1 PFP QSR, 4/19/2011 Particles and Fields Package Quarterly Status Review (QSR) April 19, 2011 Dave Curtis, PFP PM
2
2 PFP QSR, 4/19/2011 SSL Contracting Status Funded through the end of April More info in the Business Splinter presentation
3
3 PFP QSR, 4/19/2011 Schedule Status EMs have made a lot of progress this month –All EM PWBs in test but ~2 (HVPS boards, in fab) –SEP, LPW, SWEA, MAG EM mechanical assembly complete –STATIC EM TDC complete random vibe –SWIA/STATIC analyzers parts out to fab EM Package I&T in progress –LPW, SEP, SWEA test with PFDPU complete –EM ‘Early Payload Test’ with LM complete –MAG next week –Pushing to complete before CDR –EM Instrument calibrations don’t complete till after Package I&T STATIC is on critical path –13.6 weeks margin to delivery –Driven be delays in EM I&T Status at instrument CDR –SWIA, STATIC EM will not be complete –SWIA, STATIC attenuator life test not done –SWIA, STATIC power converters may still be in test –Rest of instrument EM will be complete, with perhaps some system level test still in progress
4
4 PFP QSR, 4/19/2011 Manpower RBSP-EFW instrument still not delivered – this month? –A number of problems encountered in thermal vacuum –Resolving those problems have impacted MAVEN power converter team, delayed STATIC & SWIA We are still under planned FTE rate –but climbing a bit –Mostly due to people splitting time between projects Note that 100% activity is often more than 40 hours/week in these cases –Plan was based on conservative assumptions about covering people
5
5 PFP QSR, 4/19/2011 Accomplishments LPW, SEP, SWEA EM integrated with PFDPU EM PFDPU EM Early Payload test with Spacecraft EM SWEA Peer Review Completed STATIC Random Vibration Completed SEP Attenuator Life Test Completed More in instrument sections…
6
6 PFP QSR, 4/19/2011 Ongoing Work Supporting Project planning process Supporting EMC, Payload, SDT working groups Completing EM board testing Completing SWIA/STATIC EM mechanical part fabrication Complete PF Package EM I&T Prepare for CDR
7
7 PFP QSR, 4/19/2011 EM Status
8
8 PFP QSR, 4/19/2011 PFP RFA Status All Done!
9
9 PFP QSR, 4/19/2011 Trades, Issues HV801 issue still open –Current plan is to buy HV801s from LADEE NMS, who has parts on order they no longer need. –We still don’t have the parts in hand Working on an analysis to decide if the PFDPU mechanical design needs to be augmented to support the PWBs to avoid excessive displacements in vibe –Analysis complete, passed on to GSFC expert for review. LPW Stacer Plating issue (NEW) –After plating stacer with black Nickel it no longer stows properly –Need plating for thermal reasons (aeroheating, thruster heating) –Historically we have used a paint (DAG213), but that will not survive atomic oxygen at Mars –Working with GSFC Materials on possible solutions
10
10 PFP QSR, 4/19/2011 Thermal Status Received ‘Thermal Memos’ as well as spacecraft thermal model Some of the instruments are in trouble according to the thermal memo –For example, STATIC goes to -100C We are working on identifying if the issue is the model or the design –Our preliminary results are more benign
11
11 PFP QSR, 4/19/2011 Top Risks P-20 reduced (mating procedure)
12
12 PFP QSR, 4/19/2011 Risks List
13
13 PFP QSR, 4/19/2011 PFP Mass CCR262 approved to reallocate NTE amongst PFP
14
14 PFP QSR, 4/19/2011 Mass Tracking Chart
15
15 PFP QSR, 4/19/2011 PFP Power Small increase in MAG power Small decrease in SWEA power.
16
16 PFP QSR, 4/19/2011 PFP Power Trend
17
17 PFP QSR, 4/19/2011 PFP Data Rate Per 2009-6-9 allocations from Bruce New MAG requirements on telemetry formatting puts MAG 4% over allocation
18
18 PFP QSR, 4/19/2011 Requirements Verification Status CCR (265) to update PFP Functional Requirements (Level 3) approved –some old requirements need updating Verification matrix mostly complete –Have Functional, ERD, ICD requirements complete, in review Boot software verification has started –against software level 5 requirements, which link back to FRD and ICD. STATIC TOF EM Acoustics and Vibration test complete –All but coarsest grid with thinnest foils passed –Will not use coarsest grids –Will repeat on full EM and FM EM Interface tests started –Reduces risk, not a qualification test SEP Attenuator Mechanism Life Test complete
19
19 PFP QSR, 4/19/2011 Life Testing SEP Attenuator life test complete –4100 cycles on EM twice expected life –~1000 in air, ~3000 in vacuum –Will collect some more cycles over the next few months SWIA, STATIC attenuator life test pending completion of EM attenuator –~June SWEA door mechanism identical to STEREO SWEA, STATIC door mechanism functional, life test pending LPW relay life test expected to start soon LPW deployment life test expected to start soon –Stacer coating problem holding that up
20
20 PFP QSR, 4/19/2011 MAVEN Magnetometer Status April 2011 Connerney, Sheppard, Schnurr, Oliversen, Espley, etc.
21
21 PFP QSR, 4/19/2011 GSFC/MAG - Accomplishments Last Month EM sensor assembly, pigtail, GSE sensor harness completed. Breakout PWBs fabrication completed. Draft MAG Flight Software Requirements Specification (for PFDPU). Completed Safe-to-Mate procedures for MAD board (MAVEN-MAG- PROC-0026). Completed EM Magnetometer board scale factors calibration at GSFC 22’ MAG Test Site; scale factor resistors installed on board. FPGA (rev 0) burned at Aeroflex, received and installed on MAD board. Functional testing in progress. GSE (UCB emulator) development continues; CMD and TLM successfully flowing between GSE and MAD board. Sensor non-magnetic heaters design received from vendor (Tayco), under review. Frames for MAD board and ACHE board fabricated at GSFC; boards installed in frames (see pix).
22
22 PFP QSR, 4/19/2011 GSFC/MAG - Accomplishments Last Month A/C Heater Electronics (ACHE) Board in frame -> MAG Analog and Digital (MAD) Board & frame
23
23 PFP QSR, 4/19/2011 GSFC/MAG Near Term Plans & Open Issues Mature MAG software requirements draft w/UCB. Hypertronics KPC120 connectors installation and mating issues. Radiation test plan for MIL spec CD4066 quad bilateral switches completed; testing scheduled to begin April 18, 2011. Integration and test of MAG (MAD board and sensor) w/ PFDPU at UCB scheduled April 26-28, 2011. MAD board frame modifications (test connector placement, mechanical mod for center board support) pending final approval. Continue winding FM sensor ring cores, feedback/sense bobbins, and magnetic piece parts per technician availability; fabricate sensor assembly terminal boards. Draft worst case analysis of MAD board. MAG Peer Review scheduled for May 5, 2011 @ GSFC. Workload: RBSP FM post-environmental test evaluation drags on; Juno FM system integration work in progress @ Astrotech, KSC.
24
24 PFP QSR, 4/19/2011 MAVEN PFP SWIA Status April 2011 Jasper Halekas, SWIA Lead
25
25 PFP QSR, 4/19/2011 SWIA Progress Electrical Progress –Anode and digital boards tested –Preamp/MCP loaded on preamp half Preamp half integrated and in testing with digital MCP half delayed by RBSP –LVPS mostly loaded, waiting for testing, delayed by RBSP –Sweep in testing Mechanical Progress –E-Box fabricated and assembled –Analyzer in progress Many major parts already out for fabrication Final drawings being finished up Detector Progress –MCPs in testing Early results using spare THEMIS plates indicate anode board working nominally
26
26 PFP QSR, 4/19/2011 SWIA EM Electronics & Chassis
27
27 PFP QSR, 4/19/2011 SWIA Issues Staffing/Schedule –More RBSP delays hurting mechanical and power supplies –Mechanical parts may not all be done in time for peer reviews –Power supplies waiting for loading and testing
28
28 PFP QSR, 4/19/2011 SWIA Test Data 1 2 3 45 6 7 8 9 10 11 12 13 14 15 21 22 23 17 18 19 16 2024 Anode counts from integrated test pulser correctly counted P0, P1, P2 data products correctly generated by FPGA Test pulser output divided by four ratios, sent to alternating anodes Pseudo Data Products 3-d Sky Plot Energy Spectra
29
29 PFP QSR, 4/19/2011 MAVEN PFP SWEA Status April 2011 Dave Mitchell, SWEA Lead
30
30 PFP QSR, 4/19/2011 SWEA Status – IRAP (CESR) Mechanical –Plating of external parts (Black-Ni, Gold, Alodyne) at Anoplate in New York. Most parts delivered to SSL on 4/5 and passed magnetic screening ( 10-Gauss magnetizing field) Black-Ni/Gold parts (lower deflector and interface tube) are delayed (expected 4/25) Mechanical assembly at IRAP delayed ~3 weeks Electrical: Amp, HV coupling, and HVPS boards assembled at Microtec – expecting delivery at IRAP on 4/19, then functional testing can begin. AIT: Facilities in large clean room are in progress as scheduled (installed rolling table and tools, vacuum chamber expected week of 4/18) on schedule for AIT Magnetic screening station at SSL SWEA parts plated with high-P electroless black-Ni top cover upper deflectortoroidal grid 10 cm
31
31 PFP QSR, 4/19/2011 SWEA Status, EM - SSL Mechanical: No change from last month: Pedestal fabrication and test fitting complete, ready to assemble when boards available LVPC: Some voltages not within spec, and one exhibits and oscillation. Board will be reworked (~2-3 weeks). Digital LVPS STEREO SWEA EM front-end boards SWEA Electronics I&T Digital: –Fab complete and tested. –Housekeeping and Data messages from FPGA verified. –Test pulser demonstrates that counters working as expected. –Integration with PFDPU EM and functional tests on 4/13 successful
32
32 PFP QSR, 4/19/2011 MAVEN PFP STATIC Status April 2011 Jim McFadden, STATIC Lead
33
33 PFP QSR, 4/19/2011 STATIC Accomplishments Carbon foils mounted in TOF units survive vibration test – automated software used to evaluate foil breakage Ordered carbon foils on mica slides to improve mounting yield The design of START foil grid-frames was modified to compensate for poor clamping due to fabrication tolerances - new grid-frames ordered. Design of attenuator motor completed, drawings for ETU in process Energy analyzer/deflector parts drafted and ordered EM TDC board bench testing complete, part modifications made EM preamp 1 modified and working adequately for integration w/ TDC board – will be used while optimized preamp board is developed EM Anode, Preamp and TDC boards integrated – working EM Digital board passed power and PFDPU simulator interface testing, ready for interface test with TDC EM Sweep HV board partly loaded and in test (see pictures) Clean room equipment installed – racks, SS table, GN2 purge, etc. Helmholtz coil template fabricated, waiting on welding before assembly
34
34 PFP QSR, 4/19/2011 STATIC EM Sweep HV Board
35
35 PFP QSR, 4/19/2011 STATIC Open Issues One of two TOF electrical connections broke in 1 of the 3 units during vibration test (see pics) – connection redesigned for stress relief Mounting fixtures for handling flight carbon foil frames need to be fabricated before additional EM carbon foils are loaded New START foil grid-frames will require inspections after fabrication Preamp design changes nearly complete for optimal dynamic range – may require new layout EM 15kV-MCP board changed, MCP “stack stick” multiplier abandoned in favor of a pair of VMI multipliers and a tapped transformer – EM waiting on part placement changes (Berg). Digital board FPGA still in development EM LVPS loaded – waiting to be tested Manipulator fixtures for calibration chamber testing in development Some test harnesses and test cables still on order New calibration chamber ordered – delivery late May SS sink for clean room assembled – waiting for drain assembly
36
36 PFP QSR, 4/19/2011 STATIC EM TOF Post Vib Disassembly
37
37 PFP QSR, 4/19/2011 Post-vib broken electrical connection
38
38 PFP QSR, 4/19/2011 Post-vib broken electrical connection
39
39 PFP QSR, 4/19/2011 MAVEN PFP SEP Status April, 2011 Davin Larson, SEP Lead
40
40 PFP QSR, 4/19/2011 SEP Accomplishments 2011-04-12 Mechanical attenuator tests completed –~4500 cycles completed (all but ~1000 in vacuum) Integration of DAP board (& ½ sensor sans detectors) with PFDPU begun on 2011-04- 11 –Safe to mate –ok –Initial power on - ok but receiving +6V and -6.3 volts instead of nominal +/- 5V –Command test – ok Successfully turned on test pulser Bias voltage setting not working (not yet functional on DAP? –Telemetry tests – ok Successful run of ‘SEP_DAPINIT’ Unbalanced analog voltages result in offset from baseline Successful run of “SEP_THRESH_SWEEP” Successful run of “SEP_TPSWEEP” –Some cross talk visable that was not seen with MISG –Noise level is substantially larger and assymetric –Timing Tests – skipped –SEP Aperture tests – ok –SEP auto aperture closure – problem on REG –SEP power inrush current test - OK ETU Silicon detectors (1 stack) delivered on 2011-04-12. DAP board –3 channels loaded on DAP #1 –12 channels loaded on DAP #2 –Actel programming: Using FPGA version 0x32
41
41 PFP QSR, 4/19/2011 SEP PFDPU Interface Test Data Cross talk? Dropouts? Data collected through PFDPU in APID 30 Increased noise (and asymmetric)
42
42 PFP QSR, 4/19/2011 Attenuator life test Life tests were done on 3 separate days. TCP/IP connection from computer to MISG was unreliable. Difference in actuation time is probably temperature related.
43
43 PFP QSR, 4/19/2011 Attenuator Stroke vs. bus voltage Tested the range of bus voltages that would cause actuation. Below 22 V (2.08 V across nanomuscle), actuation failed in air.
44
44 PFP QSR, 4/19/2011 SEP Open issues What voltage to use for +/- 5VA supply. –Analog supply NOT currently regulated –Need secondary regulation for A250? –Eliminate requirement of 5V Digital altogether Mods needed for flight DAP board: –Use faster transisters on pulse generator (fixes 3.3 volt logic problem) –Use 2.5V reference instead of 5VA for baseline trim –Use Valid signal for hysteresis on peak detect –Gain change on peak detect circuit (perhaps not needed now) –Switch from 10 MΩ to 1MΩ resister on bias voltage control –5 MΩ resistor to -5VA (-2.5R?) to correct for OpAmp input current (this mod is questionable if BLRena mode is working properly) Sensor –Add detectors!!!! –Insert caps on attenuator lines to clean up some noise FPGA Mods from version 0x32 –Eliminate secondary pulse by applying BLRena for 6 μsec on test pulse return –Extend test pulse duration from 10 μsec to 20 μsec –16 bit counters on no peak counters –Ability to turn off housekeeping measurement –Event mode resolution Testing: –Purchase new nimbin and test pulser to replace AWOL test pulser –Test for correct coincidence determination with FPGA –New radiation source PFDPU testing –Cross talk observed in PFDPU but not MISG? –Increased Noise observed in PFDPU (probably resolved with shield boards) –Telemetry dropouts from PFDPU science packets –Possible change in opto coupler wiring of actuator control on DCB to eliminate any possibility of noise Baseline shift at high count rates – (probably not an issue) 1 mv shift in baseline shortly after the 1 pps signal More to come
45
45 PFP QSR, 4/19/2011 MAVEN PFP DCB, Power Converter & GSE Status April 2011 Dorothy Gordon Timothy Quinn Peter Berg Chris Tiu
46
46 PFP QSR, 4/19/2011 PFDPU/DCB Status PFDPU Overall Integration oDCB/REG oFunctional and electrical verification ongoing oActuator Control, Housekeeping, Instrument Current Monitoring oDCB/REG/IIB oVerified LPW signal routing through IIB and Low Voltage Power Supply oDCB/REG/IIB/LPW (see next page) oUpcoming PFDPU integration tests oRemaining power services and signal routing to be checked on a per instrument basis
47
47 PFP QSR, 4/19/2011 PFDPU/DCB Status (2) oDCB/REG/IIB/LPW oTested/Verified oPower-switch, current monitoring on REG oOperation of LPW via the Supplies IIB LVPS oLPW/DCB Interaction via serial interface oOperation of the EUV Door Actuator oLPW Data analyzed for noise and anomalies 10 Hz – 4Vpk-pk1KHz – 4Vpk-pk100KHz – 4Vpk-pk
48
48 PFP QSR, 4/19/2011 PFDPU/DCB Status (3) PFDPU – S/C Interface Test oDCB/REG Verification at Lockheed-Martin oIntegrated power subsystem oInrush current characterized oTested S/C Discrete commands and Side Select oReset, TIME commands verified oOperated PFDPU with the Lockheed-Martin Spacecraft Emulator oVerified signal protocol of RS422 command and telemetry interfaces oOperation with Flight Software – sent a variety of packets in order to work through the checksum generation algorithm. FSW is working this issue with Lockheed-Martin.
49
49 PFP QSR, 4/19/2011 DCB Status DCB ETU Build o DCB ETU #2 Build complete o Delivered (along with FLASH FPGA daughter board) o Short on main DCB power supply (3.3V) o Problem needs to be identified and fixed DCB FPGA o Changes added to support the S/C interface modifications o Functional design is complete; undergoing life-test with flight software and PFDPU Integration
50
50 PFP QSR, 4/19/2011 GSE Hardware Status MISG Instrument Simulator o First cut operational instrument simulator delivered o uses the MISG-FPGA Block RAM o Implements the final Instrument Mode functionality o covers all 8 Instrument Interfaces o with a subset of the final pattern generator buffer space o Next Steps o Use MISG based SDRAM for Instrument Pattern storage (allowing for increased buffer space) o Incorporate new modules into next MISG-FPGA release
51
51 PFP QSR, 4/19/2011 GSE Software Status SSG –Software updated to handle special case where calculated checksum equals zero. When this occurs checksum is set to 0xFFFF GSEOS –Python modules added to perform checksum processing and verification on PFDPU telemetry –Python module added to support PFDPU Memory Loads –Delivered first rev of STATIC configuration –Created Python module for playing back raw data over TCP link with GSEOS –Supported LPW EM integration testing
52
52 PFP QSR, 4/19/2011 Power Converter Status (1) REG Board We are working on a second PCB layout for the REG board ETU#2 due to a connector mis-wiring issue on the first layout. This re-layout process has begun. The REG board tester was built and is now in operation All REG based switchable services have been tested Still pending: adjustment/tuning of the current monitoring subsystem; complete verification of the digital portion of the circuit REG Board system checkout via PFDPU I/F Tests DCB Interface/Housekeeping addressing Instrument Power Switches
53
53 PFP QSR, 4/19/2011 Power Converter Status (2) IIB board All power converter sections of the EM board have been tested with only the magnetics of MAG2 and off board connectors for STATIC, SWIA, and MAG left to be populated. (This excludes the MAG HEATER daughter boards from Goddard that are to be mounted on the IIB at a later date.) The ±90V outputs on the LPW section sat at 114V when integrated with the system. This would indicate an unloaded state as the voltage would normally drop closer to ±90V when loaded (10mA peak). The 5VD regulator on the SEP section will be changed to an LDO as the actual load is much lower with the system. The LTC1877 may have stability issues with such a low load. ACTEL turn-off delay circuit for the LPW section will be added and tested on the EM board. Optimization for noise, efficiency, and voltage levels will also be done after and in between integration.
54
54 PFP QSR, 4/19/2011 Concerns/Issues PC104 Connectors –One of the Hypertronics PC104 connectors delivered to us appear to have been assembled incorrectly –Connectors are very fragile, pins have bent and even broken during our ETU testing We have implemented a mating procedure to mitigate this issue –We still need to verify the connection insertion is met with the boards installed in their frames Schedule –Schedule for testing is tight –As the integration progresses, we are finding issues that require resolution (e.g. power supply regulation, clock distribution). We need time to sort through all the open-items (hopefully prior to CDR) yet the individual subsystem testing/tuning is still ongoing.
55
55 PFP QSR, 4/19/2011 MAVEN PFP Flight Software Status April 12 2011 Peter Harvey
56
56 PFP QSR, 4/19/2011 Boot Status Interface Documents, Meetings Reviewed PFEPTPlan. IV&V 3/31/11 Discussion confirmed Boot Requirements OK FSW Development Added temporary diagnostic outputs to support PFEPTPlan at LM Removed automatic safing sequence since S/C will not be sending ZoneAlerts “Inverted” checksum logic w/ no-0000 allowed logic added to CMD and TM Test Status All Boot Packets are Displayed in RealTime, Hot Buttons installed Retested with DCB FPGA update revision 07 and 08 PF-Spacecraft Simulator (PFEPT) test support at LM CMD Rate Test to be Repeated when GSEOS can support it Formal Test Scripts to be Developed Module tests Comprehensive Performance Dates coming up August - PROM Burn
57
57 PFP QSR, 4/19/2011 Operational Status Interface Documents, Meetings Reviewed DFB specification rev J – OK. Implemented changes to IO regs Reviewed SEP specifications rev B, C, D – OK. Supported SEP.c development Reviewed “MAG software requirements” – Not OK. Conflicts with FSW-010 IV&V Reviewed IV&V comments w.r.t Operational - OK FSW Development SSR - Developed Generic Message-APID software for I&T tests (SEP,SWEA,SWIA, STA) Wrote MAG Build1 & Build2 software (before requirements change) Wrote SEP Build1 * Wrote STATIC, SWEA, SWIA Build1 software Test Status LPW, SSR(RealTime) simulations completed LPW EM I&T test support MAG simulations completed SEP Build1 simulations complete, SEP Build1 DCB/REG/IIB/SEP EM I&T complete STA Build1 simulation – 50% complete. AHSK to be done SWIA, SWEA Build1 simulations to be done shortly. Important Dates coming up April 11 2011 – Interface test with SEP April 13 2011 – Interface test with SWEA April 27 2011 – Interface test with MAG *: Build1 supports ETU-level I&T tests
58
58 PFP QSR, 4/19/2011 Test Environment GSEOS Status: Generally functional though issues internal error messages, and crashes periodically Added APID 11 (Memory Loads) Needs Zone Alerts (for compatibility) Needs 30 ms delay between messages (per ICD) Limit checking error messages (uses raw values, not converted) Updated New Checksum needs to be checking all telemetry GSEOS Python Test Scripts, Displays Developed SEP, SWEA, SWIA, STATIC EMIT Test scripts Included/modified SEP HSK displays for EMIT test Include/modify SWEA HSK displays for EMIT test Include/modify SWIA HSK displays for EMIT test Include/modify STATIC HSK displays for EMIT test MAG has not updated scripts, HSK display (according to SVN) FSW Development Platform: DCB EM2 Built, tests are in progress Regulation board built Instrument Simulator Functional Test Scripts for Instrument Simulation being built ( LPW, SEP tested so far) PROM emulator ESD mat, wrist-straps etc installed in Rm 124 (my office)
59
59 PFP QSR, 4/19/2011 Documentation
60
60 PFP QSR, 4/19/2011 Metrics Chart
61
61 PFP QSR, 4/19/2011 Margin Chart
62
62 PFP QSR, 4/19/2011 Fever Chart 1.MAG delivered a completely new version of software requirements, conflicting with implemented software.