www.enex.is Application of decision theory to the procurement of a geothermal power plant April 2nd 2008 Viktor Þórisson
2
www.enex.is Presentation Overview 1.Company overview & background 2.What is geothermal energy? 3.Definition of the project 4.Application of @risk and precision tree in this project
3
www.enex.is Company Overview Export of Icelandic Geothermal Know-how Development of geothermal potential for electrical generation and direct use. Reliance on comprehensive know-how and operational experience. Founded in 1969 by the main geothermal consultancies in Iceland to export the Icelandic geothermal consulting. What we do Feasibility Studies & Business Plans Project Management Engineering Construction & Commissioning Operation
4
www.enex.is What is geothermal energy?
5
www.enex.is What is geothermal? The thermal energy stored within the earth's crust is collectively called geothermal energy. Faults and fractures develop where the earth crust is unstable or is moving, most commonly in areas of active volcanism.
6
www.enex.is What is geothermal? In areas of active volcanism, the upper crust is frequently intruded by hot magmatic intrusions. These intrusions move heat from the inner parts of the earth towards the outer crust. They are the prime force that usually drives geothermal systems. In some parts of the world hot rock formations within the crust contain water, which is the ideal medium for carrying this energy up to the earth's surface in a useful form.
7
www.enex.is Simplified geothermal power plant cycle
8
www.enex.is Waste water bathing
9
www.enex.is Main factors affecting the profitability Temperature of reservoir (or enthalpy) Flow from well (or production index) Depth of well Chemical conditions of the brine
10
www.enex.is Definition of the project Decision tree to answer the question: In a geothermal project. When to procure the critical components with the longest lead time for a power plant, after last drilling, before first drilling or somewhere in between?
11
www.enex.is The project chart if components are ordered after drilling
12
www.enex.is Main trade offs in the model are Benefit:Trade-off: Shorter time until plant is operational. More information available when components are ordered and thus optimizing the efficiency of the plant The risk of higher investment cost than necessary due to over dimensioning of the turbine. Potential higher costs if project results in no go after drilling and thus order cancellation fees of components are incurred.
13
www.enex.is Overview of the tree
14
www.enex.is Probabilities, methodology (1-cummulative distribution)
15
www.enex.is Fitted distributions
16
www.enex.is Definition of failure
17
www.enex.is Probability of failure first drilling Probability of failure due to reasons other than geological is defined as 5%. Probability of success first drilling is therefore: 89,26% * 95% = 84,9%
18
www.enex.is Probability of success second drilling
19
www.enex.is Given success first drilling
20
www.enex.is Results from simulation, probability of failure of the project, given success/given failure first drilling.
21
www.enex.is Potential plant size Mean plant size 13,8 MW given success first drilling. Example of Possible values: TPI 1651,5 1602,1
22
www.enex.is The newsboy problem C O * P O = C U * P U
23
www.enex.is Sensitivity of production to flow
24
www.enex.is Other costs Cost of over sizing (C O ) 500.000 EUR/MW unnecessary investment cost. Cost of under sizing (C U ) Expected cancellation fee of turbine.
25
www.enex.is The optimal path
26
www.enex.is Sensitivity of costs
27
www.enex.is Sensitivity of costs
28
www.enex.is 2 way decision analyze of costs
29
www.enex.is Sensitivity of probabilities
30
www.enex.is 2 way decision analyze of probabilities
31
www.enex.is Thank you