Project Delivery Selection Approach Keith R. Molenaar, PhD CDOT CM/GC Workshop Denver, CO February 7, 2012
2
Overview Why do we need a delivery selection guide? How was it developed? How does is work? What is the result? What are the benefits?
3
Why do we need a selection guide? The project delivery decision is complex Structured discussions promote team alignment Promotes training and organizational learning 3
4
How was it developed? CDOTFHWA ACECCCA ICAC Pilot Projects Delivery Decision Guide
5
How does it work? Create project description checklist Develop project goals Evaluate the four primary factors 1. Delivery schedule 2. Complexity & innovation 3. Level of design 4. Initial project risk assessment Evaluate the four secondary factors 5. Cost 6. Staff experience / availability 7. Level of oversight and control 8. Competition and contractor experience
6
What is the result? Project Delivery Decision Report Opportunities / Obstacles Primary Models Considered Project Goals Project Description
7
Project Example Bridge replacement on westbound US 36 over Baseline Road Funding is in place Design is at ~20% complete Project Goals: Complete project in one construction season Minimize disruption Major Challenges: ROW, Utilities, Environmental Approvals Maintain access to Baseline exit
8
Workshop Blank Form Example Evaluate Opportunities and Obstacles for Primary and Secondary Factors
9
Opportunity and Obstacles Checklist Example
10
Project Example Bridge replacement on westbound US 36 over Baseline Road Funding is in place Design is at ~20% complete Project Goals: Complete project in one construction season Minimize disruption Major Challenges: ROW, Utilities, Environmental Approvals Maintain access to Baseline exit
11
Delivery Selection Matrix Summary
12
What are the benefits? Provides defensible delivery decision Promotes a better understanding of project goals, risks and opportunities Educates team members on alternative delivery methods Promotes organizational learning for CDOT and its partners
13
Additional Information Please contact: Nabil F. Haddad, P.E. Innovative Contracting Program Manager Colorado Department of Transportation Project Development Branch 4201 East Arkansas Avenue, 4th Floor Denver, Colorado 80222 Tel: (303) 757-9104 Cell: (303) 349-0100 Email: Nabil.Haddad@dot.state.co.usNabil.Haddad@dot.state.co.us