E assignment of evaluating the impact of the UISP Engaged the CPUT to discuss Human Settlements Summit with focus on alternative building technology

15 INTERNATIONAL RELATIONS PROGRAMME
The Department led a team of South African government officials and academics to the 7th World Urban Forum (WUF 7) in Medellin, Colombia. Outcomes from WUF 7 will support the concept of the long-term planning approach to urban policy and implementation and management thereof. i.e. National Development Plan (NDP) – Vision 2030, as well as respective city visions, which can look as far ahead as 2055 Leading the country preparations for the Third United Nations Conference on Human Settlements and Sustainable Urban Development (Habitat III) in 2016 Finalising the National Report on achievements in the last 20 years, what our remaining challenges are and what we hope to have included in the New Urban Agenda to be adopted at Habitat III

16 STAKEHOLDER AND IGR PROGRAMME
The Department successfully launched the Cornubia Integrated Project in April 2014. The Graskop Project was successfully handed over from the China Government to the South African Government A Memorandum of Understanding was signed with Council of Science and Research. Preparations for the National Govan Mbeki Awards well underway with several successful provincial awards already hosted.

17 STAKEHOLDER AND IGR PROGRAMME
The following Stakeholders were engaged-: Sector engagements through a national workshop on 26 June and have further solicited written inputs to be included in the report before it is submitted to Cabinet for approval in Q2. Held the 4th Quarter Provincial, Municipal and Entity Performance Review Sessions at the end of May and have followed up on the matters arising from the reviews with the relevant provinces, metros and entities

18 STAKEHOLDER AND IGR PROGRAMME
On the Each one settle one campaign the Department has secured a total amount of R for the Youth Build Special Project including the following items: 250 construction work-suits, 50 protective shoes, 150 T-shirts, 200 blankets, a course for the Youth volunteer on skills, enterprise and cooperate training, a business management course, training on plumbing, electrical, general construction, geo-technical and mentorship program, as well as a one week catering for the volunteers. The sponsorship benefited the elderly, the destitute and child headed households. The secured funds paid for furniture, tools and other building materials through the Departmental NHBRC’s sponsorship special account

19 OUTCOME 8 – CREATE SUSTAINABLE HUMAN SETTLEMENTS AND IMPROVED QUALITY OF HOUSEHOLD LIFE

20 UPGRADING OF INFORMAL SETTLEMENTS
Upgrading of households in informal settlements with access to secure tenure rights and basic services: Target for 2014 achieved 2013/14: Total number of households assisted: Total number of households assisted to date: households Represents 111,9% of 2014 target

21 NATIONAL UPGRADING SUPPORT PROGRAMME
Performance 2013/14 : Progress from 35 Municipalities to 50 Municipalities; Achieved 96% of the 2014 target -Technical assistance in place in 47 of 49 NUSP Municipalities plus additional 3 Municipalities that requested support; The 50 Municipalities represents more than 700 informal settlements;

22 INCREASED PROVISION OF WELL-LOCATED RENTAL ACCOMMODATION
PROVINCE TOTAL DELIVERY (1 April 2013 To 31 March 2014) TARGET FOR 2015/ 2016 % OF 2015 TARGET EC 74 2636 2.8 FS 574 1745 38.9 GP 1 083 1200 90.2 KZN 660 865 76.3 LP 61 683 8.9 MP 206 79 260.7 NC 332 NW WC 2 714 1139 238.3 Total 5 704 8347 68.3

23 ACTIONS TAKEN TO ADDRESS CHALLENGES
Revision of current Social and Rental Housing Policies in process; Development of back yard rental policy receiving attention; Declaration of additional restructuring zones being attended to; Monitoring tool for private rental to be put in place; National Department will also undertake the design and costing of higher density housing typologies;

24 ACCREDITATION AND ASSIGNMENT OF MUNICIPALITIES
The annual target of undertaking 6 Workshops to capacitate the municipalities about the Accreditation Implementation Protocol was achieved. The annual target of conducting 6 workshops to capacitate provinces and municipalities on the assignment of human settlements functions to municipalities was achieved. The annual target of assessing 6 municipalities for accreditation at level 2 was not achieved, instead an assessment for the readiness of the 6 Metro municipalities to receive level 3 accreditation was conducted namely : City of Johannesburg, City of Tshwane, Ekurhuleni Metro, City of Cape Town, City of Tshwane and eThekwini Metro.

25 ACCREDITATION AND ASSIGNMENT OF MUNICIPALITIES
To assist the 6 Metros with capacity and subsidisation of the operational costs at the conclusion of the assignment of housing functions, the Municipal Human settlements Capacity Grant to the tune of R900 million was introduced over an MTEF period starting at the 2014/2015 financial year. 74% of 2014 target achieved with: Level 1: 8 District/ Local Municipalities; and Level 2: 20 Metros/ District Municipalities/ Local Municipalities; 4 implementation protocols still outstanding, namely Mangaung Metro, Nelson Mandela Metro, Tlokwe and Rustenburg; No Metro was assigned. National Treasury in the process to resolve the funding procedures and transferring of assets and projects.

26 OUTPUT 3: EFFICIENT UTILISATION OF LAND FOR HUMAN SETTLEMENTS DEVELOPMENT
An additional hectares of land was released by the HDA for future human settlements development. Over the four year period of Outcome 8, a total number of ha (both donated and acquired) of land was released representing 180,9% of the 2014 target. Land Assembly Strategy developed and will be submitted to Human Settlements MINMEC - land pipelines with selected Provinces have been developed to facilitate forward planning and budgeting. HDA commenced with discussions with relevant Provinces and Municipalities to assist with packaging of released land for development

27 OUTPUT 4: IMPROVED PROPERTY MARKET
Mortgage Default Insurance Scheme: Although various discussions were held between the National Department, National Treasury and the Reserve Bank an agreement could not be reached and approval of MDI is still outstanding. Finance Linked Individual Subsidy: Revised Policy implemented in April 2012 – need for additional amendments identified and are receiving attention; An additional 24 projects and subsidies were approved in the 2013/14 financial year; Long term fixed interest rate instrument In view of the low interest rate environment and without immediate steep inflationary expectations at the time, the instrument will not benefit households and will therefore be reconsidered when the market environment has changed 3

28 PERFORMANCE : DEVELOPMENT FINANCE INSTITUTIONS: LOANS GRANTED
TOTAL DELIVERY (1 APRIL 2013 TO 31 MARCH 2014 2015 TARGET NHFC (Mortgage Loans) 149 NHFC (Incremental Loans) 4 000 4 761 NHFC (Value of approvals: Strategic Investment) 72 000 96 499 NHFC (Leverage) 85 439 11 478 RHLF 44 610 49 667 NURCHA 1983 2 800

29 IMPROVED PROPERTY MARKET
During the same period the total number of loans made available by Banks to the GAP market was Total contribution by the DFIs and Banks towards the 2014 target: loans by the NHFC (mortgage loans, incremental loans, wholesale funding and leveraging); loans by RHLF; Construction of units financed through 54 loans granted by NURCHA; and loans to the affordable market by the Banks; and

30 CONSOLIDATION OF DFIS Phase 2 of the rationalisation process commenced. Phase 2 makes provision for the development of a business case and draft enabling legislation for a consolidated Entity.

31 TOTAL EMPLOYMENT CREATED
JOB CREATION The delivery of,48,193 serviced cites and 105,936 houses during the 2013/2014 financial created 53,278 employment opportunities. National TOTAL EMPLOYMENT CREATED Direct Indirect Induced Total Serviced Stand 6,010 603 2,796 9,408 Top Structure 22,492 3,746 17,632 43,869 28,502 4,349 20,427 53,278

32 ENHANCING SERVICE DELIVERY VIA PROFESSIONALISATION
Fledgling Scholarship programme benefiting some 347 beneficiaries since inception. Annual investment by Department is at R 9 million p.a. Bachelor of Human Settlements Development Degree (BHSD) offered via Nelson Mandela Metropolitan University (NMMU). Chair for Human Settlements Development and Management hosted by Nelson Mandela Metropolitan University (NMMU) to develop the body of knowledge in the sector. Cabinet Approval for the Degree and the Chair.

33 SELECTED PERFORMANCE INDICATORS AS PER 2013/2014 STRATEGIC PLAN: PROGRESS STATUS BY PPMU BRANCH
The Klarinet Project, located in the Mpumalanga Province, within the jurisdiction of the Emalahleni Local Municipality, has to date, delivered 1788 housing units while 62 foundations, 67 wall plates and 186 roofs are in the process of being constructed. 5500 units in the first phase of the Khutsong Project, are complete, 4976 foundations have been laid and 4428 wall plates constructed. In the Sweetwaters Project in the City of Johannesburg, 1000 units have been completed and occupied in the adjacent Tulamtwana project. In the Drommedaris Project in the Drakenstein Municipality, 974 housing units have been completed and handed over while in the Duncan Village Project in the Buffalo City Municipality, 5354 housing units have been completed in this project. On the N2 Gateway project, situated, within the jurisdiction of the City of Cape Town, a total of 11,400 units have been completed of the planned units that were planned in Phase 1 of the project.

34 SELECTED PERFORMANCE INDICATORS AS PER 2013/2014 STRATEGIC PLAN: PROGRESS STATUS BY PPMU BRANCH
Construction of houses in the Zanemvula Project, situated in the Eastern Cape, within the jurisdiction of the Nelson Mandela Bay Metropolitan Municipality, is ongoing and to date, 6181 new units have been completed and 1970 units rectified Lerato Park Project, situated in the Sol Plaatje Local Municipality, 491 units have been completed. In so far as the mining towns was concerned, it was firstly necessary to request funding from National Treasury and R1,1billion was subsequently approved for informal settlement upgrading in the identified mining towns The donation of land (with 850 serviced sites) by the Lonmin mining company will assist in providing subsidized housing for the mining community in Rustenburg.

35 ANNUAL REPORT PRESENTATION AS AT 31 MARCH 2014 FINANCIAL PERFORMANCE

36 MTEF Allocation Rand thousand Medium term estimates 2013/14 2014/15 2015/16 Indicative 2016/17 Administration 422,399 Human Settlements Policy, Strategy and Planning 84,055 89 396 94 299 Programme Delivery Support 226,922 Housing Development Finance 27,377,087 Total 28,110,463 Grants and transfers to entities constitute 97% of the total allocation.

37 Allocation MTEF: Transfer payments
2013/14 2014/15 2015/16 Indicative 2016/17 Conditional Grants Human Settlements Development Grant Urban Settlements Development Grant Municipal Human Settlements Capacity Grant - Rural Households Infrastructure Development: Direct Grant 47 624 51 000 Human Settlements Development Grant: Indirect Grant Rural Households Infrastructure Development: Indirect Grant 65 500 67 328 Sub Total Entities Social Housing Regulatory Authority: Operational 32 151 33 480 34 560 36 392 Social Housing Regulatory Authority: Capital Restructuring Grant Housing Development Agency 97 497 Community Schemes Ombuds Services 20 000 40 000 53 000 28 000 Total

38 Summary of Adjustment Budget
Programme Original Budget R`000 Roll-overs Approved R`000 Other Adjustment Disaster Relief Declared Unspent Funds Adjusted Allocation 1. Administration 2. Human Settlements Policy, Strategy and Planning 84 055 3. Programme Delivery Support 4. Housing Development Finance 44 454 Total

39 Adjustment Estimate Rollover approved
R100.5 million Rural Household Infrastructure Grant R20 million for Community Schemes Ombud Service startup funding.

40 Adjustment Estimate Other adjustments Declared Unspent Funds
R44 million to the Human Settlements Development Grant for Disaster relief Declared Unspent Funds R20 million National Upgrading Support Programme

41 Virements after adjustment estimate
Programme Adjusted Allocation R`000 Virements Revised Allocation 1. Administration (17 800) 2. Housing Policy, Research and Monitoring 84 055 2 190 86 245 3. Housing Planning and Delivery Support (12 500) 4. Housing Development Finance 28 110 Total -

42 Virements after adjustment estimate
A virement of R28.1 million from other programmes to programme 4: Housing Development Finance was approved to fund the prepayments of the Rural Household Infrastructure grant amounting to R33 million. A virement of R2.1 million from Programme 1: Administration to Programme 2: Housing Policy, Research and Monitoring was approved to partially fund the Govan Mbeki awards.

43 Annual Expenditure per Programme as at 31 March 2014
Programmes Final Allocation R`000 Expenditure Variance % Spent 1. Administration 74% 2. Human Settlements Policy, Strategy and Planning 86 245 73 327 12 918 85% 3. Programme Delivery Support 90 797 47% 4. Housing Development Finance 99% Total 98%

44 Reasons for underspending
Funds provided for the Special Investigation Unit (SIU) were not fully utilized. Under spending is due to the SIU not invoicing the Department or not providing the department with supporting documentation on work performed and invoiced. The Department held various meetings but could not resolve the matter. Funds provided for the leasing of additional office accommodation have not been fully utilised. The unspent portion of the Property Management portfolio is in respect of leasing of both 240 and 260 Justice Mahomed Street buildings. The Department of Public Works (DPW) entered into a seven year lease agreement on behalf of the Department for these buildings, effective from 01 January 2011 to 31 December 2018. A dispute arose between the DPW and the landlord that led to a delay in planned building refurbishment and tenant installation as well as the subsequent occupation of the additional office accommodation. i.e. (260 Justice Mohamed Street building) Delay in the implementation of the National Upgrading Support Programme (NUSP).

45 Reasons for under spending cont.
Other major contributing factor applicable throughout the Department is under spending on compensation of employees which amounted to R38.4 million and can be attributed to the following: Delays experienced in qualification verification by the South African Qualifications Authority (SAQA) for candidates who have been recommended. A meeting was arranged between the Department and SAQA in the 3rd Quarter and improvement has since been seen. Posts that had to be re-advertised due to the fact that no suitable candidates could be found. Problems were experienced with non-disclosure of criminal records on applications disqualifying selected candidates

46 Transfer payments as at 31 March 2014
Total Allocation R`000 Expenditure Variance % Spent Human Settlements Development Grant - 100% Urban Settlements Development Grant Disaster Relief Grant 44 454 Rural Households Infrastructure Development 25 060 90% Social Housing Regulatory Authority: Operational 32 151 Social Housing Regulatory Authority: Capital Restructuring Grant 65% Housing Development Agency 97 497 National Urban Reconstruction and Housing Agency Nelson Mandela University 3 949 Bursaries Scheme 4 220 4 553 (333) 108% UNHABITAT 1 100 1 075 26 98% Community Schemes Ombud Service 17 000 Total 99%

47 Human Settlements Development Grant (HSDG)Expenditure: 31 March 2014
Provinces DoRA Allocation 2013/14 Additional / Disaster relief Reallocation/ (Stopped) Total Available Actual Transfer Amount Received by Province Amount Spent by Province % Spent R'000 Eastern Cape 2,523,803 - 100% Free State 1,120,936 230,000 1,350,936 Gauteng 4,108,399 4,095,445 KwaZulu-Natal 3,235,428 40,156 57,000 3,332,584 3,333,979 Limpopo 1,324,742 1,368 (644,000) 682,110 303,449 44% Mpumalanga 1,124,332 1,764 1,126,096 1,014,826 90% Northern Cape 395,724 207,900 603,624 577,450 96% North West 1,224,537 117,000 1,256,637 1,341,523 107% Western Cape 1,925,971 1,166 32,100 2,044,137 1,959,237 Total 16,983,872 44,454 17,028,326 16,500,648 97%

48 Delivery Performance of HSDG as at 31 March 2014
Province Annual Delivery Targets Delivery Performance as at 31 March 2014 Variance Delivery sites Variance Delivery Top Structure Total Variance Delivery Sites (units) Top Structure (units) Total Delivery Targets Total Delivery Performance Eastern Cape 15,316 20,341 35,657 11,720 12,646 24,366 3,596 7,695 11,291 Free State 5,028 8,341 13,369 7,203 6,920 14,123 -2,175 1,421 -754 Gauteng 13,173 30,351 43,524 8,959 22,352 31,311 4,214 7,999 12,213 KwaZulu-Natal 3,362 25,377 28,739 2,790 29,151 31,941 572 -3,774 -3,202 Limpopo 493 7,382 7,875 68 3,080 3,148 425 4,302 4,727 Mpumalanga 3,319 16,404 19,723 7,578 8,126 15,704 -4,259 8,278 4,019 Northern Cape 4,734 1,735 6,469 2,875 2,464 5,339 1,859 -729 1,130 North West 2,110 14,092 16,202 305 9,362 9,667 1,805 4,730 6,535 Western Cape 6,629 13,414 20,043 6,695 11,835 18,530 -66 1,579 1,513 Total 54,164 137,437 191,601 48,193 105,936 154,129 5,971 31,501 37,472

49 Performance of the USDG as at 31 March 2014
YEAR TO DATE (01 JULY - 31 MARCH 2014) EXPENDITURE Municipality Allocated Funds National Rollovers Total Available Transferred Funds Spent by Municipality Variance Spent vs Transferred Variance Spent vs Total Available Spent as % of Total Available Unspent as % of Total Available R'000 Buffalo City 613,305 176,875 790,180 409,323 203,982 380,857 51.8% 48.2% Nelson Mandela Bay 727,986 - 341,504 386,482 46.9% 53.1% Mangaung 596,719 129,450 726,169 333,054 263,665 393,115 45.9% 54.1% Ekurhuleni 1,584,912 69,509 1,654,421 906,707 678,205 747,714 54.8% 45.2% City of JHB 1,488,877 70,347 1,559,224 607,204 881,673 952,020 38.9% 61.1% City of Tshwane 1,290,611 791,087 499,524 61.3% 38.7% eThekwini 1,580,999 1,007,292 573,707 63.7% 36.3% City of Cape Town 1,193,497 66,276 1,259,773 486,797 706,700 772,976 38.6% 61.4% Total 9,076,906 512,457 9,589,363 4,882,968 4,193,938 4,706,395 50.9% 49.1%

50 Urban Settlements Development Grant (USDG) Expenditure as at 30 June 2014
YEAR TO DATE (01 JULY - 31 MARCH 2014) EXPENDITURE Municipality Allocated Funds National Rollovers Total Available Transferred Funds Spent by Municipality Variance Spent vs Transferred Variance Spent vs Total Available Spent as % of Total Available Unspent as % of Total Available R'000 Buffalo City 677 100% 99.9% 0.1% Nelson Mandela Bay - 100.0% 0.0% Mangaung 75 032 89.7% 10.3% Ekurhuleni 69 509 87.3% 12.7% City of JHB 70 347 92.1% 7.9% City of Tshwane 44 830 96.5% 3.5% eThekwini 0% City of Cape Town 66 276 77.3% 22.7% Total 92.3% 7.7%

51 What USDG was used for as at 30 June 2014
Description Total Available Funds Expenditure on Total Available Funds Variance on Total Available Funds % Spent on Total Available R'000 Spatial Development and the Built Environment 89.7% Transport 89.2% Water 92.2% Sewerage ( ) 110.1% Solid Waste Management 16 244 90.1% Electricity 81.5% Socio-Economic Amenities 40 592 90% Local Economic Development and Job Creation 44.2% Vat 89 402 - 100% Total 92.3%

52 Financial Performance - BCM
Buffalo City Services 2013/14 Adjusted budget YTD Expenditure % Water 78,537,212 78,537,213 100% Sanitation (waste water) 190,031, 698 190,031,698 Electricity 38,667,450 Roads & Storm Water 314,288,283 314,156,492 Human settlements programme 141,031,375 140,430,865 Transport 23,999,295 23,999,294 Solid Waste Management 3,684,205 3,680,008 TOTAL 790,179,608 789,503,174

53 Non-financial Performance - BCM
The 100% expenditure of the Metro was on the following: 1 729 serviced sites 3,7 ha of land procured 56 km of roads resealed 406 km roads rehabilitated 56 km storm water drainage installed 8 km pedestrian walkways constructed 143 water service points (taps) installed for informal settlements dwellers 622 households (RDP) have been provided with access to free basic level of potable water connections 1 082 new households (RDP) with sewer connections 448 sanitation service points installed connections for backlog in the provision of basic sanitation services

54 Non-financial Performance - BCM
The 100% expenditure of the Metro was on the following: households have been provided with kerb-side waste removal services in formal areas 1 500 street lights installed 517 households(RDP) provided with electricity connections 7 project of waste minimization projects have been initiated 10 community halls have been developed 6 sports fields developed 8 parks developed 13 cemeteries developed 1 fire safety and emergency facility developed 669 jobs created through EPWP and other municipal programmes

55 Financial Performance - NMBM
Nelson Mandela Bay Services 2013/2014 Adjusted Budget YTD Expenditure % Servicing of sites 171,261,100 171,758,447 100% Upgrading of gravel roads and provision of stormwater 64,227,488 64,227,469 Provision of bulk sanitation services 224,698,222 224,262,039 Provision of bulk water services 178,397,400 178,397,334 TOTAL 727,986,000

56 Non-financial Performance - NMBM
The 100% expenditure of the Metro was on the following: 43.73 ha of land procured for Greenfields development 4 012 sites serviced 10 informal settlements upgraded (in-situ) 1 informal settlements upgraded - relocation 3.31 km graveled roads 20.45 km tarred roads rehabilitated 1.46 km storm water drain installed 3.58 km pedestrian walkways constructed 773 households (RDP) connected to water 773 households (RDP) connected to sanitation 2 459 households (RDP) connected to electricity 77 new street lights 366 high mast lights installed 1 sport field developed jobs created through EPWP

57 Financial Performance - Mangaung
Services 2013/2014 Adjusted Budget YTD Expenditure % Engineering Services (Sanitation, Roads and Waste) 343,686,390 326,112,472 95% Water Services 199,223,636 180,577,383 91% CENTLEC (Electricity) 52,631,580 31,383,501 60% Planning 44,189,512 53,416,081 97% Social Services 35,129,154 28,029,606 80% Corporate Services 28,806,892 27,017,899 94% Human Settlements and Housing 11,502,078 4,599,615 40% TOTAL 726,169,242 651,136,557 90%

58 Non-financial Performance Mangaung
The 90% expenditure of the Metro was on the following: 2 181 title deeds transferred to eligible beneficiaries 3 informal settlements upgraded - relocation 1 km of paved road 55 km of roads resurfaced 1 km of storm water drainage installed 18 km pedestrian walkways constructed 1 475 formal domestic consumers receiving water services 1 500 water service points (taps) installed for informal settlements 500 households (RDP) provided with water connection 3 625 units provided with access to free basic water 1 550 formal domestic consumers receiving sewerage services 450 households (RDP) provided with sewer connection

59 Non-financial Performance Mangaung
The 90% expenditure of the Metro was on the following: households with weekly-kerb waste removal services households in informal settlements with access to waste removal 26 high mast lights installed in informal settlements 552 households (RDP) were connected to electricity households provided with access to free basic electricity 1 community hall constructed 3 sports fields constructed 2 parks developed 1 swimming pool developed 6 cemeteries developed 1 687 jobs created through EPWP

60 Financial Performance - Ekurhuleni
Services 2013/2014 Adjusted Budget YTD Expenditure % Disaster & Emergency 27,054,350 26,194,227 97% EMPD 13,650,000 7,407,380 55% Energy 214,300,000 208,774,774 Environmental Resources Management 1,110,000 1,106,922 99% Human Settlements 64,066,538 29,333,380 46% Roads and Storm water 573,721,860 87% Health and Social Development 66,860,000 65,849,994 98% Economic Development 35,650,000 33,872,192 95% SRAC 127,975,000 123,394,311 96% Transport Planning and Provision 35,700,000 29,257,363 81%

61 Financial Performance - Ekurhuleni
Services 2013/2014 Adjusted Budget YTD Expenditure % Water & Sanitation 182,200,000 151, 837,290 83% Erwat- Wastewater treatment 50,000,000 100% Interim sanitation services (Chemical toilets) 160,916,650 154,349,245 96% Waste Management (land fill sites) 31, 29,217,417 92% Real Estate 37,600,000 31,306,050 Human Settlement USDG (Opex) 31,566,282 - 0% TOTAL 1,654,420,680 1,444,715,157 87%

62 Non-financial Performance - Ekurhuleni
The 87% expenditure of the Metro was on the following: 48 serviced sites 1 486 title deeds transferred 283 KMs of roads paved 374 KMs of graveled roads 350 KMs of roads surfaced/ rehabilitated 107 KMs of storm water drainage installed 64 KMs of pedestrian walkways constructed 1 bus terminal constructed 7 bus stops constructed 2 148 formal domestic costumer receiving water and sanitation services 154 water services points (taps) installed for informal settlements dwellers

63 Non-financial Performance - Ekurhuleni
The 87% expenditure of the Metro was on the following: households in informal settlements with access to refuse removal households (RDP) with access to refuse removal 12 waste minimization projects initiated 55 high mast lights installed in informal settlements households (RDP) provided with electricity connections 1 sports field and stadia developed 5 clinics developed 1 fire safety and emergency facilities developed jobs created using the EPWP

64 Financial Performance – City Of Johannesburg
USDG Projects – FY 13/14 2013/2014 Adjusted Budget YTD Expenditure % Expenditure R’000 Formalisation of Informal Settlements 254,524 303,873 119.4% Bulk , Link and Internal Infrastructure(water, sewer, Electricity; Roads & Storm-water) 899,162 796,075 85.3% Electrical (Substations & Streetlights) 125,715 117,341 93.3% Mixed Rental / Hostel Upgrade 96,138 85,657 89.1% Land Acquisition 20,000 19,654 98.3% Upgrade of Community Centres & Sport fields 50,090 49,306 98.4%

65 Financial Performance – City Of Johannesburg
USDG Projects – FY 13/14 USDG Budget Quarter 4 Expenditure % Expenditure R’000 Upgrade Of Clinics 30,730 23,247 75.6% Upgrade Of Landfills 46,865 34,143 72.9% Upgrade Of Parks & Cemeteries 36,000 35,726 99.2% Total 1,559,224 1,465,022 94%

66 Non-financial Performance – City Of Johannesburg
The 94% expenditure of the Metro was on the following: 20 ha of land procured for greenfield development 35 ha procured for brownfield development 1 440 km of roads graveled 242 km of roads resurfaced 18 km of roads resealed formal domestic consumers receiving water and sewerage services 3 069 households (RDP) provided with water connections 967 households provided with access to potable water 783 sanitation services points (toilets) installed for informal settlements dwellers

67 Non-financial Performance – City Of Johannesburg
The 94% expenditure of the Metro was on the following: households with weekly-kerb waste removal in formal areas households in informal settlements with access to refuse removal 4 waste minimization projects initiated formal households with access to basic electricity 1 610 high mast lights installed in informal settlements 1 562 households (RDP) connected to electricity 3 846 households provided with access to free basic electricity 1 Parks and 1 Garden constructed 2 clinics constructed 1 cemetery completed 34 markets developed 7 Fire and safety emergency facilities developed jobs created through EPWP

68 Financial Performance – City Of Tshwane
City of Tshwane Municipality Services 2013/2014 Adjusted Budget YTD Expenditure % Agriculture and Environmental Management 24,000, 000 7,604,390 31.68% Housing & Sustainable Human Settlements 469, 824, 650 445,971,291 94.92% Water and Sewer 491,735,544 489,558,668 99.56% Electricity 56,150,000 55,157,133 98.23% Sports and Recreation(SRAC) 10,000,000 9,700,270 97.00% Transport 198,190,806 198,611,555 99.85% Project management and design (technical assistance) 40,000,000 39,177,936 97.94% Total 1, 290,611, 000 1,245,781,243 97%

69 Non-financial Performance – City Of Tshwane
The Metro has spent 97% on the following: 221 ha. of land procured for human settlements development 160 ha. of land proclaimed (township establishment completed) KMs roads paved 1 555 KMSs of storm water drainage installed water service points (taps) installed for informal settlement households (RDP) provided with water connections of formal domestic customers receiving sewerage services households with weekly kerb-side waste removal services in formal areas 158 households in informal settlements with access to refuse removal households (RDP) with access to refuse removal

70 Non-financial Performance – City Of Tshwane
The Metro has spent 97% on the following: formal households with access to basic electricity 45 high mast lights installed households provided with access to Free Basic Electricity 14 libraries developed fire safety and emergency facilities developed jobs created using the EPWP

71 Financial Performance – Ethekwini
Service Budget 2013/14 R’000 Expenditure R’000 % Built Environment 1,388 1 510 109% Fully Subsidies Housing 150 179 119% Ablution Blocks, Interim Services 293 558 190% Sanitation 198 135 68% Water 411 223381 93% Roads and Storm water Control 117 116 99% Electricity 247 141 65% Social facilities 2 0% LED and Job Creation 157 71 37% Zone Plans 90 64 7% Township Renewal 103 71% TOTAL 1,581 1, 581 100%

72 Non-financial Performance – Ethekwini
The 100% expenditure of the Metro was on the following: ha. of land acquired for human settlements development 715 ha. of land procured for green field development ha. of land procured for brown field development 21 informal settlements with upgrading plans sites serviced 904 title deeds transferred 119 pedestrian walkways constructed 26 KMs of paved roads 1 bus terminals constructed

73 Non-financial Performance – Ethekwini
The 100% expenditure of the Metro was on the following: 1 129 water services points (taps) installed for informal settlements dwellers households (RDP) provided with water connections consumers provided with access to a free basic level of potable water 1 129 sanitation service points (toilets) installed for informal settlement dwellers households (RDP) provided with sewer connections households in informal settlements with access to refuse removal households (RDP) provided with access to refuse removal formal households with access to basic electricity households (RDP) provided with electricity connections households provided with access to free-basic electricity jobs created using the EPWP

74 Financial Performance – City Of Cape Town
Service Budget 2013/14 Expenditure % Electricity Services 82.8% Solid Waste services 100% Water services 78.2% Parks 85% Sport, Recreation and Amenities 51, 268, 300 66% Library services 77% Infrastructure and maintenance 88.3% City of Cape Town Transport 98.6% Health Services 48.1%

75 Financial Performance – City Of Cape Town
Service Budget 2013/14 Expenditure % Existing Settlements 31,914,023 15,560,693 48.8% New Settlements 190,053,601 132,733,507 69.8% HS Strategy & Planning 60,000,000 53,828,338 89.7% Urbanisation (incl. in-situ upgrades) 95,476,811 49,031,433 51.4% Urban Regeneration 5,000,000 0% Spatial Planning and Urban Design 354,209 100% Project Pre-Planning 38,536,344 20,188,339 52.4% Project management Fees 17,714,963 Province Allocation (Metro Projects) 19,923,120 Total 1,259,772,794 973,226,147 77.3%

76 Non-financial Performance – City Of Cape Town
The 77% expenditure of the Metro was on the following: 8 120 sites serviced 6 151 title deeds of sale agreements signed with identified beneficiaries 12 KMs roads resealed 123 roads rehabilitated 10 KMs pedestrian walkways constructed 1 bus terminal constructed 80 bus stops constructed formal domestic customers receiving water services 4 827 service points (taps) installed in informal settlements toilets installed in informal settlements

77 Non-financial Performance – City Of Cape Town
The 77% expenditure of the Metro was on the following: consumer units provided with access to free basic water formal domestic consumers receiving sewerage services households provided with solid waste removal households provided with access to basic electricity job opportunities created through EPWP

78 RESPONSE TO AUDITED OUTCOMES 2013-14

79 AUDITOR’S OPINION Unqualified opinion with emphasis of matters

80 EMPHASIS OF MATTERS IN THE AUDIT REPORT
Material underspending of the vote The department has materially underspent the budget on programme 2 , spent R12 433 000 of its allocation of R 87 773 000 in respect of Programme Implementation Facility. The department spent R108  of its allocation of R133  pertaining to implementation of the RHIG. The department was also allocated an amount of R106 721 000 to be transferred to municipalities; however these transfers were only transferred in March 2014 and a significant portion of these grants were unspent at 31 March 2014.

81 EMPHASIS OF MATTERS IN THE AUDIT REPORT CONT.
Predetermined objectives - Programme 2, 3 and 4 Changes to objectives, indicators and targets not approved Material changes were made to indicators and targets reported in the annual performance report without these changes being approved by the Minister Consistency of indicators and targets Reported indicators and targets were not consistent with those in the approved annual performance plan.

82 EMPHASIS OF MATTERS IN THE AUDIT REPORT CONT.
Measurability of indicators targets Departmental target were not specific. Auditor General could not measure the required performance. Reliability of reported performance information Significantly important targets were not reliable when compared to the source information or evidence provided.

83 EMPHASIS OF MATTERS IN THE AUDIT REPORT CONT.
Non-Compliance with laws and regulation Strategic planning and performance management Effective, efficient and transparent systems of risk management and internal control with respect to performance information and management was not in maintained as required by section 38(1)(a)(i) of the PFMA. Annual financial statements, performance and annual reports The financial statements submitted for auditing were not prepared in accordance with the prescribed financial reporting framework as required by section 40(1) (b) of the Public Finance Management Act.

84 EMPHASIS OF MATTERS IN THE AUDIT REPORT CONT.
Human resource management and compensation Funded vacant posts were not filled within 12 months as required by Public Service Regulation 1/VII/C.1A.2. A human resource plan was not in place as required by Public Service Regulation 1/III/B.2(d). Asset management and liability management Proper control systems to safeguard and maintain assets were not implemented, as required by section 38(1)(d) of the Public Finance Management Act and Treasury Regulation (a).

85 MANAGEMENT’S REPONSE REGARDING AUDIT OUTCOME
An action plan has been developed as a tool to address all the findings raised by the Auditor General. An action plan was populated with all the findings and circulated to responsible Deputy Director Generals and the Chief Directors for planed actions that are aiming at addressing the findings and mitigating/eliminating the risk of the similar audit finding being raised again in future.

86 MANAGEMENT’S REPONSE REGARDING AUDIT OUTCOME CONT.
Planned actions are monitored on a monthly basis by the CFO branch, whereby managers are required to provide progress and evidence to support what has been done. The progress is reported to the Auditor General, Audit Committee and EMT. Auditor General provides a feedback on a quarterly basis in a form of a Dashboard Report whereby the Director General is expected to come up with commitments that will address discrepancies identified during the assessment.

87 “We have come a long way – Celebrating 20 Years of Freedom!”
THANK YOU “We have come a long way – Celebrating 20 Years of Freedom!”