Transiting Exoplanet Survey Satellite Daryl Swade September 24, 2014 TESS DMS Management Meeting
2
Agenda TESS Archive Overview Contract Current Status Schedule Deliverables Testing plan Path to CDR
3
Functional Architecture
4
Archive Operations Assumption: TESS data products will be similar to Kepler data products TESS monthly processing (Kepler quarterly) Transferred from SPOC via hard drive TESS archive data volume – 50 TB/year (to be refined) Total Kepler archive data volume – 19 TB (Q0-Q17) Does not consider reprocessed Kepler data No proprietary period on data Availability depends primarily on SPOC processing time (<1 month) Primary TESS web site hosted by MIT Links to MAST web site
5
MAST Interfaces
6
Archive System Enhancements for TESS
7
TESS Contract - Cost Total: $766K for Archive Development and Operations
8
TESS Contract - Labor
9
FY15 Effort
10
Status Systems Engineering Drafted TESS Archive Operations Concept Drafted SPOC-MAST ICD Drafted TSO-MAST ICD Archive Peer Review June 18, 2014 @ NASA/Ames 1 Archive RFA Mission PDR September 9-2, 2014 @ MIT No known Archive issues
11
Archive Peer Review RFA Work with the TSO and the SPOC to find a meaningful way of presenting for public consumption the data products that MAST does not hold for Kepler. Threshold Crossing Events Data Validation Reports TESS Objects of Interest lists Follow-up Observation data To be closed by CDR
12
Archive Development Schedule Phase B ( April 1, 2014 – October 1, 2014 ) Continue developing TESS Archive Operations Concept Continue developing TESS-MAST ICD Work with SPOC to develop SPOC-MAST ICD section Work with TSO to develop TSO-MAST ICD section Continue to participate in Ground Segment Monthly Technical Reviews Participate in TESS Mission PDR (September 2014) Phase C ( October 2, 2014 – November 29, 2016) Develop TESS specific archive components based on Archive Operations Concept and TESS-MAST ICD Participate in TESS Mission CDR Participate in Ground Segment testing Phase D ( November 30, 2016 – July 17, 2017) Develop TESS Archive User’s Guide
13
MAST Deliverables DeliverableResponsibilityPhaseDate of Delivery TESS Archive Operations ConceptSystems EngineerBPDR TESS-Archive ICD SPOC-Archive TSO-Archive Systems EngineerB/CPDR/CDR Archive ArchitectureSystems EngineerCCDR Archive Catalog Design SpecificationDatabase EngineerCCDR Archive Software DesignSoftware EngineerCCDR TESS Archive User InterfaceSoftware EngineerC/DCDR/GS Test Archive Test ProceduresSystems EngineerDGS Test Archive Operations ProceduresArchive OperatorDLaunch TESS Archive User’s GuideArchive ScientistELaunch
14
Testing Plan MAST will work with the SPOC and TSO to develop test data. MAST will participate in Ground Segment end-to-end tests. GSIT 1: July 2015 GSIT 2: June-July 2016 End-to-end Test: October-November 2016 GSIT 3: May 2017
15
Path to CDR Mission CDR currently scheduled for April 2015 Systems Engineering Complete TESS Archive Architecture Data Receipt and Ingest Data Storage Options Work with SPOC to complete SPOC-MAST section of TESS-MAST ICD Work with TSO to complete TSO-MAST section of TESS-MAST ICD Archive Software Development Archive Catalog Schema Archive User Interface Prototype